The FAR overhaul, side by side
FAR Part 39: Acquisition of Information Technology
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 14 sections, 2,824 words (Part 39 as in force, eCFR as of Oct 29, 2026). Overhaul text: 12 sections, 1,500 words, titled "Acquisition of Information and Communication Technology" (on acquisition.gov ↗, issued Jun 12, 2025). By number: 0 the same, 6 changed, 8 not in the overhaul (2 with the same heading under another number), 6 new.
39.103: Changed (3% alike)
Today: Modular contracting.
(a) This section implements 41 U.S.C. 2308. Modular contracting is intended to reduce program risk and to incentivize contractor performance while meeting the Governments need for timely access to rapidly changing technology. Consistent with the agency's information technology architecture, agencies should, to the maximum extent practicable, use modular contracting to acquire major systems (see 2.101) of information technology. Agencies may also use modular contracting to acquire non-major systems of information technology.
(b) When using modular contracting, an acquisition of a system of information technology may be divided into several smaller acquisition increments that—
(1) Are easier to manage individually than would be possible in one comprehensive acquisition;
(2) Address complex information technology objectives incrementally in order to enhance the likelihood of achieving workable systems or solutions for attainment of those objectives;
(3) Provide for delivery, implementation, and testing of workable systems or solutions in discrete increments, each of which comprises a system or solution that is not dependent on any subsequent increment in order to perform its principal functions;
(4) Provide an opportunity for subsequent increments to take advantage of any evolution in technology or needs that occur during implementation and use of the earlier increments; and
(5) Reduce risk of potential adverse consequences on the overall project by isolating and avoiding custom-designed components of the system.
(c) The characteristics of an increment may vary depending upon the type of information technology being acquired and the nature of the system being developed. The following factors may be considered:
(1) To promote compatibility, the information technology acquired through modular contracting for each increment should comply with common or commercially acceptable information technology standards when available and appropriate, and shall conform to the agency's master information technology architecture.
(2) The performance requirements of each increment should be consistent with the performance requirements of the completed, overall system within which the information technology will function and should address interface requirements with succeeding increments.
(d) For each increment, contracting officers shall choose an appropriate contracting technique that facilitates the acquisition of subsequent increments. Pursuant to parts 16 and 17 of the Federal Acquisition Regulations, contracting officers shall select the contract type and method appropriate to the circumstances (e.g., indefinite delivery, indefinite quantity contracts, single contract with options, successive contracts, multiple awards, task order contracts). Contract(s) shall be structured to ensure that the Government is not required to procure additional increments.
(e) To avoid obsolescence, a modular contract for information technology should, to the maximum extent practicable, be awarded within 180 days after the date on which the solicitation is issued. If award cannot be made within 180 days, agencies should consider cancellation of the solicitation in accordance with 48 CFR 14.209 or 15.206(e). To the maximum extent practicable, deliveries under the contract should be scheduled to occur within 18 months after issuance of the solicitation.
Overhaul text: Information technology services.
When acquiring information technology services, solicitations should not describe any minimum experience or educational requirements for proposed contractor personnel, unless the contracting officer determines that the needs of the agency—
(a) Cannot be met without that requirement; or
(b) Require using other than a performance-based acquisition (see subpart 37.6).
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 39.000 | Scope of part. | none | Not in the overhaul | 53 → – |
| 39.001 | Applicability. | Applicability. | Changed · 20% alike | 112 → 58 |
| 39.002 | Definitions. | none | Not in the overhaul | 118 → – |
| 39.101 | Policy. | Management of risk. | Changed · 3% alike | 531 → 47 |
| 39.102 | Management of risk. | Modular contracting. | Changed · 5% alike | 190 → 284 |
| 39.103 | Modular contracting. | Information technology services. | Changed · 3% alike | 479 → 51 |
| 39.104 | Information technology services. | ICT accessibility standards. | Changed · 0% alike | 53 → 0 |
| 39.104-1 | none | Scope. | New number | – → 45 |
| 39.104-2 | none | Policy. | New number | – → 86 |
| 39.104-3 | none | Applicability. | New number | – → 214 |
| 39.104-4 | none | Exceptions. | New number Same heading as today's 39.204 | – → 162 |
| 39.104-5 | none | Exemptions. | New number Same heading as today's 39.205 | – → 424 |
| 39.105 | Privacy. | none | Not in the overhaul | 134 → – |
| 39.106 | Contract clause. | none | Not in the overhaul | 55 → – |
| 39.201 | Scope of subpart. | ICT accessibility standards for indefinite-quantity contracts. | Changed · 7% alike | 139 → 81 |
| 39.202 | Definition. | none | Not in the overhaul | 13 → – |
| 39.203 | Applicability. | none | Not in the overhaul | 352 → – |
| 39.204 | Exceptions. | none | Not in the overhaul Same heading at 39.104-4 | 161 → – |
| 39.205 | Exemptions. | none | Not in the overhaul Same heading at 39.104-5 | 434 → – |
| 39.301 | none | ICT accessibility standards for task orders or delivery orders. | New number | – → 48 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress