FAR 41.301 Requirements.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section tells agencies how and where to send requests for GSA contracting authority or assistance with utility service contracts, including the specific information that must accompany those requests. It matters to contractors because it sets the timing and content requirements for utility acquisition requests, such as the 120-day advance submission for contracting assistance.
Applies to: Agencies requesting GSA contracting authority or assistance for utility services
What it requires
- Send requests for GSA contracting authority or assistance to the GSA region where service is required
- Submit requests for utility contracting assistance no later than 120 days before new services must start or an existing contract expires
- Include a technical description or specification of the type, quantity, and quality of service required, and a delivery schedule
- Provide the required information for new or existing utility service requirements as applicable
Key terms: delegations of GSA contracting authority · utility services · technical description or specification · delivery schedule · connection charge
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Requests for delegations of GSA contracting authority, assistance with a proposed contract as provided in 41.203, and the submission of other information required by this part, shall be sent or submitted to the General Services Administration (GSA) region in which service is required. The names and locations of GSA regional offices are available from the General Services Administration, Energy Division—PMA, 1800 F St NW, Washington, DC 20405; website: www.gsa.gov/energy; Email: [email protected].
(b) Requests for contracting assistance for utility services shall be sent not later than 120 days prior to the date new services are required to commence an existing contract will expire. Requests for assistance shall contain the following information:
(1) A technical description or specification of the type, quantity, and quality of service required, and a delivery schedule.
(2) A copy of any service proposal or proposed contract.
(3) Copies of all current published or unpublished rates of the utility supplier.
(4) Identification of any unusual factors affecting the acquisition.
(5) Identification of all available sources or methods of supply, an analysis of the cost effectiveness of each, and a statement of the ability of each source to provide the required services, including the location and a description of each available supplier's facilities at the nearest point of service, and the cost of providing or obtaining necessary backup and other ancillary services.
(c) For new utility service requirements, the agency shall furnish the information in paragraph (a) of this section and the following as applicable:
(1) The date initial service is required.
(2) For the first 12 months of full service, estimated maximum demand, monthly consumption, other pertinent information (e.g., demand side management, load or energy management, peak shaving, on site generation, load shaping), and annual cost of the service.
(3) Known or estimated time schedule for growth to ultimate requirements.
(4) Estimated ultimate maximum demand and ultimate monthly consumption.
(5) A simple schematic diagram or line drawing showing the meter locations, the location of the new utility facilities to be constructed on Federal property by the Federal agency, and any required new connection facilities on either side of the delivery point to be constructed by the utility supplier to provide the new services.
(6) Accounting and appropriation data to cover the required utility services and any connection charges required to be paid by the agency receiving such utility services.
(7) The following data concerning proposed facilities and related charges or costs:
(i) Proposed refundable or nonrefundable connection charge, termination liability, or other facilities charge to be paid by the agency, together with a description of the supplier's proposed facilities and estimated construction costs, and its rationale for the charge (e.g., tariff provisions or policies).
(ii) A copy of the acquiring agency's estimate to make its own connection to the supplier's facilities through use of its own resources or by separate contract. When feasible, the acquiring agency shall provide its estimates to construct and operate its own utility facilities in lieu of participating in a cost-sharing construction program with the proposed utility supplier.
(d) For existing utility service, the agency shall furnish GSA the information in paragraph (b) of this section and the following, as applicable:
(1) A copy of the most recent 12-months' service invoices.
(2) A tabulation, by month, for the most recent 12 months, showing the actual utility demands, consumption, connection charges, fuel adjustment charges, and the average monthly cost per unit of consumption.
(3) An estimate, by month, for the next 12 months, showing the estimated maximum demands, monthly consumption, other pertinent information (e.g., demand side management, load or energy management, peak shaving, on site generation, load shaping), and annual cost of the service.
(4) Accounting and appropriation data to cover the costs for the continuation of utility services.
(5) A statement noting whether the transformer, or other system components, on either side of the delivery point are owned by the Federal agency or the utility supplier, and if the metering is on the primary or secondary side of the transformer.
Sections it refers to
- 41.203 GSA assistance.
Sections that refer to it
← 41.206 Interagency agreements. · 41.401 Monthly and annual review. →
Rule changes for FAR Part 41
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 ↗ · proposed 2026-06-23 · comments due 2026-07-23
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.