FAR 28.102-3 Contract clauses.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section tells contracting officers which bond-related clauses to put into construction solicitations and contracts based on expected contract value. It matters to contractors because it determines whether performance and payment bonds or alternative payment protections will be required, and at what dollar thresholds.

Applies to: Construction solicitations and contracts

Key terms: Performance and Payment Bonds—Construction · Alternative Payment Protections · performance and payment bonds · payment protections · contracting officer

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) Insert a clause substantially the same as the clause at 52.228-15, Performance and Payment Bonds—Construction, in solicitations and contracts for construction that contain a requirement for performance and payment bonds if the resultant contract is expected to exceed $150,000. The contracting officer may revise paragraphs (b)(1) and/or (b)(2) of the clause to establish a lower percentage in accordance with 28.102-2(b). If the provision at 52.228-1 is not included in the solicitation, the contracting officer must set a period of time for return of executed bonds.

(b) Insert the clause at 52.228-13, Alternative Payment Protections, in solicitations and contracts for construction, when the estimated or actual value exceeds $35,000 but does not exceed $150,000. Complete the clause by specifying the payment protections selected (see 28.102-1(b)(1)) and the deadline for submission. The contracting officer may revise paragraph (b) of the clause to establish a lower percentage in accordance with 28.102-2(c).

Sections it refers to

Sections that refer to it

  • 52.228-13 Alternative Payment Protections.
  • 52.228-15 Performance and Payment Bonds—Construction.

← 28.102-2 Amount required. · 28.103 Performance and payment bonds for other than construction contracts. →

Rule changes for FAR Part 28

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.