FAR 42.803 Disallowing costs after incurrence.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section explains how costs can be disallowed after they have been incurred under cost-reimbursement, certain fixed-price, letter, time-and-material, and labor-hour contracts. It describes the procedures for handling vouchers, including when auditors may suspend or disapprove questionable costs, and it gives contractors a way to challenge those deductions.

Applies to: Cost-reimbursement contracts, the cost-reimbursement portion of fixed-price contracts, letter contracts that provide for reimbursement of costs, and time-and-material and labor-hour contracts.

What it requires

  • Contracting officers receiving vouchers directly from the contractor must approve or disapprove them in accordance with the normal procedures of the individual agency.
  • If authorized by agency regulations, the contract auditor must forward approved vouchers for payment to the cognizant contracting, finance, or disbursing officer, as appropriate under the agency's procedures.
  • If the auditor questions the allowability of a cost, the auditor may issue a notice of contract costs suspended and/or disapproved simultaneously to the contractor and the disbursing officer, with a copy to the cognizant contracting officer, for deduction from current payments.
  • If the contractor disagrees with the deduction, the contractor may submit a written request to the cognizant contracting officer to consider whether the unreimbursed costs should be paid and to discuss the findings with the contractor, or file a claim under the Disputes clause, or both.

Key terms: disallowing costs · cost-reimbursement contracts · letter contracts · time-and-material and labor-hour contracts · vouchers

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

Cost-reimbursement contracts, the cost-reimbursement portion of fixed-price contracts, letter contracts that provide for reimbursement of costs, and time-and-material and labor-hour contracts provide for disallowing costs during the course of performance after the costs have been incurred. The following procedures shall apply:

(a) Contracting officer receipt of vouchers. When contracting officers receive vouchers directly from the contractor and, with or without auditor assistance, approve or disapprove them, the process shall be conducted in accordance with the normal procedures of the individual agency.

(b) Auditor receipt of vouchers. (1) When authorized by agency regulations, the contract auditor may be authorized to (i) receive reimbursement vouchers directly from contractors, (ii) approve for payment those vouchers found acceptable, and (iii) suspend payment of questionable costs. The auditor shall forward approved vouchers for payment to the cognizant contracting, finance, or disbursing officer, as appropriate under the agency's procedures.

(2) If the examination of a voucher raises a question regarding the allowability of a cost under the contract terms, the auditor, after informal discussion as appropriate, may, where authorized by agency regulations, issue a notice of contract costs suspended and/or disapproved simultaneously to the contractor and the disbursing officer, with a copy to the cognizant contracting officer, for deduction from current payments with respect to costs claimed but not considered reimbursable.

(3) If the contractor disagrees with the deduction from current payments, the contractor may—

(i) Submit a written request to the cognizant contracting officer to consider whether the unreimbursed costs should be paid and to discuss the findings with the contractor;

(ii) File a claim under the Disputes clause, which the cognizant contracting officer will process in accordance with agency procedures; or

(iii) Do both of the above.

← 42.802 Contract clause. · 42.900 Scope of subpart. →

Rule changes for FAR Part 42

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 42.803 Disallowing costs after incurrence · SpendQuery