DFARS 252.247-7002 Revision of prices.
In plain English: This clause lets either the Contracting Officer or the contractor demand renegotiation of contract prices when wages or working conditions change, but only in limited ways: a wage adjustment must be generally applicable to the port area, affect contract cost substantially, and apply to the contractor's non-government work too. Demands are limited in timing, the contractor must submit detailed cost data, and disagreements go to the Disputes clause while the existing prices stay in effect. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 247.270-4(b), which says when contracting officers use it.
Last amended 2019-06-28 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.247-7002 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.247-7002 · Ask the AI chat about it
In more detail
Applies to: contractors performing services under a contract that includes this clause, typically port-area work
What it requires
- Submit a new estimate and cost breakdown, an explanation of differences from the prior estimate, supporting operating and cost data, and actual costs to date when a price revision is demanded
- Request a price adjustment within 30 days of any retroactive wage adjustment, supported by an estimate, complete supporting information, and a certified copy of the agreement or award
- Notify the Contracting Officer in writing within 20 days of any employee request that may result in a retroactive wage adjustment
- Continue performance even if the parties fail to agree on revised prices
Key terms: wage adjustment · revision of prices · demand for negotiation · retroactive wage adjustment · effective date of the price revision
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 247.270-4(b), use the following clause:
Revision of Prices (DEC 1991)
(a) Definition. Wage adjustment, as used in this clause, means a change in the wages, salaries, or other terms or conditions of employment which—
(1) Substantially affects the cost of performing this contract;
(2) Is generally applicable to the port where work under this contract is performed; and
(3) Applies to operations by the Contractor on non-Government work as well as to work under this contract.
(b) General. The prices fixed in this contract are based on wages and working conditions established by collective bargaining agreements, and on other conditions in effect on the date of this contract. The Contracting Officer and the Contractor may agree to increase or decrease such prices in accordance with this clause.
(c) Demand for negotiation. (1) At any time, subject to the limitations specified in this clause, either the Contracting Officer or the Contractor may deliver to the other a written demand that the parties negotiate to revise the prices under this contract.
(2) No such demand shall be made before 90 days after the date of this contract, and thereafter neither party shall make a demand having an effective date within 90 days of the effective date of any prior demand. However, this limitation does not apply to a wage adjustment during the 90 day period.
(3) Each demand shall specify a date (the same as or subsequent to the date of the delivery of the demand) as to when the revised prices shall be effective. This date is the effective date of the price revision.
(i) If the Contractor makes a demand under this clause, the demand shall briefly state the basis of the demand and include the statements and data referred to in paragraph (d) of this clause.
(ii) If the demand is made by the Contracting Officer, the Contractor shall furnish the statements and data within 30 days of the delivery of the demand.
(d) Submission of data. At the times specified in paragraphs (c)(3)(i) and (ii) of this clause, the Contractor shall submit—
(1) A new estimate and breakdown of the unit cost and the proposed prices for the services the Contractor will perform under this contract after the effective date of the price revision, itemized to be consistent with the original negotiations of the contract;
(2) An explanation of the difference between the original (or last preceding) estimate and the new estimate;
(3) Such relevant operating data, cost records, overhead absorption reports, and accounting statements as may be of assistance in determining the accuracy and reliability of the new estimate;
(4) A statement of the actual costs of performance under this contract to the extent that they are available at the time of the negotiation of the revision of prices under this clause; and
(5) Any other relevant data usually furnished in the case of negotiations of prices under a new contract. The Government may examine and audit the Contractor's accounts, records, and books as the Contracting Officer considers necessary.
(e) Negotiations. (1) Upon the filing of the statements and data required by paragraph (d) of this clause, the Contractor and the Contracting Officer shall negotiate promptly in good faith to agree upon prices for services the Contractor will perform on and after the effective date of the price revision.
(2) If the prices in this contract were established by competitive negotiation, they shall not be revised upward unless justified by changes in conditions occurring after the contract was awarded.
(3) The agreement reached after each negotiation will be incorporated into the contract by supplemental agreement.
(f) Disagreements. If, within 30 days after the date on which statements and data are required pursuant to paragraph (c) of this clause, the Contracting Officer and the Contractor fail to agree to revised prices, the failure to agree shall be resolved in accordance with the Disputes clause of this contract. The prices fixed by the Contracting Officer will remain in effect for the balance of the contract, and the Contractor shall continue performance.
(g) Retroactive changes in wages or working conditions. (1) In the event of a retroactive wage adjustment, the Contractor or the Contracting Officer may request an equitable adjustment in the prices in this contract.
(2) The Contractor shall request a price adjustment within 30 days of any retroactive wage adjustment. The Contractor shall support its request with—
(i) An estimate of the changes in cost resulting from the retroactive wage adjustment;
(ii) Complete information upon which the estimate is based; and
(iii) A certified copy of the collective bargaining agreement, arbitration award, or other document evidencing the retroactive wage adjustment.
(3) Subject to the limitation in paragraph (g)(2) of this clause as to the time of making a request, completion or termination of this contract shall not affect the Contractor's right under paragraph (g) of this clause.
(4) In case of disagreement concerning any question of fact, including whether any adjustment should be made, or the amount of such adjustment, the disagreement will be resolved in accordance with the Disputes clause of this contract.
(5) The Contractor shall notify the Contracting Officer in writing of any request by or on behalf of the employees of the Contractor which may result in a retroactive wage adjustment. The notice shall be given within 20 days after the request, or if the request occurs before contract execution, at the time of execution.
(End of clause)
Sections it refers to
- 247.270-4 Contract clauses.
Sections that refer to it
- 247.270-4 Contract clauses.
Related DFARS 252.247 sections
- 252.247-7000 Hardship conditions.
- 252.247-7001 [Reserved]
- 252.247-7003 Pass-Through of Motor Carrier Fuel Surcharge Adjustment To The Cost Bearer.
- 252.247-7004—252.247-7006 [Reserved]
- 252.247-7007 Liability and insurance.
- 252.247-7008—252.247-7013 [Reserved]
- 252.247-7014 Demurrage.
- 252.247-7015 [Reserved]
- 252.247-7016 Contractor liability for loss or damage.
- 252.247-7017—252.247-7021 [Reserved]
- 252.247-7022 [Reserved]
- 252.247-7023 Transportation of Supplies by Sea.
← 252.247-7001 [Reserved] · 252.247-7003 Pass-Through of Motor Carrier Fuel Surcharge Adjustment To The Cost Bearer. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.