FAR 48.104-1 Determining sharing period.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section tells contracting officers how to set the sharing period for each Value Engineering Change Proposal (VECP). The sharing period starts when the first unit incorporating the VECP is accepted and ends on a date or unit-count determined by rules in the section. It matters because the sharing period controls how long the contractor may share in savings from the VECP.
Applies to: Contracting officers determining VECP sharing periods
What it requires
- Contracting officers must determine discrete sharing periods for each VECP.
Key terms: VECP · sharing period · contracting officer · acceptance · future contract units
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Contracting officers must determine discrete sharing periods for each VECP. If more than one VECP is incorporated into a contract, the sharing period for each VECP need not be identical.
(b) The sharing period begins with acceptance of the first unit incorporating the VECP. Except as provided in paragraph (c) of this section, the end of the sharing period is a specific calendar date that is the later of—
(1) 36 to 60 consecutive months (set at the discretion of the contracting officer for each VECP) after the first unit affected by the VECP is accepted; or
(2) The last scheduled delivery date of an item affected by the VECP under the instant contract delivery schedule in effect at the time the VECP is accepted.
(c) For engineering-development contracts and contracts containing low-rate-initial-production or early production units, the end of the sharing period is based not on a calendar date, but on acceptance of a specified quantity of future contract units. This quantity is the number of units affected by the VECP that are scheduled to be delivered over a period of between 36 and 60 consecutive months (set at the discretion of the contracting officer for each VECP) that spans the highest planned production, based on planning and programming or production documentation at the time the VECP is accepted. The specified quantity begins with the first future contract unit affected by the VECP and continues over consecutive deliveries until the sharing period ends at acceptance of the last of the specified quantity of units.
(d) For contracts (other than those in paragraph (c) of this subsection) for items requiring a prolonged production schedule (e.g., ship construction, major system acquisition), the end of the sharing period is determined according to paragraph (b) of this subsection. Agencies may prescribe sharing of future contract savings on all future contract units to be delivered under contracts awarded within the sharing period for essentially the same item, even if the scheduled delivery date is outside the sharing period.
← 48.104 Sharing arrangements. · 48.104-2 Sharing acquisition savings. →