The FAR overhaul, side by side
FAR Part 26: Other Socioeconomic Programs
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 36 sections, 3,678 words (Part 26 as in force, eCFR as of Oct 29, 2026). Overhaul text: 28 sections, 1,862 words (on acquisition.gov ↗, issued Aug 8, 2025). By number: 1 the same, 16 changed, 19 not in the overhaul (6 with the same heading under another number), 11 new.
26.202-1: Changed (22% alike)
Today: Local area set-aside.
The contracting officer may set aside solicitations to allow only local firms within a specific geographic area to compete (see 6.208).
(a) The contracting officer, in consultation with the requirements office, shall define the specific geographic area for the local set-aside.
(b) A major disaster or emergency area may span counties in several contiguous States. The set-aside area need not include all the counties in the declared disaster/emergency area(s), but cannot go outside it.
(c) The contracting officer shall also determine whether a local area set-aside should be further restricted to small business concerns in the set-aside area (see Part 19).
Overhaul text: Policy.
(a) Local area preference. Contracting officers must, when practicable, award emergency response contracts to local firms (see 42 U.S.C. 5150). To support this policy, contracting officers may—
(1) Set aside acquisitions to allow only local firms within a specific geographic area to compete (see part 6); or
(2) Use an evaluation preference.
(b) Transition of work.
(1) Agencies may award emergency response contracts before a major disaster or emergency occurs to ensure immediate relief is available. Structure such contracts to support timely transition of work to local firms after a major disaster or emergency area has been established.
(2) Agencies must transition emergency response contracts to local firms after a major disaster or emergency is declared, unless the head of the agency determines on an individual or class basis that is not practicable. However, agencies are not required to terminate or renegotiate existing contracts to make the transition.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 26.100 | Scope of subpart. | none | Not in the overhaul | 24 → – |
| 26.101 | Definitions. | Definitions. | Changed · 96% alike | 225 → 219 |
| 26.102 | Policy. | Presolicitation. | Changed · 0% alike | 66 → 0 |
| 26.102-1 | none | Policy. | New number | – → 35 |
| 26.102-2 | none | Contract clause. | New number Same heading as today's 26.104 | – → 66 |
| 26.103 | Procedures. | Postaward. | Changed · 34% alike | 337 → 81 |
| 26.104 | Contract clause. | none | Not in the overhaul Same heading at 26.102-2 | 66 → – |
| 26.200 | Scope of subpart. | none | Not in the overhaul | 35 → – |
| 26.201 | Definitions. | Definitions. | Changed · 96% alike | 97 → 103 |
| 26.202 | Local area preference. | Presolicitation. | Changed · 0% alike | 104 → 0 |
| 26.202-1 | Local area set-aside. | Policy. | Changed · 22% alike | 109 → 149 |
| 26.202-2 | Evaluation preference. | Procedures. | Changed · 4% alike | 15 → 149 |
| 26.202-3 | none | Solicitation provision and contract clauses. | New number Same heading as today's 26.206 | – → 85 |
| 26.203 | Transition of work. | none | Not in the overhaul | 288 → – |
| 26.204 | Justification for expenditures to other than local firms. | none | Not in the overhaul | 99 → – |
| 26.205 | Disaster Response Registry. | none | Not in the overhaul | 110 → – |
| 26.206 | Solicitation provision and contract clauses. | none | Not in the overhaul Same heading at 26.202-3 | 93 → – |
| 26.300 | Scope of subpart. | none | Not in the overhaul | 46 → – |
| 26.301 | [Reserved] | Presolicitation. | Same | 0 → 0 |
| 26.301-1 | none | General. | New number | – → 45 |
| 26.301-2 | none | Solicitation provision. | New number Same heading as today's 26.304 | – → 41 |
| 26.302 | General policy. | none | Not in the overhaul | 17 → – |
| 26.303 | Data collection and reporting requirements. | none | Not in the overhaul | 28 → – |
| 26.304 | Solicitation provision. | none | Not in the overhaul Same heading at 26.301-2 | 37 → – |
| 26.400 | Scope of subpart. | none | Not in the overhaul | 14 → – |
| 26.401 | Definitions. | Definitions. | Changed · 91% alike | 131 → 111 |
| 26.402 | Policy. | Presolicitation. | Changed · 0% alike | 35 → 0 |
| 26.402-1 | none | Policy. | New number | – → 98 |
| 26.402-2 | none | Contract clause. | New number Same heading as today's 26.104 | – → 31 |
| 26.403 | Procedures. | none | Not in the overhaul | 231 → – |
| 26.404 | Contract clause. | none | Not in the overhaul Same heading at 26.102-2 | 33 → – |
| 26.500 | Scope of subpart. | none | Not in the overhaul | 10 → – |
| 26.501 | Applicability. | Applicability. | Changed · 88% alike | 151 → 125 |
| 26.502 | Authority. | Definitions. | Changed · 2% alike | 7 → 156 |
| 26.503 | Definitions. | Presolicitation. | Changed · 0% alike | 159 → 0 |
| 26.503-1 | none | Contract clause. | New number Same heading as today's 26.104 | – → 18 |
| 26.504 | Policy. | Evaluation and award. | Changed · 0% alike | 556 → 0 |
| 26.504-1 | none | Policy. | New number | – → 70 |
| 26.505 | Suspension of payments, termination of contract, and debarment and suspension actions. | Postaward. | Changed · 0% alike | 252 → 0 |
| 26.505-1 | none | Suspension of payments, contract termination, and debarment and suspension actions. | New number | – → 211 |
| 26.506 | Contract clause. | none | Not in the overhaul Same heading at 26.102-2 | 18 → – |
| 26.601 | Purpose. | Presolicitation. | Changed · 0% alike | 29 → 0 |
| 26.601-1 | none | Policy. | New number | – → 49 |
| 26.602 | Applicability. | 26.601-2 Contract clause. | Changed · 36% alike | 8 → 20 |
| 26.603 | Definitions. | none | Not in the overhaul | 175 → – |
| 26.604 | Policy. | none | Not in the overhaul | 49 → – |
| 26.605 | Contract clause. | none | Not in the overhaul Same heading at 26.102-2 | 24 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress