FAR and DFARS › FAR Part 48
FAR Part 48: Value Engineering
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
In plain English
FAR Part 48 explains how contractors may propose value engineering change proposals (VECPs) that make a contract's work cheaper or more efficient without impairing essential functions, and how the Government shares the resulting savings with the contractor. It matters to small businesses because accepted VECPs can earn a share of acquisition and collateral savings, but the sharing rates, sharing periods, and acceptance decisions are set by the contracting officer under the contract's value engineering clause.
Key rules
- Value engineering is a formal technique under which contractors may voluntarily suggest more economical methods and share in the resulting savings, or may be required to run a value engineering program. (48.101)
- The voluntary incentive approach uses the contractor's own resources to develop VECPs, and the contract provides for savings sharing and payment of allowable development and implementation costs only if a VECP is accepted. (48.101, 48.001)
- The contracting officer must accept or reject a VECP within 45 days of Government receipt, or give written notice of the reasons and an anticipated decision date if more time is needed. (48.103)
- For supply and service contracts, acquisition savings are shared at rates set by contract type, clause or alternate used, and savings type, and the contractor's share of net acquisition savings is generally calculated and paid as each savings event occurs. (48.104-2)
- Collateral savings (reductions in agency operation, maintenance, logistic support, or Government-furnished property costs) are shared unless the head of the contracting activity finds that tracking them costs more than they are worth, and the contractor's share is capped. (48.104-3, 48.201)
- The sharing period for each VECP begins when the first affected unit is accepted and runs for a contracting-officer-set 36 to 60 months or to the last scheduled delivery date, whichever is later. (48.104-1)
- Benefits of an accepted VECP that are already rewarded under performance, design-to-cost, or similar incentives are not counted twice, and those incentive targets are not adjusted for the VECP. (48.105)
- The value engineering incentive clause (52.248-1) goes in supply and service solicitations and contracts above the simplified acquisition threshold, and the construction clause (52.248-3) goes in construction contracts above that threshold unless an incentive contract is contemplated. (48.201, 48.202)
Who does what
- Decide whether to accept or reject each VECP, document the file with the rationale, and notify the contractor in writing if more evaluation time is needed.
- Set the sharing period and sharing rate for each VECP and determine whether a no-cost settlement is in the Government's best interest.
- Consider degradation of performance, service life, or capability when measuring collateral savings.
- Prepare and submit VECPs using the instructions in the value engineering clause.
- Reimburse the Government for its proportionate share of savings payments if units are later rejected or not received after an accepted VECP.
- Establish and maintain cost-effective value engineering procedures and processes, and provide contractors a substantial financial incentive to submit VECPs.
- Establish guidelines for processing VECPs objectively and expeditiously, and provide contractors a fair share of accepted-VECP savings.
In practice
- Before proposing a change, check whether the contract's performance or design-to-cost incentives already reward the same benefit, since the savings may not be double-counted.
- Expect the Government to decide within 45 days, or to receive written notice of a longer review and an anticipated date; until a VECP is accepted by modification, perform under the existing contract.
- Track the units and delivery schedule affected by an accepted VECP, because savings shares are tied to accepted units and the sharing period end date.
Common pitfalls
- Assuming a VECP's savings are fully yours: sharing rates differ by contract type, savings type, and clause, and the contracting officer may set the rate within limits.
- Ignoring the reimbursement obligation: if the Government later rejects units or does not receive units on which a savings share was paid, the contractor must repay its proportionate share.
- Overlooking that collateral savings are capped and may not be shared at all if the head of the contracting activity finds tracking them is not worth the cost.
Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.
Subparts and sections
Subpart 48.1: Policies and Procedures
- 48.101 General.
- 48.102 Policies.
- 48.103 Processing value engineering change proposals.
- 48.104 Sharing arrangements.
- 48.104-1 Determining sharing period.
- 48.104-2 Sharing acquisition savings.
- 48.104-3 Sharing collateral savings.
- 48.104-4 Sharing alternative—no-cost settlement method.
- 48.105 Relationship to other incentives.
Subpart 48.2: Contract Clauses
← Part 47: TransportationPart 49: Termination of Contracts →
All FAR parts
- Part 1 Federal Acquisition Regulations System
- Part 2 Definitions of Words and Terms
- Part 3 Improper Business Practices and Personal Conflicts of Interest
- Part 4 Administrative and Information Matters
- Part 5 Publicizing Contract Actions
- Part 6 Competition Requirements
- Part 7 Acquisition Planning
- Part 8 Required Sources of Supplies and Services
- Part 9 Contractor Qualifications
- Part 10 Market Research
- Part 11 Describing Agency Needs
- Part 12 Acquisition of Commercial Products and Commercial Services
- Part 13 Simplified Acquisition Procedures
- Part 14 Sealed Bidding
- Part 15 Contracting by Negotiation
- Part 16 Types of Contracts
- Part 17 Special Contracting Methods
- Part 18 Emergency Acquisitions
- Part 19 Small Business Programs
- Part 22 Application of Labor Laws to Government Acquisitions
- Part 23 Environment, Sustainable Acquisition, and Material Safety
- Part 24 Protection of Privacy and Freedom of Information
- Part 25 Foreign Acquisition
- Part 26 Other Socioeconomic Programs
- Part 27 Patents, Data, and Copyrights
- Part 28 Bonds and Insurance
- Part 29 Taxes
- Part 30 Cost Accounting Standards Administration
- Part 31 Contract Cost Principles and Procedures
- Part 32 Contract Financing
- Part 33 Protests, Disputes, and Appeals
- Part 34 Major System Acquisition
- Part 35 Research and Development Contracting
- Part 36 Construction and Architect-engineer Contracts
- Part 37 Service Contracting
- Part 38 Federal Supply Schedule Contracting
- Part 39 Acquisition of Information Technology
- Part 40 Information Security and Supply Chain Security
- Part 41 Acquisition of Utility Services
- Part 42 Contract Administration and Audit Services
- Part 43 Contract Modifications
- Part 44 Subcontracting Policies and Procedures
- Part 45 Government Property
- Part 46 Quality Assurance
- Part 47 Transportation
- Part 48 Value Engineering
- Part 49 Termination of Contracts
- Part 50 Extraordinary Contractual Actions and the Safety Act
- Part 51 Use of Government Sources by Contractors
- Part 52 Solicitation Provisions and Contract Clauses
- Part 53 Forms
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.