FAR and DFARS › FAR Part 49

FAR Part 49: Termination of Contracts

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

In plain English

FAR Part 49 governs how federal contracts are ended, either completely or partly, when the Government terminates for its own convenience or because the contractor defaulted. For a small business, it determines what can be recovered for work and preparations already done, how subcontractor claims flow through the prime, and what liabilities follow a default termination.

Key rules

  • The contracting officer may terminate for convenience or default only by written notice to the contractor, which can be expedited by electronic means. (49.102, 49.601, 49.601-1, 49.601-2)
  • After receiving a termination notice, the contractor must comply with the notice and the termination clause, except as the termination contracting officer directs otherwise, including terminating subcontracts to the extent the notice requires. (49.104, 49.108-2)
  • A settlement should compensate the contractor fairly for work done and preparations made on the terminated portion, including a reasonable profit, but profit is not allowed if the contractor would have incurred a loss had the whole contract been completed. (49.201, 49.202, 49.203)
  • The total settlement may not exceed the contract price less payments otherwise made, and the settlement is reduced by deductions such as the agreed price of termination inventory the contractor keeps. (49.207, 49.204)
  • Subcontractors have no contractual rights against the Government on prime termination; their settlement claims run against the prime contractor, which must settle them generally following the same principles as prime settlements. (49.108-1, 49.108-3)
  • Under a default termination, the Government is not liable for costs on undelivered work and may recover advance and progress payments, and the contractor and surety may be liable for resulting damages. (49.402-2, 49.406, 49.402-7)
  • Where a contractor must submit a settlement proposal, it should do so promptly, and a final settlement proposal generally must be submitted within one year of the termination effective date for cost-reimbursement contracts unless extended. (49.206-1, 49.303-1, 49.304-2)

Who does what

Contracting officers
  • Issue the written termination notice and, for default, review the decision and document the reasons in a memorandum for the contract file.
  • Estimate settlement funds and recommend release of excess funds within 30 days after the termination notice.
  • Refer large settlement proposals to audit, prepare a settlement negotiation memorandum, and issue a settlement determination if no agreement is reached.
  • Repurchase still-needed supplies or services against the defaulted contractor's account as soon as practicable, and assess other damages.
Contractors
  • Comply with the termination notice and clause, and terminate subcontracts as required.
  • Promptly submit a settlement proposal with inventory disposal schedules when termination inventory is involved.
  • Settle subcontractor claims generally in line with the prime settlement principles, and assign subcontract rights to the Government when directed.
  • Submit final settlement proposals within the required period, which for cost-reimbursement work is generally one year from the termination effective date.
Agencies
  • Establish procedures for administrative review of proposed termination settlements.
  • Establish reporting procedures for default termination notices and their withdrawal or conversion.

In practice

  • Keep detailed, allocable cost records and inventory records from the moment a termination notice arrives, since settlement proposals are built from them.
  • Expect profit only on work and preparations done for the terminated portion, not on settlement expenses, and expect none if the contract would have been a loss.
  • Flow down termination terms to subcontracts so your settlement exposure to subcontractors is manageable.
  • On a default termination, expect the Government to recover unliquidated advance and progress payments and possibly repurchase costs.

Common pitfalls

  • Submitting an incomplete or late settlement proposal, since the regulation sets a one-year period for final proposals on cost-reimbursement terminations.
  • Assuming subcontractors can claim directly against the Government; under 49.108-1 they must pursue the prime contractor.
  • Expecting profit on settlement expenses or on anticipated profits from the terminated work, which the text excludes.
  • Failing to account for termination inventory you keep or purchase, which is deducted from the settlement amount.

Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.

Rule changes for FAR Part 49

Subparts and sections

Subpart 49.1: General Principles

Subpart 49.2: Additional Principles for Fixed-Price Contracts Terminated for Convenience

Subpart 49.3: Additional Principles for Cost-Reimbursement Contracts Terminated for Convenience

Subpart 49.4: Termination for Default

Subpart 49.5: Contract Termination Clauses

Subpart 49.6: Contract Termination Forms and Formats

← Part 48: Value EngineeringPart 50: Extraordinary Contractual Actions and the Safety Act →

All FAR parts

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.