FAR 9.204 Responsibilities for establishment of a qualification requirement.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section outlines the responsibilities of agency activities that establish qualification requirements for products. It requires them to publicize requirements, potentially bear testing costs for small businesses, and maintain lists of qualified products. Contractors should understand that qualification requirements are managed by the government and that small businesses may receive financial assistance for testing under certain conditions.
Applies to: Agency activities that establish qualification requirements
What it requires
- Arrange publicity for qualification requirements, including periodic notices through the GPE if competition is limited, unless national security is compromised.
- Bear the cost of specified testing and evaluation for small business concerns that meet qualification standards and are expected to compete, if cost savings are determined likely.
- Qualify products that meet specification requirements.
- List manufacturers and suppliers whose products are qualified.
Key terms: qualification requirement · Governmentwide point of entry (GPE) · small business concern · QPL · OML
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
The responsibilities of agency activities that establish qualification requirements include the following:
(a) Arranging publicity for the qualification requirements. If active competition on anticipated future qualification requirements is likely to be fewer than two manufacturers or the products of two manufacturers, the activity responsible for establishment of the qualification requirements must—
(1) Periodically furnish through the Governmentwide point of entry (GPE) a notice seeking additional sources or products for qualification unless the contracting officer determines that such publication would compromise the national security.
(2) Bear the cost of conducting the specified testing and evaluation (excluding the costs associated with producing the item or establishing the production, quality control, or other system to be tested and evaluated) for a small business concern or a product manufactured by a small business concern which has met the standards specified for qualification and which could reasonably be expected to compete for a contract for that requirement. However, such costs may be borne only if it is determined in accordance with agency procedures that such additional qualified sources or products are likely to result in cost savings from increased competition for future requirements sufficient to amortize the costs incurred by the agency within a reasonable period of time, considering the duration and dollar value of anticipated future requirements. A prospective contractor requesting the United States to bear testing and evaluation costs must certify as to its status as a small business concern under section 3 of the Small Business Act in order to receive further consideration.
(b) Qualifying products that meet specification requirements.
(c) Listing manufacturers and suppliers whose products are qualified in accordance with agency procedures.
(d) Furnishing QPL's, OML's, or QBL's or the qualification requirements themselves to prospective offerors and the public upon request(see 9.202(a)(2)(i)).
(e) Clarifying, as necessary, qualification requirements.
(f) In appropriate cases, when requested by the contracting officer, providing concurrence in a decision not to enforce a qualification requirement for a solicitation.
(g) Withdrawing or omitting qualification of a listed product, manufacturer or offeror, as necessary.
(h) Advising persons furnished any list of products, manufacturers or offerors meeting a qualification requirement and suppliers whose products are on any such list that—
(1) The list does not constitute endorsement of the product, manufacturer, or other source by the Government;
(2) The products or sources listed have been qualified under the latest applicable specification;
(3) The list may be amended without notice;
(4) The listing of a product or source does not release the supplier from compliance with the specification; and
(5) Use of the list for advertising or publicity is permitted. However, it must not be stated or implied that a particular product or source is the only product or source of that type qualified, or that the Government in any way recommends or endorses the products or the sources listed.
(i) Reexamining a qualified product or manufacturer when—
(1) The manufacturer has modified its product, or changed the material or the processing sufficiently so that the validity of previous qualification is questionable;
(2) The requirements in the specification have been amended or revised sufficiently to affect the character of the product; or
(3) It is otherwise necessary to determine that the quality of the product is maintained in conformance with the specification.
Sections it refers to
- 9.202 Policy.
← 9.203 QPL's, QML's, and QBL's. · 9.205 Opportunity for qualification before award. →
Rule changes for FAR Part 9
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Prohibition on Certain Semiconductor Products and Services ↗ · proposed 2026-02-17 · comments due 2026-04-20
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Controlled Unclassified Information ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Disclosure of Greenhouse Gas Emissions and Climate-Related Financial Risk ↗ · proposed 2025-01-13
- Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment ↗ · final rule 2025-01-03 · effective 2025-01-17
- Federal Acquisition Regulation: Certification of Service-Disabled Veteran-Owned Small Businesses ↗ · final rule 2024-12-16 · effective 2024-12-16
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.