FAR and DFARS › FAR Part 49
FAR Part 49: Termination of Contracts
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
In plain English
FAR Part 49 governs how federal contracts are ended, either completely or partly, when the Government terminates for its own convenience or because the contractor defaulted. For a small business, it determines what can be recovered for work and preparations already done, how subcontractor claims flow through the prime, and what liabilities follow a default termination.
Key rules
- The contracting officer may terminate for convenience or default only by written notice to the contractor, which can be expedited by electronic means. (49.102, 49.601, 49.601-1, 49.601-2)
- After receiving a termination notice, the contractor must comply with the notice and the termination clause, except as the termination contracting officer directs otherwise, including terminating subcontracts to the extent the notice requires. (49.104, 49.108-2)
- A settlement should compensate the contractor fairly for work done and preparations made on the terminated portion, including a reasonable profit, but profit is not allowed if the contractor would have incurred a loss had the whole contract been completed. (49.201, 49.202, 49.203)
- The total settlement may not exceed the contract price less payments otherwise made, and the settlement is reduced by deductions such as the agreed price of termination inventory the contractor keeps. (49.207, 49.204)
- Subcontractors have no contractual rights against the Government on prime termination; their settlement claims run against the prime contractor, which must settle them generally following the same principles as prime settlements. (49.108-1, 49.108-3)
- Under a default termination, the Government is not liable for costs on undelivered work and may recover advance and progress payments, and the contractor and surety may be liable for resulting damages. (49.402-2, 49.406, 49.402-7)
- Where a contractor must submit a settlement proposal, it should do so promptly, and a final settlement proposal generally must be submitted within one year of the termination effective date for cost-reimbursement contracts unless extended. (49.206-1, 49.303-1, 49.304-2)
Who does what
- Issue the written termination notice and, for default, review the decision and document the reasons in a memorandum for the contract file.
- Estimate settlement funds and recommend release of excess funds within 30 days after the termination notice.
- Refer large settlement proposals to audit, prepare a settlement negotiation memorandum, and issue a settlement determination if no agreement is reached.
- Repurchase still-needed supplies or services against the defaulted contractor's account as soon as practicable, and assess other damages.
- Comply with the termination notice and clause, and terminate subcontracts as required.
- Promptly submit a settlement proposal with inventory disposal schedules when termination inventory is involved.
- Settle subcontractor claims generally in line with the prime settlement principles, and assign subcontract rights to the Government when directed.
- Submit final settlement proposals within the required period, which for cost-reimbursement work is generally one year from the termination effective date.
- Establish procedures for administrative review of proposed termination settlements.
- Establish reporting procedures for default termination notices and their withdrawal or conversion.
In practice
- Keep detailed, allocable cost records and inventory records from the moment a termination notice arrives, since settlement proposals are built from them.
- Expect profit only on work and preparations done for the terminated portion, not on settlement expenses, and expect none if the contract would have been a loss.
- Flow down termination terms to subcontracts so your settlement exposure to subcontractors is manageable.
- On a default termination, expect the Government to recover unliquidated advance and progress payments and possibly repurchase costs.
Common pitfalls
- Submitting an incomplete or late settlement proposal, since the regulation sets a one-year period for final proposals on cost-reimbursement terminations.
- Assuming subcontractors can claim directly against the Government; under 49.108-1 they must pursue the prime contractor.
- Expecting profit on settlement expenses or on anticipated profits from the terminated work, which the text excludes.
- Failing to account for termination inventory you keep or purchase, which is deducted from the settlement amount.
Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.
Rule changes for FAR Part 49
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
Subparts and sections
Subpart 49.1: General Principles
- 49.100 Scope of subpart.
- 49.101 Authorities and responsibilities.
- 49.102 Notice of termination.
- 49.103 Methods of settlement.
- 49.104 Duties of prime contractor after receipt of notice of termination.
- 49.105 Duties of termination contracting officer after issuance of notice of termination.
- 49.105-1 Termination status reports.
- 49.105-2 Release of excess funds.
- 49.105-3 Termination case file.
- 49.105-4 Cleanup of construction site.
- 49.106 Fraud or other criminal conduct.
- 49.107 Audit of prime contract settlement proposals and subcontract settlements.
- 49.108 Settlement of subcontract settlement proposals.
- 49.108-1 Subcontractor's rights.
- 49.108-2 Prime contractor's rights and obligations.
- 49.108-3 Settlement procedure.
- 49.108-4 Authorization for subcontract settlements without approval or ratification.
- 49.108-5 Recognition of judgments and arbitration awards.
- 49.108-6 Delay in settling subcontractor settlement proposals.
- 49.108-7 Government assistance in settling subcontracts.
- 49.108-8 Assignment of rights under subcontracts.
- 49.109 Settlement agreements.
- 49.109-1 General.
- 49.109-2 Reservations.
- 49.109-3 Government property.
- 49.109-4 No-cost settlement.
- 49.109-5 Partial settlements.
- 49.109-6 Joint settlement of two or more settlement proposals.
- 49.109-7 Settlement by determination.
- 49.110 Settlement negotiation memorandum.
- 49.111 Review of proposed settlements.
- 49.112 Payment.
- 49.112-1 Partial payments.
- 49.112-2 Final payment.
- 49.113 Cost principles.
- 49.114 Unsettled contract changes.
- 49.115 Settlement of terminated incentive contracts.
Subpart 49.2: Additional Principles for Fixed-Price Contracts Terminated for Convenience
- 49.201 General.
- 49.202 Profit.
- 49.203 Adjustment for loss.
- 49.204 Deductions.
- 49.205 Completed end items.
- 49.206 Settlement proposals.
- 49.206-1 Submission of settlement proposals.
- 49.206-2 Bases for settlement proposals.
- 49.206-3 Submission of inventory disposal schedules.
- 49.207 Limitation on settlements.
- 49.208 Equitable adjustment after partial termination.
Subpart 49.3: Additional Principles for Cost-Reimbursement Contracts Terminated for Convenience
- 49.301 General.
- 49.302 Discontinuance of vouchers.
- 49.303 Procedure after discontinuing vouchers.
- 49.303-1 Submission of settlement proposal.
- 49.303-2 Submission of inventory disposal schedules.
- 49.303-3 Audit of settlement proposal.
- 49.303-4 Adjustment of indirect costs.
- 49.303-5 Final settlement.
- 49.304 Procedure for partial termination.
- 49.304-1 General.
- 49.304-2 Submission of settlement proposal (fee only).
- 49.304-3 Submission of vouchers.
- 49.305 Adjustment of fee.
- 49.305-1 General.
- 49.305-2 Construction contracts.
Subpart 49.4: Termination for Default
- 49.401 General.
- 49.402 Termination of fixed-price contracts for default.
- 49.402-1 The Government's right.
- 49.402-2 Effect of termination for default.
- 49.402-3 Procedure for default.
- 49.402-4 Procedure in lieu of termination for default.
- 49.402-5 Memorandum by the contracting officer.
- 49.402-6 Repurchase against contractor's account.
- 49.402-7 Other damages.
- 49.402-8 Reporting information.
- 49.403 Termination of cost-reimbursement contracts for default.
- 49.404 Surety-takeover agreements.
- 49.405 Completion by another contractor.
- 49.406 Liquidation of liability.
Subpart 49.5: Contract Termination Clauses
Subpart 49.6: Contract Termination Forms and Formats
- 49.601 Notice of termination for convenience.
- 49.601-1 Electronic notice.
- 49.601-2 Letter notice.
- 49.602 Forms for settlement of terminated contracts.
- 49.602-1 Termination settlement proposal forms.
- 49.602-2 Inventory forms.
- 49.602-3 Schedule of accounting information.
- 49.602-4 Partial payments.
- 49.602-5 Settlement agreement.
- 49.603 Formats for termination for convenience settlement agreements.
- 49.603-1 Fixed-price contracts—complete termination.
- 49.603-2 Fixed-price contracts—partial termination.
- 49.603-3 Cost-reimbursement contracts—complete termination, if settlement includes cost.
- 49.603-4 Cost-reimbursement contracts—complete termination, with settlement limited to fee.
- 49.603-5 Cost-reimbursement contracts—partial termination.
- 49.603-6 No-cost settlement agreement—complete termination.
- 49.603-7 No-cost settlement agreement—partial termination.
- 49.603-8 Fixed-price contracts—settlements with subcontractors only.
- 49.603-9 Settlement of reservations.
- 49.604 Release of excess funds under terminated contracts.
- 49.605 Request to settle subcontractor settlement proposals.
- 49.606 Granting subcontract settlement authorization.
- 49.607 Delinquency notices.
← Part 48: Value EngineeringPart 50: Extraordinary Contractual Actions and the Safety Act →
All FAR parts
- Part 1 Federal Acquisition Regulations System
- Part 2 Definitions of Words and Terms
- Part 3 Improper Business Practices and Personal Conflicts of Interest
- Part 4 Administrative and Information Matters
- Part 5 Publicizing Contract Actions
- Part 6 Competition Requirements
- Part 7 Acquisition Planning
- Part 8 Required Sources of Supplies and Services
- Part 9 Contractor Qualifications
- Part 10 Market Research
- Part 11 Describing Agency Needs
- Part 12 Acquisition of Commercial Products and Commercial Services
- Part 13 Simplified Acquisition Procedures
- Part 14 Sealed Bidding
- Part 15 Contracting by Negotiation
- Part 16 Types of Contracts
- Part 17 Special Contracting Methods
- Part 18 Emergency Acquisitions
- Part 19 Small Business Programs
- Part 22 Application of Labor Laws to Government Acquisitions
- Part 23 Environment, Sustainable Acquisition, and Material Safety
- Part 24 Protection of Privacy and Freedom of Information
- Part 25 Foreign Acquisition
- Part 26 Other Socioeconomic Programs
- Part 27 Patents, Data, and Copyrights
- Part 28 Bonds and Insurance
- Part 29 Taxes
- Part 30 Cost Accounting Standards Administration
- Part 31 Contract Cost Principles and Procedures
- Part 32 Contract Financing
- Part 33 Protests, Disputes, and Appeals
- Part 34 Major System Acquisition
- Part 35 Research and Development Contracting
- Part 36 Construction and Architect-engineer Contracts
- Part 37 Service Contracting
- Part 38 Federal Supply Schedule Contracting
- Part 39 Acquisition of Information Technology
- Part 40 Information Security and Supply Chain Security
- Part 41 Acquisition of Utility Services
- Part 42 Contract Administration and Audit Services
- Part 43 Contract Modifications
- Part 44 Subcontracting Policies and Procedures
- Part 45 Government Property
- Part 46 Quality Assurance
- Part 47 Transportation
- Part 48 Value Engineering
- Part 49 Termination of Contracts
- Part 50 Extraordinary Contractual Actions and the Safety Act
- Part 51 Use of Government Sources by Contractors
- Part 52 Solicitation Provisions and Contract Clauses
- Part 53 Forms
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.