FAR and DFARS › FAR Part 49
FAR Part 49: Termination of Contracts
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
FAR Part 49 establishes policies and procedures for terminating Government contracts, either for the convenience of the Government or for default. It covers the rights and duties of contractors and contracting officers, settlement methods, and required clauses. This part matters because it governs how terminations are handled, affecting contractors' recovery of costs and potential liability.
Key rules
- The contracting officer must terminate contracts for convenience or default only by written notice to the contractor. (49.102)
- After receiving a termination notice, the prime contractor must comply with the notice and the termination clause, except as directed by the termination contracting officer (TCO). (49.104)
- The TCO must direct the prime contractor's actions, examine settlement proposals, and negotiate settlements. (49.105)
- A subcontractor has no contractual rights against the Government upon termination of a prime contract, but may have rights against the prime contractor. (49.108-1)
- Settlement of terminated cost-reimbursement contracts and fixed-price contracts terminated for convenience may be by negotiated agreement, determination by the TCO, or costing-out under the termination clause. (49.103)
- The TCO must refer each prime contractor settlement proposal at or above the threshold for certified cost or pricing data to the appropriate audit agency. (49.107)
- If the contractor and TCO cannot agree on a settlement, or if a proposal is not submitted timely, the TCO shall issue a determination. (49.109-7)
- The total amount payable for a settlement, before deductions and excluding settlement costs, must not exceed the contract price less payments otherwise made. (49.207)
Who does what
- Terminate contracts for convenience or default by written notice.
- Ensure that information on termination for default is reported in accordance with agency procedures.
- Prepare a memorandum for the contract file explaining the reasons for a default termination or a procedure in lieu thereof.
- Comply with the termination notice and the termination clause, except as directed by the TCO.
- Submit settlement proposals promptly to the TCO.
- Terminate subcontracts to the extent required, unless directed otherwise by the TCO.
- Establish procedures for administrative review of proposed termination settlements.
- Provide termination settlement services for other agencies when necessary.
In practice
- When you receive a termination notice, immediately follow the instructions in the notice and the contract's termination clause to protect your rights to recovery.
- Submit a complete settlement proposal on time, using the correct basis (inventory or total cost) as specified in the termination clause.
- If you are a prime contractor, you are responsible for settling with your subcontractors, but you may need TCO authorization for larger settlements.
- If you disagree with the TCO's settlement determination, you may have appeal rights under the Disputes clause, but you must follow the specified procedures.
Common pitfalls
- Failing to submit a settlement proposal within the time required by the termination clause may result in the TCO issuing a determination without your input.
- Assuming that a subcontractor can claim directly against the Government; subcontractors have no privity of contract with the Government.
- Overlooking the limitation that the total settlement cannot exceed the contract price less prior payments, which may reduce your recovery.
- Not reserving rights or demands in the settlement agreement may waive them permanently.
Written by AI from this part's codified text (2026-10-04); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.
Rule changes for FAR Part 49
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
Subparts and sections
Subpart 49.1: General Principles
- 49.100 Scope of subpart.
- 49.101 Authorities and responsibilities.
- 49.102 Notice of termination.
- 49.103 Methods of settlement.
- 49.104 Duties of prime contractor after receipt of notice of termination.
- 49.105 Duties of termination contracting officer after issuance of notice of termination.
- 49.105-1 Termination status reports.
- 49.105-2 Release of excess funds.
- 49.105-3 Termination case file.
- 49.105-4 Cleanup of construction site.
- 49.106 Fraud or other criminal conduct.
- 49.107 Audit of prime contract settlement proposals and subcontract settlements.
- 49.108 Settlement of subcontract settlement proposals.
- 49.108-1 Subcontractor's rights.
- 49.108-2 Prime contractor's rights and obligations.
- 49.108-3 Settlement procedure.
- 49.108-4 Authorization for subcontract settlements without approval or ratification.
- 49.108-5 Recognition of judgments and arbitration awards.
- 49.108-6 Delay in settling subcontractor settlement proposals.
- 49.108-7 Government assistance in settling subcontracts.
- 49.108-8 Assignment of rights under subcontracts.
- 49.109 Settlement agreements.
- 49.109-1 General.
- 49.109-2 Reservations.
- 49.109-3 Government property.
- 49.109-4 No-cost settlement.
- 49.109-5 Partial settlements.
- 49.109-6 Joint settlement of two or more settlement proposals.
- 49.109-7 Settlement by determination.
- 49.110 Settlement negotiation memorandum.
- 49.111 Review of proposed settlements.
- 49.112 Payment.
- 49.112-1 Partial payments.
- 49.112-2 Final payment.
- 49.113 Cost principles.
- 49.114 Unsettled contract changes.
- 49.115 Settlement of terminated incentive contracts.
Subpart 49.2: Additional Principles for Fixed-Price Contracts Terminated for Convenience
- 49.201 General.
- 49.202 Profit.
- 49.203 Adjustment for loss.
- 49.204 Deductions.
- 49.205 Completed end items.
- 49.206 Settlement proposals.
- 49.206-1 Submission of settlement proposals.
- 49.206-2 Bases for settlement proposals.
- 49.206-3 Submission of inventory disposal schedules.
- 49.207 Limitation on settlements.
- 49.208 Equitable adjustment after partial termination.
Subpart 49.3: Additional Principles for Cost-Reimbursement Contracts Terminated for Convenience
- 49.301 General.
- 49.302 Discontinuance of vouchers.
- 49.303 Procedure after discontinuing vouchers.
- 49.303-1 Submission of settlement proposal.
- 49.303-2 Submission of inventory disposal schedules.
- 49.303-3 Audit of settlement proposal.
- 49.303-4 Adjustment of indirect costs.
- 49.303-5 Final settlement.
- 49.304 Procedure for partial termination.
- 49.304-1 General.
- 49.304-2 Submission of settlement proposal (fee only).
- 49.304-3 Submission of vouchers.
- 49.305 Adjustment of fee.
- 49.305-1 General.
- 49.305-2 Construction contracts.
Subpart 49.4: Termination for Default
- 49.401 General.
- 49.402 Termination of fixed-price contracts for default.
- 49.402-1 The Government's right.
- 49.402-2 Effect of termination for default.
- 49.402-3 Procedure for default.
- 49.402-4 Procedure in lieu of termination for default.
- 49.402-5 Memorandum by the contracting officer.
- 49.402-6 Repurchase against contractor's account.
- 49.402-7 Other damages.
- 49.402-8 Reporting information.
- 49.403 Termination of cost-reimbursement contracts for default.
- 49.404 Surety-takeover agreements.
- 49.405 Completion by another contractor.
- 49.406 Liquidation of liability.
Subpart 49.5: Contract Termination Clauses
Subpart 49.6: Contract Termination Forms and Formats
- 49.601 Notice of termination for convenience.
- 49.601-1 Electronic notice.
- 49.601-2 Letter notice.
- 49.602 Forms for settlement of terminated contracts.
- 49.602-1 Termination settlement proposal forms.
- 49.602-2 Inventory forms.
- 49.602-3 Schedule of accounting information.
- 49.602-4 Partial payments.
- 49.602-5 Settlement agreement.
- 49.603 Formats for termination for convenience settlement agreements.
- 49.603-1 Fixed-price contracts—complete termination.
- 49.603-2 Fixed-price contracts—partial termination.
- 49.603-3 Cost-reimbursement contracts—complete termination, if settlement includes cost.
- 49.603-4 Cost-reimbursement contracts—complete termination, with settlement limited to fee.
- 49.603-5 Cost-reimbursement contracts—partial termination.
- 49.603-6 No-cost settlement agreement—complete termination.
- 49.603-7 No-cost settlement agreement—partial termination.
- 49.603-8 Fixed-price contracts—settlements with subcontractors only.
- 49.603-9 Settlement of reservations.
- 49.604 Release of excess funds under terminated contracts.
- 49.605 Request to settle subcontractor settlement proposals.
- 49.606 Granting subcontract settlement authorization.
- 49.607 Delinquency notices.
← Part 48: Value EngineeringPart 50: Extraordinary Contractual Actions and the Safety Act →
All FAR parts
- Part 1 Federal Acquisition Regulations System
- Part 2 Definitions of Words and Terms
- Part 3 Improper Business Practices and Personal Conflicts of Interest
- Part 4 Administrative and Information Matters
- Part 5 Publicizing Contract Actions
- Part 6 Competition Requirements
- Part 7 Acquisition Planning
- Part 8 Required Sources of Supplies and Services
- Part 9 Contractor Qualifications
- Part 10 Market Research
- Part 11 Describing Agency Needs
- Part 12 Acquisition of Commercial Products and Commercial Services
- Part 13 Simplified Acquisition Procedures
- Part 14 Sealed Bidding
- Part 15 Contracting by Negotiation
- Part 16 Types of Contracts
- Part 17 Special Contracting Methods
- Part 18 Emergency Acquisitions
- Part 19 Small Business Programs
- Part 22 Application of Labor Laws to Government Acquisitions
- Part 23 Environment, Sustainable Acquisition, and Material Safety
- Part 24 Protection of Privacy and Freedom of Information
- Part 25 Foreign Acquisition
- Part 26 Other Socioeconomic Programs
- Part 27 Patents, Data, and Copyrights
- Part 28 Bonds and Insurance
- Part 29 Taxes
- Part 30 Cost Accounting Standards Administration
- Part 31 Contract Cost Principles and Procedures
- Part 32 Contract Financing
- Part 33 Protests, Disputes, and Appeals
- Part 34 Major System Acquisition
- Part 35 Research and Development Contracting
- Part 36 Construction and Architect-engineer Contracts
- Part 37 Service Contracting
- Part 38 Federal Supply Schedule Contracting
- Part 39 Acquisition of Information Technology
- Part 40 Information Security and Supply Chain Security
- Part 41 Acquisition of Utility Services
- Part 42 Contract Administration and Audit Services
- Part 43 Contract Modifications
- Part 44 Subcontracting Policies and Procedures
- Part 45 Government Property
- Part 46 Quality Assurance
- Part 47 Transportation
- Part 48 Value Engineering
- Part 49 Termination of Contracts
- Part 50 Extraordinary Contractual Actions and the Safety Act
- Part 51 Use of Government Sources by Contractors
- Part 52 Solicitation Provisions and Contract Clauses
- Part 53 Forms
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.