FAR 49.304-1 General.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section explains how a termination contracting officer (TCO) handles a partial termination. Generally, the TCO limits the settlement to adjusting the fee and, with the contracting office's agreement, reducing the estimated cost. However, if the terminated part is clearly severable or the remaining work is not substantial, different procedures apply.
Applies to: Termination contracting officers handling partial terminations
What it requires
- Limit the settlement to an adjustment of the fee, if any, and with the concurrence of the contracting office, to a reduction in the estimated cost
- Adjust the fee as provided in 49.304-2 and 49.305, unless the exceptions in paragraph (a) apply
Key terms: partial termination · TCO · settlement · fee · estimated cost
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) In a partial termination, the TCO shall limit the settlement to an adjustment of the fee, if any, and with the concurrence of the contracting office, to a reduction in the estimated cost. The TCO shall adjust the fee as provided in 49.304-2 and 49.305, unless—
(1) The terminated portion is clearly severable from the balance of the contract; or
(2) Performance of the contract is virtually complete, or performance of any continued portion is only on subsidiary items or spare parts, or is otherwise not substantial.
(b) In the case of the exceptions in paragraph (a), the procedures in 49.302 and 49.303 apply.
← 49.304 Procedure for partial termination. · 49.304-2 Submission of settlement proposal (fee only). →
Rule changes for FAR Part 49
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.