The FAR overhaul, side by side
FAR Part 45: Government Property
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 33 sections, 5,879 words (Part 45 as in force, eCFR as of Oct 29, 2026). Overhaul text: 33 sections, 5,589 words (on acquisition.gov ↗, issued Sep 11, 2025). By number: 10 the same, 23 changed, 0 not in the overhaul, 0 new.
45.107: Changed (99% alike)
Today: Contract clauses.
(a)(1) Except as provided in paragraph (d) of this section, the contracting officer shall insert the clause at 52.245-1, Government Property, in—
(i) All cost-reimbursement and time-and-material type solicitations and contracts, and labor-hour solicitations when property is expected to be furnished for the labor-hour contracts.
(ii) Fixed-price solicitations and contracts when the Government will provide Government property.
(iii) Contracts or modifications awarded under FAR Part 12 procedures where Government property that exceeds the simplified acquisition threshold, as defined in FAR 2.101, is furnished or where the contractor is directed to acquire property for use under the contract that is titled in the Government.
(2) The contracting officer shall use the clause with its Alternate I in contracts other than those identified in FAR 45.104(a), Responsibility and Liability for Government Property.
(3) The contracting officer shall use the clause with its Alternate II when a contract for the conduct of basic or applied research at nonprofit institutions of higher education or at nonprofit organizations whose primary purpose is the conduct of scientific research (see 35.014) is contemplated.
(b) The contracting officer shall also insert the clause at 52.245-2, Government Property (Installation Operation Services), in fixed-price service contracts to be performed on a Government installation when Government-furnished property will be provided for initial provisioning only and the Government is not responsible for repair or replacement.
(c) The contracting officer shall insert the clause at 52.245-9, Use and Charges, in solicitations and contracts when the clause at 52.245-1 is included.
(d) Purchase orders for property repair need not include a Government property clause when the unit acquisition cost of Government property to be repaired does not exceed the simplified acquisition threshold, unless other Government property (not for repair) is provided.
Overhaul text: Contract clauses.
(a)
(1) Except as provided in paragraph (d) of this section, the contracting officer must insert the clause at 52.245-1, Government Property, in-
(i) All cost-reimbursement and time-and-material type solicitations and contracts, and labor-hour solicitations when property is expected to be furnished for the labor-hour contracts.
(ii) Fixed-price solicitations and contracts when the Government will provide Government property.
(iii) Contracts or modifications awarded under FAR part 12 procedures where Government property that exceeds the simplified acquisition threshold, as defined in FAR 2.101, is furnished or where the contractor is directed to acquire property for use under the contract that is titled in the Government.
(2) The contracting officer must use the clause with its Alternate I in contracts other than those identified in FAR 45.104(a), Responsibility and Liability for Government Property.
(3) The contracting officer must use the clause with its Alternate II when a contract for the conduct of basic or applied research at nonprofit institutions of higher education or at nonprofit organizations whose primary purpose is the conduct of scientific research (see 35.014) is contemplated.
(b) The contracting officer must also insert the clause at 52.245-2, Government Property (Installation Operation Services), in fixed-price service contracts to be performed on a Government installation when Government-furnished property will be provided for initial provisioning only and the Government is not responsible for repair or replacement.
(c) The contracting officer shall insert the clause at 52.245-9, Use and Charges, in solicitations and contracts when the clause at 52.245-1 is included.
(d) Purchase orders for property repair need not include a Government property clause when the unit acquisition cost of Government property to be repaired does not exceed the simplified acquisition threshold, unless other Government property (not for repair) is provided.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 45.000 | Scope of part. | Scope of part. | Same | 151 → 151 |
| 45.101 | Definitions. | Definitions. | Changed · 100% alike | 866 → 866 |
| 45.102 | Policy. | Policy. | Changed · 98% alike | 185 → 186 |
| 45.103 | General. | General. | Changed · 98% alike | 158 → 158 |
| 45.104 | Responsibility and liability for Government property. | Responsibility and liability for Government property. | Changed · 69% alike | 197 → 118 |
| 45.105 | Contractors' property management system compliance. | Contractors’ property management system compliance. | Changed · 97% alike | 289 → 289 |
| 45.106 | Transferring accountability. | Transferring accountability. | Changed · 97% alike | 88 → 88 |
| 45.107 | Contract clauses. | Contract clauses. | Changed · 99% alike | 301 → 301 |
| 45.201 | Solicitation. | Solicitation. | Changed · 93% alike | 381 → 339 |
| 45.202 | Evaluation procedures. | Evaluation procedures. | Changed · 95% alike | 75 → 74 |
| 45.301 | Use and rental. | Use and rental. | Changed · 99% alike | 321 → 321 |
| 45.302 | Contracts with foreign governments or international organizations. | Contracts with foreign governments or international organizations. | Changed · 96% alike | 24 → 24 |
| 45.303 | Use of Government property on independent research and development programs. | Use of Government property on independent research and development programs. | Same | 105 → 105 |
| 45.401 | Title to Government-furnished property. | Title to Government-furnished property. | Changed · 98% alike | 47 → 47 |
| 45.402 | Title to contractor-acquired property. | Title to contractor-acquired property. | Changed · 99% alike | 152 → 152 |
| 45.501 | Prime contractor alternate locations. | Prime contractor alternate locations. | Same | 33 → 33 |
| 45.502 | Subcontractor and alternate prime contractor locations. | Subcontractor and alternate prime contractor locations. | Changed · 98% alike | 113 → 113 |
| 45.503 | Support property administrator findings. | Support property administrator findings. | Changed · 97% alike | 30 → 30 |
| 45.600 | Scope of subpart. | Scope of subpart. | Changed · 67% alike | 77 → 39 |
| 45.601 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 45.602 | Reutilization of Government property. | Reutilization of Government property. | Same | 41 → 41 |
| 45.602-1 | Inventory disposal schedules. | Inventory disposal schedules. | Changed · 89% alike | 307 → 254 |
| 45.602-2 | Reutilization priorities. | Reutilization priorities. | Changed · 100% alike | 244 → 244 |
| 45.602-3 | Screening. | Screening. | Changed · 96% alike | 843 → 856 |
| 45.602-4 | Interagency property transfer costs. | Interagency property transfer costs. | Changed · 94% alike | 91 → 90 |
| 45.603 | Abandonment or destruction of personal property. | Abandonment or destruction of personal property. | Same | 331 → 331 |
| 45.604 | Sale of surplus personal property. | Sale of surplus personal property. | Same | 0 → 0 |
| 45.604-1 | Sales procedures. | Sales procedures. | Changed · 98% alike | 49 → 49 |
| 45.604-2 | Use of GSA sponsored sales centers. | Use of GSA sponsored sales centers. | Same | 31 → 31 |
| 45.604-3 | Proceeds from sales of surplus property. | Proceeds from sales of surplus property. | Same | 50 → 50 |
| 45.604-4 | Sale of property pursuant to the exchange/sale authority. | Sale of property pursuant to the exchange/sale authority. | Same | 40 → 40 |
| 45.605 | Inventory disposal reports. | Inventory disposal reports. | Changed · 95% alike | 90 → 89 |
| 45.606 | Contractor scrap procedures. | Contractor scrap procedures. | Changed · 64% alike | 169 → 80 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress