FAR 52.232-10 Payments Under Fixed-Price Architect-Engineer Contracts.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This clause governs how the Government pays a contractor under a fixed-price architect-engineer contract. It requires monthly estimates of work performed, allows the Contracting Officer to withhold up to 10 percent only if needed to protect the Government, and sets a limit on progress payments for undefinitized contract actions. It also requires a release of claims before final payment.

Applies to: Contractors under fixed-price architect-engineer contracts

What it requires

  • Prepare monthly estimates of the amount and value of work and services performed that meet contract quality standards, along with any required supporting data, and submit them with the voucher.
  • Before final payment or settlement upon termination, execute and deliver to the Contracting Officer a release of all claims against the Government arising under or by virtue of this contract, except claims specifically excepted in stated amounts.

Key terms: undefinitized contract actions · progress payments · withholding · release of claims · voucher

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 32.111(c)(1), insert the following clause:

Payments Under Fixed-Price Architect-Engineer Contracts (APR 2010)

(a) Estimates shall be made monthly of the amount and value of the work and services performed by the Contractor under this contract which meet the standards of quality established under this contract. The estimates, along with any supporting data required by the Contracting Officer, shall be prepared by the Contractor and submitted along with its voucher.

(b) After receipt of each substantiated voucher, the Government shall pay the voucher as approved by the Contracting Officer or authorized representative. The Contracting Officer shall require a withholding from amounts due under paragraph (a) of this clause of up to 10 percent only if the Contracting Officer determines that such a withholding is necessary to protect the Government's interest and ensure satisfactory completion of the contract. The amount withheld shall be determined based upon the Contractor's performance record under this contract. Whenever the Contracting Officer determines that the work is substantially complete and that the amount retained is in excess of the amount adequate for the protection of the Government, the Contracting Officer shall release the excess amount to the Contractor.

(c) Upon satisfactory completion by the Contractor and final acceptance by the Contracting Officer of all the work done by the Contractor under the “Statement of Architect-Engineer Services”, the Contractor will be paid the unpaid balance of any money due for work under the statement, including all withheld amounts.

(d) Before final payment under the contract, or before settlement upon termination of the contract, and as a condition precedent thereto, the Contractor shall execute and deliver to the Contracting Officer a release of all claims against the Government arising under or by virtue of this contract, other than any claims that are specifically excepted by the Contractor from the operation of the release in amounts stated in the release.

(e) Notwithstanding any other provision in this contract, and specifically paragraph (b) of this clause, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A contract action is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(End of clause)

Sections it refers to

  • 32.111 Contract clauses for noncommercial purchases.

Sections that refer to it

  • 32.001 Definitions.
  • 32.111 Contract clauses for noncommercial purchases.
  • 32.904 Determining payment due dates.
  • 32.905 Payment documentation and process.
  • 32.908 Contract clauses.
  • 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

← 52.232-9 Limitation on Withholding of Payments. · 52.232-11 Extras. →

Rule changes for FAR Part 52

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.