FAR and DFARS › FAR Part 48: Value Engineering › Subpart 48.1

FAR 48.101 General.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section explains value engineering, a formal technique for finding more economical ways to perform work. Contractors can either voluntarily propose cost-saving ideas and share in savings, or be required by the Government to run a value engineering program. It matters because it describes how contractors may save the Government money and potentially share in those savings.

Applies to: Government contractors, particularly those with contracts containing value engineering clauses

What it requires

  • If under a mandatory program, perform value engineering of the scope and level of effort required by the Government's program plan
  • If under a mandatory program, treat the value engineering effort as a separately priced item of work in the contract Schedule

Key terms: value engineering · value engineering change proposal (VECP) · incentive approach · mandatory program · sharing of savings

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) Value engineering is the formal technique by which contractors may (1) voluntarily suggest methods for performing more economically and share in any resulting savings or (2) be required to establish a program to identify and submit to the Government methods for performing more economically. Value engineering attempts to eliminate, without impairing essential functions or characteristics, anything that increases acquisition, operation, or support costs.

(b) There are two value engineering approaches:

(1) The first is an incentive approach in which contractor participation is voluntary and the contractor uses its own resources to develop and submit any value engineering change proposals (VECP's). The contract provides for sharing of savings and for payment of the contractor's allowable development and implementation costs only if a VECP is accepted. This voluntary approach should not in itself increase costs to the Government.

(2) The second approach is a mandatory program in which the Government requires and pays for a specific value engineering program effort. The contractor must perform value engineering of the scope and level of effort required by the Government's program plan and included as a separately priced item of work in the contract Schedule. No value engineering (VE) sharing is permitted in architect-engineer contracts. All other contracts with a program clause share in savings on accepted VECP's, but at a lower percentage rate than under the voluntary approach. The objective of this value engineering program requirement is to ensure that the contractor's value engineering effort is applied to areas of the contract that offer opportunities for considerable savings consistent with the functional requirements of the end item of the contract.

Sections that refer to it

← 48.001 Definitions. · 48.102 Policies. →

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 48.101 General · SpendQuery