FAR and DFARS › FAR Part 9: Contractor Qualifications › Subpart 9.3
FAR 9.306 Solicitation requirements.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
FAR 9.306 specifies what solicitations must include when they contain a first article testing and approval requirement. It ensures offerors know the technical criteria, testing responsibilities, and evaluation factors, and it allows for waiver and alternative offers under certain conditions.
Applies to: Solicitations with a first article testing and approval requirement
What it requires
- Provide the performance or other characteristics the first article must meet for approval
- Provide detailed technical requirements for tests if the contractor is responsible for testing
- Provide necessary data to be submitted in the first article approval test report if the contractor is responsible for testing
- Provide the tests to which the first article will be subjected if the Government is responsible for testing
Key terms: first article · first article approval testing · solicitation · offeror · waiver
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
Solicitations containing a testing and approval requirement shall—
(a) Provide, in the circumstance where the contractor is to be responsible for the first article approval testing—
(1) The performance or other characteristics that the first article must meet for approval;
(2) The detailed technical requirements for the tests that must be performed for approval; and
(3) The necessary data that must be submitted to the Government in the first article approval test report;
(b) Provide, in the circumstance where the Government is to be responsible for the first article approval testing—
(1) The performance or other characteristics that the first article must meet for approval; and
(2) The tests to which the first article will be subjected for approval;
(c) Inform offerors that the requirement may be waived when supplies identical or similar to those called for have previously been delivered by the offeror and accepted by the Government (see 52.209-3(h) and 52.209- 4(i));
(d) Permit the submission of alternative offers, one including testing and approval and the other excluding testing and approval (if eligible under paragraph (c) of this section);
(e) State clearly the first article's relationship to the contract quantity (see paragraph (e) of the clause at 52.209-3, First Article Approval—Contractor Testing, or 52.209-4, First Article Approval—Government Testing);
(f) Contain a delivery schedule for the production quantity (see 11.403). The delivery schedule may—
(1) Be the same whether or not testing and approval is waived; or
(2) Provide for earlier delivery when testing and approval is waived and the Government desires earlier delivery. In the latter case, any resulting difference in delivery schedules shall not be a factor in evaluation for award. The clause at 52.209-4, First Article Approval—Government Testing, shall contain the delivery schedule for the first article;
(g) Provide for the submission of contract numbers, if any, to document the offeror's eligibility under paragraph (c) of this section;
(h) State whether the approved first article will serve as a manufacturing standard;
(i) Include, when the Government is responsible for first article testing, the Government's estimated testing costs as a factor for use in evaluating offers (when appropriate); and
(j) Inform offerors that the prices for first articles and first article tests in relation to production quantities shall not be materially unbalanced (see 15.404-1(g)) if first article test items or tests are to be separately priced.
← 9.305 Risk. · 9.307 Government administration procedures. →
Rule changes for FAR Part 9
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Prohibition on Certain Semiconductor Products and Services ↗ · proposed 2026-02-17 · comments due 2026-04-20
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Controlled Unclassified Information ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Disclosure of Greenhouse Gas Emissions and Climate-Related Financial Risk ↗ · proposed 2025-01-13
- Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment ↗ · final rule 2025-01-03 · effective 2025-01-17
- Federal Acquisition Regulation: Certification of Service-Disabled Veteran-Owned Small Businesses ↗ · final rule 2024-12-16 · effective 2024-12-16
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.