The FAR overhaul, side by side
FAR Part 44: Subcontracting Policies and Procedures
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 24 sections, 3,205 words (Part 44 as in force, eCFR as of Oct 29, 2026). Overhaul text: 16 sections, 1,689 words (on acquisition.gov ↗, issued Sep 4, 2025). By number: 2 the same, 6 changed, 16 not in the overhaul (4 with the same heading under another number), 8 new.
44.201-1: Changed (39% alike)
Today: Consent requirements.
(a) If the contractor has an approved purchasing system, consent is required for subcontracts specifically identified by the contracting officer in the subcontracts clause of the contract. The contracting officer may require consent to subcontract if the contracting officer has determined that an individual consent action is required to protect the Government adequately because of the subcontract type, complexity, or value, or because the subcontract needs special surveillance. These can be subcontracts for critical systems, subsystems, components, or services. Subcontracts may be identified by subcontract number or by class of items (e.g., subcontracts for engines on a prime contract for airframes).
(b) If the contractor does not have an approved purchasing system, consent to subcontract is required for cost-reimbursement, time-and-materials, labor-hour, or letter contracts, and also for unpriced actions (including unpriced modifications and unpriced delivery orders) under fixed-price contracts that exceed the simplified acquisition threshold, for—
(1) Cost-reimbursement, time-and-materials, or labor-hour subcontracts; and
(2) Fixed-price subcontracts that exceed—
(i) For the Department of Defense, the Coast Guard, and the National Aeronautics and Space Administration, the greater of the simplified acquisition threshold or 5 percent of the total estimated cost of the contract; or
(ii) For civilian agencies other than the Coast Guard and the National Aeronautics and Space Administration, either the simplified acquisition threshold or 5 percent of the total estimated cost of the contract.
(c) Consent may be required for subcontracts under prime contracts for architect-engineer services.
(d) The contracting officer's written authorization for the contractor to purchase from Government sources (see part 51) constitutes consent.
Overhaul text: Consent requirements.
(a) If the contractor has an approved purchasing system, consent is required for subcontracts specifically identified by the contracting officer in paragraph (d) of 52.244-2, Subcontracts. The contracting officer may require consent to subcontract to protect the Government because of the subcontract type, complexity, or value, or because the subcontract needs special surveillance.
(b) If the contractor does not have an approved purchasing system, consent to subcontract is required for certain subcontracts identified in paragraph (c) of 52.244-2, Subcontracts.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 44.000 | Scope of part. | Scope of part. | Changed · 88% alike | 53 → 47 |
| 44.001 | none | Definitions. | New number Same heading as today's 44.101 | – → 125 |
| 44.101 | Definitions. | none | Not in the overhaul Same heading at 44.001 | 147 → – |
| 44.201 | Consent and advance notification requirements. | Consent to subcontracts and requirements for advance notice. | Same | 0 → 0 |
| 44.201-1 | Consent requirements. | Consent requirements. | Changed · 39% alike | 270 → 81 |
| 44.201-2 | Advance notification requirements. | Advance notification requirements. | Same | 145 → 145 |
| 44.201-3 | none | Contracting officer’s responsibilities. | New number | – → 170 |
| 44.201-4 | none | Consent limitations. | New number Same heading as today's 44.203 | – → 115 |
| 44.201-5 | none | Contract clauses. | New number Same heading as today's 44.204 | – → 228 |
| 44.202 | Contracting officer's evaluation. | none | Not in the overhaul | 0 → – |
| 44.202-1 | Responsibilities. | none | Not in the overhaul | 153 → – |
| 44.202-2 | Considerations. | none | Not in the overhaul | 388 → – |
| 44.203 | Consent limitations. | none | Not in the overhaul Same heading at 44.201-4 | 284 → – |
| 44.204 | Contract clauses. | none | Not in the overhaul Same heading at 44.201-5 | 257 → – |
| 44.301 | Objective. | Contractors’ purchasing systems reviews. | Changed · 0% alike | 52 → 0 |
| 44.301-1 | none | Objective. | New number | – → 47 |
| 44.301-2 | none | Requirements. | New number Same heading as today's 44.302 | – → 135 |
| 44.301-3 | none | Responsibilities for granting, withholding or withdrawing approval. | New number | – → 58 |
| 44.301-4 | none | Notice. | New number | – → 358 |
| 44.302 | Requirements. | none | Not in the overhaul Same heading at 44.301-2 | 185 → – |
| 44.303 | Extent of review. | none | Not in the overhaul | 276 → – |
| 44.304 | Surveillance. | none | Not in the overhaul | 115 → – |
| 44.305 | Granting, withholding, or withdrawing approval. | none | Not in the overhaul | 0 → – |
| 44.305-1 | Responsibilities. | none | Not in the overhaul | 63 → – |
| 44.305-2 | Notification. | none | Not in the overhaul | 216 → – |
| 44.305-3 | Withholding or withdrawing approval. | none | Not in the overhaul | 216 → – |
| 44.306 | Disclosure of approval status. | none | Not in the overhaul | 57 → – |
| 44.307 | Reports. | none | Not in the overhaul | 61 → – |
| 44.400 | Scope of subpart. | none | Not in the overhaul | 36 → – |
| 44.401 | Applicability. | Definition. | Changed · 12% alike | 26 → 25 |
| 44.402 | Policy requirements. | Requirements. | Changed · 35% alike | 175 → 138 |
| 44.403 | Contract clause. | Contract clause. | Changed · 68% alike | 30 → 17 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress