The FAR overhaul, side by side

FAR Part 52: Solicitation Provisions and Contract Clauses

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 680 sections, 340,855 words (Part 52 as in force, eCFR as of Oct 29, 2026). Overhaul text: 765 sections, 289,132 words (on acquisition.gov ↗, issued Oct 28, 2025, updated Jul 1, 2026). By number: 124 the same, 541 changed, 15 not in the overhaul, 100 new.

52.245-1: Changed (99% alike)

Today: Government Property.

This section in plain English

As prescribed in 45.107(a), insert the following clause:

Government Property (SEP 2021)

(a) Definitions. As used in this clause—

Cannibalize means to remove parts from Government property for use or for installation on other Government property.

Contractor-acquired property means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract, and to which the Government has title.

Contractor inventory means—

(1) Any property acquired by and in the possession of a Contractor or subcontractor under a contract for which title is vested in the Government and which exceeds the amounts needed to complete full performance under the entire contract;

(2) Any property that the Government is obligated or has the option to take over under any type of contract, e.g., as a result either of any changes in the specifications or plans thereunder or of the termination of the contract (or subcontract thereunder), before completion of the work, for the convenience or at the option of the Government; and

(3) Government-furnished property that exceeds the amounts needed to complete full performance under the entire contract.

Contractor's managerial personnel means the Contractor's directors, officers, managers, superintendents, or equivalent representatives who have supervision or direction of—

(1) All or substantially all of the Contractor's business;

(2) All or substantially all of the Contractor's operation at any one plant or separate location; or

(3) A separate and complete major industrial operation.

Demilitarization means rendering a product unusable for, and not restorable to, the purpose for which it was designed or is customarily used.

Discrepancies incident to shipment means any differences (e.g., count or condition) between the items documented to have been shipped and items actually received.

Equipment means a tangible item that is functionally complete for its intended purpose, durable, nonexpendable, and needed for the performance of a contract. Equipment is not intended for sale, and does not ordinarily lose its identity or become a component part of another article when put into use. Equipment does not include material, real property, special test equipment or special tooling.

Government-furnished property means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract.

Government property means all property owned or leased by the Government. Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Loss of Government property means unintended, unforeseen or accidental loss, damage or destruction to Government property that reduces the Government's expected economic benefits of the property. Loss of Government property does not include purposeful destructive testing, obsolescence, normal wear and tear or manufacturing defects. Loss of Government property includes, but is not limited to—

(1) Items that cannot be found after a reasonable search;

(2) Theft;

(3) Damage resulting in unexpected harm to property requiring repair to restore the item to usable condition; or

(4) Destruction resulting from incidents that render the item useless for its intended purpose or beyond economical repair.

Material means property that may be consumed or expended during the performance of a contract, component parts of a higher assembly, or items that lose their individual identity through incorporation into an end item. Material does not include equipment, special tooling, special test equipment or real property.

Nonseverable means property that cannot be removed after construction or installation without substantial loss of value or damage to the installed property or to the premises where installed.

Precious metals means silver, gold, platinum, palladium, iridium, osmium, rhodium, and ruthenium.

Production scrap means unusable material resulting from production, engineering, operations and maintenance, repair, and research and development contract activities. Production scrap may have value when re-melted or reprocessed, e.g., textile and metal clippings, borings, and faulty castings and forgings.

Property means all tangible property, both real and personal.

Property Administrator means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.

Property records means the records created and maintained by the contractor in support of its stewardship responsibilities for the management of Government property.

Provide means to furnish, as in Government-furnished property, or to acquire, as in contractor-acquired property.

Real property. See Federal Management Regulation 102-71.20 (41 CFR 102-71.20).

Sensitive property means property potentially dangerous to the public safety or security if stolen, lost, or misplaced, or that shall be subject to exceptional physical security, protection, control, and accountability. Examples include weapons, ammunition, explosives, controlled substances, radioactive materials, hazardous materials or wastes, or precious metals.

Unit acquisition cost means—

(1) For Government-furnished property, the dollar value assigned by the Government and identified in the contract; and

(2) For contractor-acquired property, the cost derived from the Contractor's records that reflect consistently applied generally accepted accounting principles.

(b) Property management. (1) The Contractor shall have a system of internal controls to manage (control, use, preserve, protect, repair, and maintain) Government property in its possession. The system shall be adequate to satisfy the requirements of this clause. In doing so, the Contractor shall initiate and maintain the processes, systems, procedures, records, and methodologies necessary for effective and efficient control of Government property. The Contractor shall disclose any significant changes to its property management system to the Property Administrator prior to implementation of the changes. The Contractor may employ customary commercial practices, voluntary consensus standards, or industry-leading practices and standards that provide effective and efficient Government property management that are necessary and appropriate for the performance of this contract (except where inconsistent with law or regulation).

(2) The Contractor's responsibility extends from the initial acquisition and receipt of property, through stewardship, custody, and use until formally relieved of responsibility by authorized means, including delivery, consumption, expending, sale (as surplus property), or other disposition, or via a completed investigation, evaluation, and final determination for lost property. This requirement applies to all Government property under the Contractor's accountability, stewardship, possession or control, including its vendors or subcontractors (see paragraph (f)(1)(v) of this cluase).

(3) The Contractor shall include the requirements of this clause in all subcontracts under which Government property is acquired or furnished for subcontract performance.

(4) The Contractor shall establish and maintain procedures necessary to assess its property management system effectiveness and shall perform periodic internal reviews, surveillances, self assessments, or audits. Significant findings or results of such reviews and audits pertaining to Government property shall be made available to the Property Administrator.

(c) Use of Government property. (1) The Contractor shall use Government property, either furnished or acquired under this contract, only for performing this contract, unless otherwise provided for in this contract or approved by the Contracting Officer.

(2) Modifications or alterations of Government property are prohibited, unless they are—

(i) Reasonable and necessary due to the scope of work under this contract or its terms and conditions;

(ii) Required for normal maintenance; or

(iii) Otherwise authorized by the Contracting Officer.

(3) The Contractor shall not cannibalize Government property unless otherwise provided for in this contract or approved by the Contracting Officer.

(d) Government-furnished property. (1) The Government shall deliver to the Contractor the Government-furnished property described in this contract. The Government shall furnish related data and information needed for the intended use of the property. The warranties of suitability of use and timely delivery of Government-furnished property do not apply to property acquired or fabricated by the Contractor as contractor-acquired property and subsequently transferred to another contract with this Contractor.

(2) The delivery and/or performance dates specified in this contract are based upon the expectation that the Government-furnished property will be suitable for contract performance and will be delivered to the Contractor by the dates stated in the contract.

(i) If the property is not delivered to the Contractor by the dates stated in the contract, the Contracting Officer shall, upon the Contractor's timely written request, consider an equitable adjustment to the contract.

(ii) In the event property is received by the Contractor, or for Government-furnished property after receipt and installation, in a condition not suitable for its intended use, the Contracting Officer shall, upon the Contractor's timely written request, advise the Contractor on a course of action to remedy the problem. Such action may include repairing, replacing, modifying, returning, or otherwise disposing of the property at the Government's expense. Upon completion of the required action(s), the Contracting Officer shall consider an equitable adjustment to the contract (see also paragraph (f)(1)(ii)(A) of this clause).

(iii) The Government may, at its option, furnish property in an “as-is” condition. The Contractor will be given the opportunity to inspect such property prior to the property being provided. In such cases, the Government makes no warranty with respect to the serviceability and/or suitability of the property for contract performance. Any repairs, replacement, and/or refurbishment shall be at the Contractor's expense.

(3)(i) The Contracting Officer may by written notice, at any time—

(A) Increase or decrease the amount of Government-furnished property under this contract;

(B) Substitute other Government-furnished property for the property previously furnished, to be furnished, or to be acquired by the Contractor for the Government under this contract; or

(C) Withdraw authority to use property.

(ii) Upon completion of any action(s) under aragraph (d)(3)(i) of this clause, and the Contractor's timely written request, the Contracting Officer shall consider an equitable adjustment to the contract.

(e) Title to Government property. (1) All Government-furnished property and all property acquired by the Contractor, title to which vests in the Government under this paragraph (collectively referred to as “Government property”), is subject to the provisions of this clause. The Government shall retain title to all Government-furnished property. Title to Government property shall not be affected by its incorporation into or attachment to any property not owned by the Government, nor shall Government property become a fixture or lose its identity as personal property by being attached to any real property.

(2) Title vests in the Government for all property acquired or fabricated by the Contractor in accordance with the financing provisions or other specific requirements for passage of title in the contract. Under fixed price type contracts, in the absence of financing provisions or other specific requirements for passage of title in the contract, the Contractor retains title to all property acquired by the Contractor for use on the contract, except for property identified as a deliverable end item. If a deliverable item is to be retained by the Contractor for use after inspection and acceptance by the Government, it shall be made accountable to the contract through a contract modification listing the item as Government-furnished property.

(3) Title under Cost-Reimbursement or Time-and-Material Contracts or Cost-Reimbursable line items under Fixed-Price contracts. (i) Title to all property purchased by the Contractor for which the Contractor is entitled to be reimbursed as a direct item of cost under this contract shall pass to and vest in the Government upon the vendor's delivery of such property.

(ii) Title to all other property, the cost of which is reimbursable to the Contractor, shall pass to and vest in the Government upon—

(A) Issuance of the property for use in contract performance;

(B) Commencement of processing of the property for use in contract performance; or

(C) Reimbursement of the cost of the property by the Government, whichever occurs first.

(f) Contractor plans and systems. (1) Contractors shall establish and implement property management plans, systems, and procedures at the contract, program, site or entity level to enable the following outcomes:

(i) Acquisition of Property. The Contractor shall document that all property was acquired consistent with its engineering, production planning, and property control operations.

(ii) Receipt of Government Property. The Contractor shall receive Government property and document the receipt, record the information necessary to meet the record requirements of paragraph (f)(1)(iii)(A)(1) through (5) of this clause, identify as Government owned in a manner appropriate to the type of property (e.g., stamp, tag, mark, or other identification), and manage any discrepancies incident to shipment.

(A) Government-furnished property. The Contractor shall furnish a written statement to the Property Administrator containing all relevant facts, such as cause or condition and a recommended course(s) of action, if overages, shortages, or damages and/or other discrepancies are discovered upon receipt of Government-furnished property.

(B) Contractor-acquired property. The Contractor shall take all actions necessary to adjust for overages, shortages, damage and/or other discrepancies discovered upon receipt, in shipment of Contractor-acquired property from a vendor or supplier, so as to ensure the proper allocability and allowability of associated costs.

(iii) Records of Government property. The Contractor shall create and maintain records of all Government property accountable to the contract, including Government-furnished and Contractor-acquired property.

(A) Property records shall enable a complete, current, auditable record of all transactions and shall, unless otherwise approved by the Property Administrator, contain the following:

(1) The name, part number and description, National Stock Number (if needed for additional item identification tracking and/or disposition), and other data elements as necessary and required in accordance with the terms and conditions of the contract.

(2) Quantity received (or fabricated), issued, and balance-on-hand.

(3) Unit acquisition cost.

(4) Unique-item identifier or equivalent (if available and necessary for individual item tracking).

(5) Unit of measure.

(6) Accountable contract number or equivalent code designation.

(7) Location.

(8) Disposition.

(9) Posting reference and date of transaction.

(10) Date placed in service (if required in accordance with the terms and conditions of the contract).

(B) Use of a Receipt and Issue System for Government Material. When approved by the Property Administrator, the Contractor may maintain, in lieu of formal property records, a file of appropriately cross-referenced documents evidencing receipt, issue, and use of material that is issued for immediate consumption.

(iv) Physical inventory. The Contractor shall periodically perform, record, and disclose physical inventory results. A final physical inventory shall be performed upon contract completion or termination. The Property Administrator may waive this final inventory requirement, depending on the circumstances (e.g., overall reliability of the Contractor's system or the property is to be transferred to a follow-on contract).

(v) Subcontractor control. (A) The Contractor shall award subcontracts that clearly identify items to be provided and the extent of any restrictions or limitations on their use. The Contractor shall ensure appropriate flow down of contract terms and conditions (e.g., extent of liability for loss of Government property.

(B) The Contractor shall assure its subcontracts are properly administered and reviews are periodically performed to determine the adequacy of the subcontractor's property management system.

(vi) Reports. The Contractor shall have a process to create and provide reports of discrepancies, loss of Government property, physical inventory results, audits and self-assessments, corrective actions, and other property-related reports as directed by the Contracting Officer.

(vii) Relief of stewardship responsibility and liability. The Contractor shall have a process to enable the prompt recognition, investigation, disclosure and reporting of loss of Government property, including losses that occur at subcontractor or alternate site locations.

(A) This process shall include the corrective actions necessary to prevent recurrence.

(B) Unless otherwise directed by the Property Administrator, the Contractor shall investigate and report to the Government all incidents of property loss as soon as the facts become known. Such reports shall, at a minimum, contain the following information:

(1) Date of incident (if known).

(2) The data elements required under paragraph (f)(1)(iii)(A) of this clause.

(3) Quantity.

(4) Accountable contract number.

(5) A statement indicating current or future need.

(6) Unit acquisition cost, or if applicable, estimated sales proceeds, estimated repair or replacement costs.

(7) All known interests in commingled material of which includes Government material.

(8) Cause and corrective action taken or to be taken to prevent recurrence.

(9) A statement that the Government will receive compensation covering the loss of Government property, in the event the Contractor was or will be reimbursed or compensated.

(10) Copies of all supporting documentation.

(11) Last known location.

(12) A statement that the property did or did not contain sensitive, export controlled, hazardous, or toxic material, and that the appropriate agencies and authorities were notified.

(C) Unless the contract provides otherwise, the Contractor shall be relieved of stewardship responsibility and liability for property when—

(1) Such property is consumed or expended, reasonably and properly, or otherwise accounted for, in the performance of the contract, including reasonable inventory adjustments of material as determined by the Property Administrator;

(2) Property Administrator grants relief of responsibility and liability for loss of Government property;

(3) Property is delivered or shipped from the Contractor's plant, under Government instructions, except when shipment is to a subcontractor or other location of the Contractor; or

(4) Property is disposed of in accordance with paragraphs (j) and (k) of this clause.

(viii) Utilizing Government property. (A) The Contractor shall utilize, consume, move, and store Government Property only as authorized under this contract. The Contractor shall promptly disclose and report Government property in its possession that is excess to contract performance.

(B) Unless otherwise authorized in this contract or by the Property Administrator the Contractor shall not commingle Government material with material not owned by the Government.

(ix) Maintenance. The Contractor shall properly maintain Government property. The Contractor's maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair. The Contractor shall disclose and report to the Property Administrator the need for replacement and/or capital rehabilitation.

(x) Property closeout. The Contractor shall promptly perform and report to the Property Administrator contract property closeout, to include reporting, investigating and securing closure of all loss of Government property cases; physically inventorying all property upon termination or completion of this contract; and disposing of items at the time they are determined to be excess to contractual needs.

(2) The Contractor shall establish and maintain Government accounting source data, as may be required by this contract, particularly in the areas of recognition of acquisitions, loss of Government property, and disposition of material and equipment.

(g) Systems analysis. (1) The Government shall have access to the Contractor's premises and all Government property, at reasonable times, for the purposes of reviewing, inspecting and evaluating the Contractor's property management plan(s), systems, procedures, records, and supporting documentation that pertains to Government property. This access includes all site locations and, with the Contractor's consent, all subcontractor premises.

(2) Records of Government property shall be readily available to authorized Government personnel and shall be appropriately safeguarded.

(3) Should it be determined by the Government that the Contractor's (or subcontractor's) property management practices are inadequate or not acceptable for the effective management and control of Government property under this contract, or present an undue risk to the Government, the Contractor shall prepare a corrective action plan when requested by the Property Administrator and take all necessary corrective actions as specified by the schedule within the corrective action plan.

(h) Contractor Liability for Government Property. (1) Unless otherwise provided for in the contract, the Contractor shall not be liable for loss of Government property furnished or acquired under this contract, except when any one of the following applies—

(i) The risk is covered by insurance or the Contractor is otherwise reimbursed (to the extent of such insurance or reimbursement). The allowability of insurance costs shall be determined in accordance with 31.205-19.

(ii) Loss of Government property that is the result of willful misconduct or lack of good faith on the part of the Contractor's managerial personnel.

(iii) The Contracting Officer has, in writing, revoked the Government's assumption of risk for loss of Government property due to a determination under paragraph (g) of this clause that the Contractor's property management practices are inadequate, and/or present an undue risk to the Government, and the Contractor failed to take timely corrective action. If the Contractor can establish by clear and convincing evidence that the loss of Government property occurred while the Contractor had adequate property management practices or the loss did not result from the Contractor's failure to maintain adequate property management practices, the Contractor shall not be held liable.

(2) The Contractor shall take all reasonable actions necessary to protect the property from further loss. The Contractor shall separate the damaged and undamaged property, place all the affected property in the best possible order, and take such other action as the Property Administrator directs.

(3) The Contractor shall do nothing to prejudice the Government's rights to recover against third parties for any loss of Government property.

(4) The Contractor shall reimburse the Government for loss of Government property, to the extent that the Contractor is financially liable for such loss, as directed by the Contracting Officer.

(5) Upon the request of the Contracting Officer, the Contractor shall, at the Government's expense, furnish to the Government all reasonable assistance and cooperation, including the prosecution of suit and the execution of instruments of assignment in favor of the Government in obtaining recovery.

(i) Equitable adjustment. Equitable adjustments under this clause shall be made in accordance with the procedures of the Changes clause. However, the Government shall not be liable for breach of contract for the following:

(1) Any delay in delivery of Government-furnished property.

(2) Delivery of Government-furnished property in a condition not suitable for its intended use.

(3) An increase, decrease, or substitution of Government-furnished property.

(4) Failure to repair or replace Government property for which the Government is responsible.

(j) Contractor inventory disposal. Except as otherwise provided for in this contract, the Contractor shall not dispose of Contractor inventory until authorized to do so by the Plant Clearance Officer or authorizing official.

(1) Predisposal requirements. (i) If the Contractor determines that the property has the potential to fulfill requirements under other contracts, the Contractor, in consultation with the Property Administrator, shall request that the Contracting Officer transfer the property to the contract in question, or provide authorization for use, as appropriate. In lieu of transferring the property, the Contracting Officer may authorize the Contractor to credit the costs of Contractor-acquired property (material only) to the losing contract, and debit the gaining contract with the corresponding cost, when such material is needed for use on another contract. Property no longer needed shall be considered contractor inventory.

(ii) For any remaining Contractor-acquired property, the Contractor may purchase the property at the unit acquisition cost if desired or make reasonable efforts to return unused property to the appropriate supplier at fair market value (less, if applicable, a reasonable restocking fee that is consistent with the supplier's customary practices.)

(2) Inventory disposal schedules. (i) Absent separate contract terms and conditions for property disposition, and provided the property was not reutilized, transferred, or otherwise disposed of, the Contractor, as directed by the Plant Clearance Officer or authorizing official, shall use Standard Form 1428, Inventory Disposal Schedule or electronic equivalent, to identify and report—

(A) Government-furnished property that is no longer required for performance of this contract;

(B) Contractor-acquired property, to which the Government has obtained title under paragraph (e) of this clause, which is no longer required for performance of that contract; and

(C) Termination inventory.

(ii) The Contractor may annotate inventory disposal schedules to identify property the Contractor wishes to purchase from the Government, in the event that the property is offered for sale.

(iii) Separate inventory disposal schedules are required for aircraft in any condition, flight safety critical aircraft parts, and other items as directed by the Plant Clearance Officer.

(iv) The Contractor shall provide the information required by FAR 52.245-1(f)(1)(iii) along with the following:

(A) Any additional information that may facilitate understanding of the property's intended use.

(B) For work-in-progress, the estimated percentage of completion.

(C) For precious metals in raw or bulk form, the type of metal and estimated weight.

(D) For hazardous material or property contaminated with hazardous material, the type of hazardous material.

(E) For metals in mill product form, the form, shape, treatment, hardness, temper, specification (commercial or Government) and dimensions (thickness, width and length).

(v) Property with the same description, condition code, and reporting location may be grouped in a single line item.

(vi) Scrap should be reported by “lot” along with metal content, estimated weight and estimated value.

(3) Submission requirements. (i) The Contractor shall submit inventory disposal schedules to the Plant Clearance Officer no later than—

(A) 30 days following the Contractor's determination that a property item is no longer required for performance of this contract;

(B) 60 days, or such longer period as may be approved by the Plant Clearance Officer, following completion of contract deliveries or performance; or

(C) 120 days, or such longer period as may be approved by the Termination Contracting Officer, following contract termination in whole or in part.

(ii) Unless the Plant Clearance Officer determines otherwise, the Contractor need not identify or report production scrap on inventory disposal schedules, and may process and dispose of production scrap in accordance with its own internal scrap procedures. The processing and disposal of other types of Government-owned scrap will be conducted in accordance with the terms and conditions of the contract or Plant Clearance Officer direction, as appropriate.

(4) Corrections. The Plant Clearance Officer may—

(i) Reject a schedule for cause (e.g., contains errors, determined to be inaccurate); and

(ii) Require the Contractor to correct an inventory disposal schedule.

(5) Postsubmission adjustments. The Contractor shall notify the Plant Clearance Officer at least 10 working days in advance of its intent to remove an item from an approved inventory disposal schedule. Upon approval of the Plant Clearance Officer, or upon expiration of the notice period, the Contractor may make the necessary adjustments to the inventory schedule.

(6) Storage. (i) The Contractor shall store the property identified on an inventory disposal schedule pending receipt of disposal instructions. The Government's failure to furnish disposal instructions within 120 days following acceptance of an inventory disposal schedule may entitle the Contractor to an equitable adjustment for costs incurred to store such property on or after the 121 st day.

(ii) The Contractor shall obtain the Plant Clearance Officer's approval to remove property from the premises where the property is currently located prior to receipt of final disposition instructions. If approval is granted, any costs incurred by the Contractor to transport or store the property shall not increase the price or fee of any Government contract. The storage area shall be appropriate for assuring the property's physical safety and suitability for use. Approval does not relieve the Contractor of any liability for such property under this contract.

(7) Disposition instructions.

(i) The Contractor shall prepare for shipment, deliver f.o.b. origin, or dispose of Contractor inventory as directed by the Plant Clearance Officer Unless otherwise directed by the Contracting Officer or by the Plant Clearance Officer, the Contractor shall remove and destroy any markings identifying the property as U.S. Government-owned property prior to its disposal.

(ii) The Contracting Officer may require the Contractor to demilitarize the property prior to shipment or disposal. In such cases, the Contractor may be entitled to an equitable adjustment under paragraph (i) of this clause.

(8) Disposal proceeds. As directed by the Contracting Officer, the Contractor shall credit the net proceeds from the disposal of Contractor inventory to the contract, or to the Treasury of the United States as miscellaneous receipts.

(9) Subcontractor inventory disposal schedules. The Contractor shall require its Subcontractors to submit inventory disposal schedules to the Contractor in accordance with the requirements of paragraph (j)(3) of this clause.

(k) Abandonment of property. (1) The Government shall not abandon sensitive property or termination inventory without the Contractor's written consent.

(2) The Government, upon notice to the Contractor, may abandon any nonsensitive property in place, at which time all obligations of the Government regarding such property shall cease.

(3) Absent contract terms and conditions to the contrary, the Government may abandon parts removed and replaced from property as a result of normal maintenance actions, or removed from property as a result of the repair, maintenance, overhaul, or modification process.

(4) The Government has no obligation to restore or rehabilitate the Contractor's premises under any circumstances; however, if Government—furnished property is withdrawn or is unsuitable for the intended use, or if other Government property is substituted, then the equitable adjustment under paragraph (i) of this clause may properly include restoration or rehabilitation costs.

(l) Communication. All communications under this clause shall be in writing.

(m) Contracts outside the United States. If this contract is to be performed outside of the United States and its outlying areas, the words “Government” and “Government-furnished” (wherever they appear in this clause) shall be construed as “United States Government” and “United States Government-furnished,” respectively.

(End of clause)

Alternate I (APR 2012). As prescribed in 45.107(a)(2), substitute the following for paragraph (h)(1) of the basic clause:

(h)(1) The Contractor assumes the risk of, and shall be responsible for, any loss of Government property upon its delivery to the Contractor as Government-furnished property. However, the Contractor is not responsible for reasonable wear and tear to Government property or for Government property properly consumed in performing this contract.

Alternate II (APR 2012). As prescribed in 45.107(a)(3), substitute the following for paragraph (e)(3) of the basic clause:

(e)(3) Title to property (and other tangible personal property) purchased with funds available for research and having a unit acquisition cost of less than $5,000 shall vest in the Contractor upon acquisition or as soon thereafter as feasible; provided that the Contractor obtained the Contracting Officer's approval before each acquisition. Title to property purchased with funds available for research and having a unit acquisition cost of $5,000 or more shall vest as set forth in this contract. If title to property vests in the Contractor under this paragraph, the Contractor agrees that no costs shall be allowed for any depreciation, amortization, or use under any existing or future Government contract or subcontract thereunder. The Contractor shall furnish the Contracting Officer a list of all property to which title is vested in the Contractor under this paragraph within 10 days following the end of the calendar quarter during which it was received. Vesting title under this paragraph is subject to civil rights legislation, 42 U.S.C. 2000d. Before title is vested and by signing this contract, the Contractor accepts and agrees that—

“No person in the United States or its outlying areas shall, on the ground of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under this contemplated financial assistance (title to property).”

Overhaul text: Government Property.

On acquisition.gov ↗

As prescribed in 45.107(a) , insert the following clause:

Government Property (Sep 2021)

(a) Definitions. As used in this clause-

Cannibalize means to remove parts from Government property for use or for installation on other Government property.

Contractor-acquired property means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract, and to which the Government has title.

Contractor inventory means-

(1) Any property acquired by and in the possession of a Contractor or subcontractor under a contract for which title is vested in the Government and which exceeds the amounts needed to complete full performance under the entire contract;

(2) Any property that the Government is obligated or has the option to take over under any type of contract, e.g., as a result either of any changes in the specifications or plans thereunder or of the termination of the contract (or subcontract thereunder), before completion of the work, for the convenience or at the option of the Government; and

(3) Government-furnished property that exceeds the amounts needed to complete full performance under the entire contract.

Contractor’s managerial personnel means the Contractor’s directors, officers, managers, superintendents, or equivalent representatives who have supervision or direction of-

(1) All or substantially all of the Contractor’s business;

(2) All or substantially all of the Contractor’s operation at any one plant or separate location; or

(3) A separate and complete major industrial operation.

Demilitarization means rendering a product unusable for, and not restorable to, the purpose for which it was designed or is customarily used.

Discrepancies incident to shipment means any differences (e.g., count or condition) between the items documented to have been shipped and items actually received.

Equipment means a tangible item that is functionally complete for its intended purpose, durable, nonexpendable, and needed for the performance of a contract. Equipment is not intended for sale, and does not ordinarily lose its identity or become a component part of another article when put into use. Equipment does not include material, real property, special test equipment or special tooling.

Government-furnished property means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract.

Government property means all property owned or leased by the Government. Government property includes both Government- furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Loss of Government property means unintended, unforeseen or accidental loss, damage or destruction to Government property that reduces the Government’s expected economic benefits of the property. Loss of Government property does not include purposeful destructive testing, obsolescence, normal wear and tear or manufacturing defects. Loss of Government property includes, but is not limited to-

(1) Items that cannot be found after a reasonable search;

(2) Theft;

(3) Damage resulting in unexpected harm to property requiring repair to restore the item to usable condition; or

(4) Destruction resulting from incidents that render the item useless for its intended purpose or beyond economical repair.

Material means property that may be consumed or expended during the performance of a contract, component parts of a higher assembly, or items that lose their individual identity through incorporation into an end item. Material does not include equipment, special tooling, special test equipment or real property.

Nonseverable means property that cannot be removed after construction or installation without substantial loss of value or damage to the installed property or to the premises where installed.

Precious metals means silver, gold, platinum, palladium, iridium, osmium, rhodium, and ruthenium.

Production scrap means unusable material resulting from production, engineering, operations and maintenance, repair, and research and development contract activities. Production scrap may have value when re-melted or reprocessed, e.g., textile and metal clippings, borings, and faulty castings and forgings.

Property means all tangible property, both real and personal.

Property Administrator means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.

Property records means the records created and maintained by the contractor in support of its stewardship responsibilities for the management of Government property.

Provide means to furnish, as in Government-furnished property, or to acquire, as in contractor-acquired property.

Real property See Federal Management Regulation 102-71.20 ( 41 CFR 102-71.20 ).

Sensitive property means property potentially dangerous to the public safety or security if stolen, lost, or misplaced, or that shall be subject to exceptional physical security, protection, control, and accountability. Examples include weapons, ammunition, explosives, controlled substances, radioactive materials, hazardous materials or wastes, or precious metals.

Unit acquisition cost means-

(1) For Government-furnished property, the dollar value assigned by the Government and identified in the contract; and

(2) For contractor-acquired property, the cost derived from the Contractor’s records that reflect consistently applied generally accepted accounting principles.

(b) Property management.

(1) The Contractor shall have a system of internal controls to manage (control, use, preserve, protect, repair, and maintain) Government property in its possession. The system shall be adequate to satisfy the requirements of this clause. In doing so, the Contractor shall initiate and maintain the processes, systems, procedures, records, and methodologies necessary for effective and efficient control of Government property. The Contractor shall disclose any significant changes to its property management system to the Property Administrator prior to implementation of the changes. The Contractor may employ customary commercial practices, voluntary consensus standards, or industry-leading practices and standards that provide effective and efficient Government property management that are necessary and appropriate for the performance of this contract (except where inconsistent with law or regulation).

(2) The Contractor’s responsibility extends from the initial acquisition and receipt of property, through stewardship, custody, and use until formally relieved of responsibility by authorized means, including delivery, consumption, expending, sale (as surplus property), or other disposition, or via a completed investigation, evaluation, and final determination for lost property. This requirement applies to all Government property under the Contractor’s accountability, stewardship, possession or control, including its vendors or subcontractors (see paragraph (f)(1)(v) of this clause).

(3) The Contractor shall include the requirements of this clause in all subcontracts under which Government property is acquired or furnished for subcontract performance.

(4) The Contractor shall establish and maintain procedures necessary to assess its property management system effectiveness and shall perform periodic internal reviews, surveillances, self assessments, or audits. Significant findings or results of such reviews and audits pertaining to Government property shall be made available to the Property Administrator.

(c) Use of Government property.

(1) The Contractor shall use Government property, either furnished or acquired under this contract, only for performing this contract, unless otherwise provided for in this contract or approved by the Contracting Officer.

(2) Modifications or alterations of Government property are prohibited, unless they are-

(i) Reasonable and necessary due to the scope of work under this contract or its terms and conditions;

(ii) Required for normal maintenance; or

(iii) Otherwise authorized by the Contracting Officer.

(3) The Contractor shall not cannibalize Government property unless otherwise provided for in this contract or approved by the Contracting Officer.

(d) Government-furnished property.

(1) The Government shall deliver to the Contractor the Government-furnished property described in this contract. The Government shall furnish related data and information needed for the intended use of the property. The warranties of suitability of use and timely delivery of Government-furnished property do not apply to property acquired or fabricated by the Contractor as contractor-acquired property and subsequently transferred to another contract with this Contractor.

(2) The delivery and/or performance dates specified in this contract are based upon the expectation that the Government-furnished property will be suitable for contract performance and will be delivered to the Contractor by the dates stated in the contract.

(i) If the property is not delivered to the Contractor by the dates stated in the contract, the Contracting Officer shall, upon the Contractor’s timely written request, consider an equitable adjustment to the contract.

(ii) In the event property is received by the Contractor, or for Government-furnished property after receipt and installation, in a condition not suitable for its intended use, the Contracting Officer shall, upon the Contractor’s timely written request, advise the Contractor on a course of action to remedy the problem. Such action may include repairing, replacing, modifying, returning, or otherwise disposing of the property at the Government’s expense. Upon completion of the required action(s), the Contracting Officer shall consider an equitable adjustment to the contract (see also paragraph (f)(1)(ii)(A) of this clause).

(iii) The Government may, at its option, furnish property in an "as-is" condition. The Contractor will be given the opportunity to inspect such property prior to the property being provided. In such cases, the Government makes no warranty with respect to the serviceability and/or suitability of the property for contract performance. Any repairs, replacement, and/or refurbishment shall be at the Contractor’s expense.

(3)

(i) The Contracting Officer may by written notice, at any time-

(A) Increase or decrease the amount of Government-furnished property under this contract;

(B) Substitute other Government-furnished property for the property previously furnished, to be furnished, or to be acquired by the Contractor for the Government under this contract; or

(C) Withdraw authority to use property.

(ii) Upon completion of any action(s) under paragraph (d)(3)(i) of this clause, and the Contractor’s timely written request, the Contracting Officer shall consider an equitable adjustment to the contract.

(e) Title to Government property.

(1) All Government-furnished property and all property acquired by the Contractor, title to which vests in the Government under this paragraph (collectively referred to as "Government property"), is subject to the provisions of this clause. The Government shall retain title to all Government-furnished property. Title to Government property shall not be affected by its incorporation into or attachment to any property not owned by the Government, nor shall Government property become a fixture or lose its identity as personal property by being attached to any real property.

(2) Title vests in the Government for all property acquired or fabricated by the Contractor in accordance with the financing provisions or other specific requirements for passage of title in the contract. Under fixed price type contracts, in the absence of financing provisions or other specific requirements for passage of title in the contract, the Contractor retains title to all property acquired by the Contractor for use on the contract, except for property identified as a deliverable end item. If a deliverable item is to be retained by the Contractor for use after inspection and acceptance by the Government, it shall be made accountable to the contract through a contract modification listing the item as Government-furnished property.

(3) Title under Cost-Reimbursement or Time-and-Material Contracts or Cost-Reimbursable line items under Fixed-Price contracts .

(i) Title to all property purchased by the Contractor for which the Contractor is entitled to be reimbursed as a direct item of cost under this contract shall pass to and vest in the Government upon the vendor’s delivery of such property.

(ii) Title to all other property, the cost of which is reimbursable to the Contractor, shall pass to and vest in the Government upon-

(A) Issuance of the property for use in contract performance;

(B) Commencement of processing of the property for use in contract performance; or

(C) Reimbursement of the cost of the property by the Government, whichever occurs first.

(f) Contractor plans and systems .

(1) Contractors shall establish and implement property management plans, systems, and procedures at the contract, program, site or entity level to enable the following outcomes:

(i) Acquisition of Property. The Contractor shall document that all property was acquired consistent with its engineering, production planning, and property control operations.

(ii) Receipt of Government Property . The Contractor shall receive Government property and document the receipt, record the information necessary to meet the record requirements of paragraph (f)(1)(iii)(A)( 1 ) through ( 5 ) of this clause, identify as Government owned in a manner appropriate to the type of property ( e.g. , stamp, tag, mark, or other identification), and manage any discrepancies incident to shipment.

(A) Government-furnished property . The Contractor shall furnish a written statement to the Property Administrator containing all relevant facts, such as cause or condition and a recommended course(s) of action, if overages, shortages, or damages and/or other discrepancies are discovered upon receipt of Government-furnished property.

(B) Contractor-acquired property . The Contractor shall take all actions necessary to adjust for overages, shortages, damage and/or other discrepancies discovered upon receipt, in shipment of Contractor-acquired property from a vendor or supplier, so as to ensure the proper allocability and allowability of associated costs.

(iii) Records of Government property. The Contractor shall create and maintain records of all Government property accountable to the contract, including Government-furnished and Contractor-acquired property.

(A) Property records shall enable a complete, current, auditable record of all transactions and shall, unless otherwise approved by the Property Administrator, contain the following:

(1) The name, part number and description, National Stock Number (if needed for additional item identification tracking and/or disposition), and other data elements as necessary and required in accordance with the terms and conditions of the contract.

(2) Quantity received (or fabricated), issued, and balance-on-hand.

(3) Unit acquisition cost.

(4) Unique-item identifier or equivalent (if available and necessary for individual item tracking).

(5) Unit of measure.

(6) Accountable contract number or equivalent code designation.

(7) Location.

(8) Disposition.

(9) Posting reference and date of transaction.

(10) Date placed in service (if required in accordance with the terms and conditions of the contract).

(B) Use of a Receipt and Issue System for Government Material . When approved by the Property Administrator, the Contractor may maintain, in lieu of formal property records, a file of appropriately cross-referenced documents evidencing receipt, issue, and use of material that is issued for immediate consumption.

(iv) Physical inventory . The Contractor shall periodically perform, record, and disclose physical inventory results. A final physical inventory shall be performed upon contract completion or termination. The Property Administrator may waive this final inventory requirement, depending on the circumstances ( e.g. , overall reliability of the Contractor’s system or the property is to be transferred to a follow-on contract).

(v) Subcontractor control .

(A) The Contractor shall award subcontracts that clearly identify items to be provided and the extent of any restrictions or limitations on their use. The Contractor shall ensure appropriate flow down of contract terms and conditions ( e.g. , extent of liability for loss of Government property.

(B) The Contractor shall assure its subcontracts are properly administered and reviews are periodically performed to determine the adequacy of the subcontractor’s property management system.

(vi) Reports . The Contractor shall have a process to create and provide reports of discrepancies, loss of Government property, physical inventory results, audits and self-assessments, corrective actions, and other property-related reports as directed by the Contracting Officer.

(vii) Relief of stewardship responsibility and liability . The Contractor shall have a process to enable the prompt recognition, investigation, disclosure and reporting of loss of Government property, including losses that occur at subcontractor or alternate site locations.

(A) This process shall include the corrective actions necessary to prevent recurrence.

(B) Unless otherwise directed by the Property Administrator, the Contractor shall investigate and report to the Government all incidents of property loss as soon as the facts become known. Such reports shall, at a minimum, contain the following information:

(1) Date of incident (if known).

(2) The data elements required under paragraph (f)(1)(iii)(A) of this clause.

(3) Quantity.

(4) Accountable contract number.

(5) A statement indicating current or future need.

(6) Unit acquisition cost, or if applicable, estimated sales proceeds, estimated repair or replacement costs.

(7) All known interests in commingled material of which includes Government material.

(8) Cause and corrective action taken or to be taken to prevent recurrence.

(9) A statement that the Government will receive compensation covering the loss of Government property, in the event the Contractor was or will be reimbursed or compensated.

(10) Copies of all supporting documentation.

(11) Last known location.

(12) A statement that the property did or did not contain sensitive, export controlled, hazardous, or toxic material, and that the appropriate agencies and authorities were notified.

(C) Unless the contract provides otherwise, the Contractor shall be relieved of stewardship responsibility and liability for property when-

(1) Such property is consumed or expended, reasonably and properly, or otherwise accounted for, in the performance of the contract, including reasonable inventory adjustments of material as determined by the Property Administrator;

(2) Property Administrator grants relief of responsibility and liability for loss of Government property;

(3) Property is delivered or shipped from the Contractor's plant, under Government instructions, except when shipment is to a subcontractor or other location of the Contractor; or

(4) Property is disposed of in accordance with paragraphs (j) and (k) of this clause.

(viii) Utilizing Government property .

(A) The Contractor shall utilize, consume, move, and store Government Property only as authorized under this contract. The Contractor shall promptly disclose and report Government property in its possession that is excess to contract performance.

(B) Unless otherwise authorized in this contract or by the Property Administrator the Contractor shall not commingle Government material with material not owned by the Government.

(ix) Maintenance . The Contractor shall properly maintain Government property. The Contractor’s maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair. The Contractor shall disclose and report to the Property Administrator the need for replacement and/or capital rehabilitation.

(x) Property closeout . The Contractor shall promptly perform and report to the Property Administrator contract property closeout, to include reporting, investigating and securing closure of all loss of Government property cases; physically inventorying all property upon termination or completion of this contract; and disposing of items at the time they are determined to be excess to contractual needs.

(2) The Contractor shall establish and maintain Government accounting source data, as may be required by this contract, particularly in the areas of recognition of acquisitions, loss of Government property, and disposition of material and equipment.

(g) Systems analysis .

(1) The Government shall have access to the Contractor’s premises and all Government property, at reasonable times, for the purposes of reviewing, inspecting and evaluating the Contractor’s property management plan(s), systems, procedures, records, and supporting documentation that pertains to Government property. This access includes all site locations and, with the Contractor’s consent, all subcontractor premises.

(2) Records of Government property shall be readily available to authorized Government personnel and shall be appropriately safeguarded.

(3) Should it be determined by the Government that the Contractor’s (or subcontractor’s) property management practices are inadequate or not acceptable for the effective management and control of Government property under this contract, or present an undue risk to the Government, the Contractor shall prepare a corrective action plan when requested by the Property Administrator and take all necessary corrective actions as specified by the schedule within the corrective action plan.

(h) Contractor Liability for Government Property.

(1) Unless otherwise provided for in the contract, the Contractor shall not be liable for loss of Government property furnished or acquired under this contract, except when any one of the following applies-

(i) The risk is covered by insurance or the Contractor is otherwise reimbursed (to the extent of such insurance or reimbursement). The allowability of insurance costs shall be determined in accordance with 31.205-19.

(ii) Loss of Government property that is the result of willful misconduct or lack of good faith on the part of the Contractor’s managerial personnel.

(iii) The Contracting Officer has, in writing, revoked the Government’s assumption of risk for loss of Government property due to a determination under paragraph (g) of this clause that the Contractor’s property management practices are inadequate, and/or present an undue risk to the Government, and the Contractor failed to take timely corrective action. If the Contractor can establish by clear and convincing evidence that the loss of Government property occurred while the Contractor had adequate property management practices or the loss did not result from the Contractor’s failure to maintain adequate property management practices, the Contractor shall not be held liable.

(2) The Contractor shall take all reasonable actions necessary to protect the property from further loss. The Contractor shall separate the damaged and undamaged property, place all the affected property in the best possible order, and take such other action as the Property Administrator directs.

(3) The Contractor shall do nothing to prejudice the Government’s rights to recover against third parties for any loss of Government property.

(4) The Contractor shall reimburse the Government for loss of Government property, to the extent that the Contractor is financially liable for such loss, as directed by the Contracting Officer.

(5) Upon the request of the Contracting Officer, the Contractor shall, at the Government’s expense, furnish to the Government all reasonable assistance and cooperation, including the prosecution of suit and the execution of instruments of assignment in favor of the Government in obtaining recovery.

(i) Equitable adjustment . Equitable adjustments under this clause shall be made in accordance with the procedures of the Changes clause. However, the Government shall not be liable for breach of contract for the following:

(1) Any delay in delivery of Government-furnished property.

(2) Delivery of Government-furnished property in a condition not suitable for its intended use.

(3) An increase, decrease, or substitution of Government-furnished property.

(4) Failure to repair or replace Government property for which the Government is responsible.

(j) Contractor inventory disposal . Except as otherwise provided for in this contract, the Contractor shall not dispose of Contractor inventory until authorized to do so by the Plant Clearance Officer or authorizing official.

(1) Predisposal requirements .

(i) If the Contractor determines that the property has the potential to fulfill requirements under other contracts, the Contractor, in consultation with the Property Administrator, shall request that the Contracting Officer transfer the property to the contract in question, or provide authorization for use, as appropriate. In lieu of transferring the property, the Contracting Officer may authorize the Contractor to credit the costs of Contractor-acquired property (material only) to the losing contract, and debit the gaining contract with the corresponding cost, when such material is needed for use on another contract. Property no longer needed shall be considered contractor inventory.

(ii) For any remaining Contractor-acquired property, the Contractor may purchase the property at the unit acquisition cost if desired or make reasonable efforts to return unused property to the appropriate supplier at fair market value (less, if applicable, a reasonable restocking fee that is consistent with the supplier’s customary practices.)

(2) Inventory disposal schedules .

(i) Absent separate contract terms and conditions for property disposition, and provided the property was not reutilized, transferred, or otherwise disposed of, the Contractor, as directed by the Plant Clearance Officer or authorizing official, shall use Standard Form 1428 , Inventory Disposal Schedule or electronic equivalent, to identify and report-

(A) Government-furnished property that is no longer required for performance of this contract;

(B) Contractor-acquired property, to which the Government has obtained title under paragraph (e) of this clause, which is no longer required for performance of that contract; and

(C) Termination inventory.

(ii) The Contractor may annotate inventory disposal schedules to identify property the Contractor wishes to purchase from the Government, in the event that the property is offered for sale.

(iii) Separate inventory disposal schedules are required for aircraft in any condition, flight safety critical aircraft parts, and other items as directed by the Plant Clearance Officer.

(iv) The Contractor shall provide the information required by FAR 52.245-1 (f)(1)(iii) along with the following:

(A) Any additional information that may facilitate understanding of the property’s intended use.

(B) For work-in-progress, the estimated percentage of completion.

(C) For precious metals in raw or bulk form, the type of metal and estimated weight.

(D) For hazardous material or property contaminated with hazardous material, the type of hazardous material.

(E) For metals in mill product form, the form, shape, treatment, hardness, temper, specification (commercial or Government) and dimensions (thickness, width and length).

(v) Property with the same description, condition code, and reporting location may be grouped in a single line item.

(vi) Scrap should be reported by "lot" along with metal content, estimated weight and estimated value.

(3) Submission requirements .

(i) The Contractor shall submit inventory disposal schedules to the Plant Clearance Officer no later than-

(A) 30 days following the Contractor’s determination that a property item is no longer required for performance of this contract;

(B) 60 days, or such longer period as may be approved by the Plant Clearance Officer, following completion of contract deliveries or performance; or

(C) 120 days, or such longer period as may be approved by the Termination Contracting Officer, following contract termination in whole or in part.

(ii) Unless the Plant Clearance Officer determines otherwise, the Contractor need not identify or report production scrap on inventory disposal schedules, and may process and dispose of production scrap in accordance with its own internal scrap procedures. The processing and disposal of other types of Government-owned scrap will be conducted in accordance with the terms and conditions of the contract or Plant Clearance Officer direction, as appropriate.

(4) Corrections . The Plant Clearance Officer may-

(i) Reject a schedule for cause ( e.g. , contains errors, determined to be inaccurate); and

(ii) Require the Contractor to correct an inventory disposal schedule.

(5) Postsubmission adjustments . The Contractor shall notify the Plant Clearance Officer at least 10 working days in advance of its intent to remove an item from an approved inventory disposal schedule. Upon approval of the Plant Clearance Officer, or upon expiration of the notice period, the Contractor may make the necessary adjustments to the inventory schedule.

(6) Storage .

(i) The Contractor shall store the property identified on an inventory disposal schedule pending receipt of disposal instructions. The Government’s failure to furnish disposal instructions within 120 days following acceptance of an inventory disposal schedule may entitle the Contractor to an equitable adjustment for costs incurred to store such property on or after the 121st day.

(ii) The Contractor shall obtain the Plant Clearance Officer’s approval to remove property from the premises where the property is currently located prior to receipt of final disposition instructions. If approval is granted, any costs incurred by the Contractor to transport or store the property shall not increase the price or fee of any Government contract. The storage area shall be appropriate for assuring the property’s physical safety and suitability for use. Approval does not relieve the Contractor of any liability for such property under this contract.

(7) Disposition instructions .

(i) The Contractor shall prepare for shipment, deliver f.o.b. origin, or dispose of Contractor inventory as directed by the Plant Clearance Officer. Unless otherwise directed by the Contracting Officer or by the Plant Clearance Officer, the Contractor shall remove and destroy any markings identifying the property as U.S. Government-owned property prior to its disposal.

(ii) The Contracting Officer may require the Contractor to demilitarize the property prior to shipment or disposal. In such cases, the Contractor may be entitled to an equitable adjustment under paragraph (i) of this clause.

(8) Disposal proceeds . As directed by the Contracting Officer, the Contractor shall credit the net proceeds from the disposal of Contractor inventory to the contract, or to the Treasury of the United States as miscellaneous receipts.

(9) Subcontractor inventory disposal schedules . The Contractor shall require its Subcontractors to submit inventory disposal schedules to the Contractor in accordance with the requirements of paragraph (j)(3) of this clause.

(k) Abandonment of property .

(1) The Government shall not abandon sensitive property or termination inventory without the Contractor’s written consent.

(2) The Government, upon notice to the Contractor, may abandon any nonsensitive property in place, at which time all obligations of the Government regarding such property shall cease.

(3) Absent contract terms and conditions to the contrary, the Government may abandon parts removed and replaced from property as a result of normal maintenance actions, or removed from property as a result of the repair, maintenance, overhaul, or modification process.

(4) The Government has no obligation to restore or rehabilitate the Contractor’s premises under any circumstances; however, if Government-furnished property is withdrawn or is unsuitable for the intended use, or if other Government property is substituted, then the equitable adjustment under paragraph (i) of this clause may properly include restoration or rehabilitation costs.

(l) Communication . All communications under this clause shall be in writing.

(m) Contracts outside the United States. If this contract is to be performed outside of the United States and its outlying areas, the words "Government" and "Government-furnished" (wherever they appear in this clause) shall be construed as "United States Government" and "United States Government-furnished," respectively.

(End of clause)

Alternate I (Apr 2012) . As prescribed in 45.107 (a)(2), substitute the following for paragraph (h)(1) of the basic clause:

(h)(1) The Contractor assumes the risk of, and shall be responsible for, any loss of Government property upon its delivery to the Contractor as Government-furnished property. However, the Contractor is not responsible for reasonable wear and tear to Government property or for Government property properly consumed in performing this contract.

Alternate II (Apr 2012) . As prescribed in 45.107 (a)(3), substitute the following for paragraph (e)(3) of the basic clause:

(e)(3) Title to property (and other tangible personal property) purchased with funds available for research and having a unit acquisition cost of less than $5,000 shall vest in the Contractor upon acquisition or as soon thereafter as feasible; provided that the Contractor obtained the Contracting Officer’s approval before each acquisition. Title to property purchased with funds available for research and having a unit acquisition cost of $5,000 or more shall vest as set forth in this contract. If title to property vests in the Contractor under this paragraph, the Contractor agrees that no costs shall be allowed for any depreciation, amortization, or use under any existing or future Government contract or subcontract thereunder. The Contractor shall furnish the Contracting Officer a list of all property to which title is vested in the Contractor under this paragraph within 10 days following the end of the calendar quarter during which it was received. Vesting title under this paragraph is subject to civil rights legislation, 42 U.S.C. 2000d . Before title is vested and by signing this contract, the Contractor accepts and agrees that-

"No person in the United States or its outlying areas shall, on the ground of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under this contemplated financial assistance (title to property)."

Section by section

SectionTodayOverhaul textStatusWords
52.000Scope of part.Scope of part.Same58 → 58
52.100Scope of subpart.Scope of subpart.Same53 → 53
52.101Using part 52.Using Part 52.Changed · 98% alike869 → 869
52.102Incorporating provisions and clauses.Incorporating provisions and clauses.Changed · 98% alike410 → 403
52.103Identification of provisions and clauses.Identification of provisions and clauses.Same422 → 422
52.104Procedures for modifying and completing provisions and clauses.Procedures for modifying and completing provisions and clauses.Same188 → 188
52.105Procedures for using alternates.Procedures for using alternates.Same167 → 167
52.106[Reserved][Reserved]Same0 → 0
52.107Provisions and clauses prescribed in subpart 52.1.Provisions and clauses prescribed in subpart 52.1.Same319 → 319
52.200Scope of subpart.Scope of subpart.Same33 → 33
52.201none[Reserved]New number– → 0
52.201-1Acquisition 360: Voluntary Survey.[Reserved]Changed · 0% alike145 → 2
52.202none[Reserved]New number– → 0
52.202-1Definitions.Definitions.Changed · 98% alike167 → 164
52.203none[Reserved]New number– → 0
52.203-1[Reserved][Reserved]Same0 → 0
52.203-2Certificate of Independent Price Determination.Certificate of Independent Price Determination.Changed · 96% alike411 → 421
52.203-3Gratuities.Gratuities.Changed · 99% alike223 → 225
52.203-4[Reserved][Reserved]Same0 → 0
52.203-5Covenant Against Contingent Fees.Covenant Against Contingent Fees.Same285 → 285
52.203-6Restrictions on Subcontractor Sales to the Government.Restrictions on Subcontractor Sales to the Government.Changed · 98% alike250 → 254
52.203-7Anti-Kickback Procedures.Anti-Kickback Procedures.Changed · 100% alike636 → 637
52.203-8Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity.Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity.Changed · 99% alike235 → 234
52.203-9[Reserved][Reserved]Same0 → 0
52.203-10Price or Fee Adjustment for Illegal or Improper Activity.Price or Fee Adjustment for Illegal or Improper Activity.Changed · 99% alike513 → 512
52.203-11Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.Changed · 97% alike347 → 353
52.203-12Limitation on Payments to Influence Certain Federal Transactions.Limitation on Payments to Influence Certain Federal Transactions.Changed · 99% alike1846 → 1858
52.203-13Contractor Code of Business Ethics and Conduct.Contractor Code of Business Ethics and Conduct.Changed · 100% alike1417 → 1418
52.203-14Display of Hotline Poster(s).Display of Hotline Poster(s).Same307 → 307
52.203-15Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009[Reserved]Changed · 0% alike88 → 2
52.203-16Preventing Personal Conflicts of Interest.Preventing Personal Conflicts of Interest.Changed · 100% alike1124 → 1127
52.203-17Contractor Employee Whistleblower Rights.Contractor Employee Whistleblower Rights.Same98 → 98
52.203-18Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation.Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation.Changed · 99% alike299 → 301
52.203-19Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.Changed · 100% alike406 → 407
52.204none[Reserved]New number– → 0
52.204-1Approval of Contract.[Reserved]Changed · 0% alike45 → 2
52.204-2Security Requirements.[Reserved]Changed · 0% alike629 → 2
52.204-3Taxpayer identification.[Reserved]Changed · 0% alike400 → 2
52.204-4[Reserved][Reserved]Same0 → 0
52.204-5Women-Owned Business (Other Than Small Business).Women-Owned Business (Other Than Small Business).Changed · 97% alike133 → 135
52.204-6Unique Entity Identifier.[Reserved]Changed · 1% alike282 → 2
52.204-7System for Award Management.System for Award Management—Registration.Changed · 26% alike592 → 1158
52.204-8Annual Representations and Certifications.[Reserved]Changed · 0% alike1613 → 2
52.204-9Personal Identity Verification of Contractor Personnel.Personal Identity Verification of Contractor Personnel.Changed · 99% alike237 → 238
52.204-10Reporting Executive Compensation and First-Tier Subcontract Awards.Reporting Executive Compensation and First-Tier Subcontract Awards.Changed · 77% alike1306 → 999
52.204-11[Reserved][Reserved]Same0 → 0
52.204-12Unique Entity Identifier Maintenance.[Reserved]Changed · 0% alike141 → 2
52.204-13System for Award Management Maintenance.System for Award Management—Maintenance.Changed · 51% alike901 → 872
52.204-14Service Contract Reporting Requirements.Service Contract Reporting Requirements.Changed · 90% alike430 → 452
52.204-15Service Contract Reporting Requirements for Indefinite-Delivery Contracts.Service Contract Reporting Requirements for Indefinite-Delivery Contracts.Changed · 90% alike443 → 466
52.204-16Commercial and Government Entity Code Reporting.[Reserved]Changed · 0% alike639 → 2
52.204-17Ownership or Control of Offeror.[Reserved]Changed · 0% alike368 → 2
52.204-18Commercial and Government Entity Code Maintenance.[Reserved]Changed · 0% alike402 → 2
52.204-19Incorporation by Reference of Representations and Certifications.Incorporation by Reference of Representations and Certifications.Changed · 96% alike45 → 45
52.204-20Predecessor of Offeror.[Reserved]Changed · 0% alike313 → 2
52.204-21Basic Safeguarding of Covered Contractor Information Systems.[Reserved]Changed · 0% alike590 → 2
52.204-22Alternative Line Item Proposal.[Reserved]Changed · 0% alike159 → 2
52.204-23Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities.[Reserved]Changed · 0% alike526 → 2
52.204-24Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.[Reserved]Changed · 0% alike1177 → 2
52.204-25Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.[Reserved]Changed · 0% alike1297 → 2
52.204-26Covered Telecommunications Equipment or Services—Representation.[Reserved]Changed · 0% alike168 → 2
52.204-27Prohibition on a ByteDance Covered Application.[Reserved]Changed · 0% alike386 → 2
52.204-28Federal Acquisition Supply Chain Security Act Orders—Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts.[Reserved]Changed · 0% alike855 → 2
52.204-29Federal Acquisition Supply Chain Security Act Orders—Representation and Disclosures.[Reserved]Changed · 0% alike551 → 2
52.204-30Federal Acquisition Supply Chain Security Act Orders—Prohibition.[Reserved]Changed · 0% alike2341 → 2
52.204-90noneOfferor Identification.New number– → 983
52.204-91noneContractor Identification.New number– → 341
52.205none[Reserved]New number– → 0
52.205-52.206[Reserved]noneNot in the overhaul0 → –
52.206none[Reserved]New number– → 0
52.207none[Reserved]New number– → 0
52.207-1Notice of Standard Competition.[Reserved]Changed · 0% alike219 → 2
52.207-2Notice of Streamlined Competition.[Reserved]Changed · 0% alike164 → 2
52.207-3Right of First Refusal of Employment.[Reserved]Changed · 0% alike154 → 2
52.207-4Economic Purchase Quantity—Supplies.Economic Purchase Quantity-Supplies.Changed · 99% alike190 → 195
52.207-5Option To Purchase Equipment.Option to Purchase Equipment.Same256 → 256
52.207-6Solicitation of Offers from Small Business Concerns and Small Business Teaming Arrangements or Joint Ventures (Multiple-Award Contracts).Solicitation of Offers from Small Business Concerns and Small Business Teaming Arrangements or Joint Ventures (Multiple-Award Contracts).Changed · 99% alike318 → 322
52.208none[Reserved]New number– → 0
52.208-1none[Reserved]New number– → 0
52.208-1-52.208-3[Reserved]noneNot in the overhaul0 → –
52.208-2none[Reserved]New number– → 0
52.208-3none[Reserved]New number– → 0
52.208-4Vehicle Lease Payments.[Reserved]Changed · 1% alike253 → 2
52.208-5Condition of Leased Vehicles.[Reserved]Changed · 0% alike173 → 2
52.208-6Marking of Leased Vehicles.[Reserved]Changed · 0% alike118 → 2
52.208-7Tagging of Leased Vehicles.[Reserved]Changed · 0% alike78 → 2
52.208-8[Reserved][Reserved]Same0 → 0
52.208-9Contractor Use of Mandatory Sources of Supply or Services.Contractor Use of Mandatory Sources of Supply or Services.Changed · 97% alike298 → 311
52.208-90noneGovernment Supply Sources.New number– → 80
52.208-91noneGSA Fleet Vehicles and Related Services.New number– → 78
52.209none[Reserved]New number– → 0
52.209-1Qualification Requirements.Qualification Requirements.Changed · 97% alike463 → 481
52.209-2Prohibition on Contracting With Inverted Domestic Corporations—Representation.Prohibition on Contracting With Inverted Domestic Corporations-Representation.Changed · 68% alike130 → 177
52.209-3First Article Approval—Contractor Testing.First Article Approval-Contractor Testing.Changed · 99% alike782 → 780
52.209-4First Article Approval—Government Testing.First Article Approval-Government Testing.Changed · 97% alike793 → 787
52.209-5Certification Regarding Responsibility Matters.Certification Regarding Responsibility Matters.Changed · 79% alike912 → 639
52.209-6Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded.Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded.Changed · 98% alike508 → 509
52.209-7Information Regarding Responsibility Matters.Information Regarding Responsibility Matters.Changed · 99% alike554 → 555
52.209-8[Reserved][Reserved]Same0 → 0
52.209-9Updates of Publicly Available Information Regarding Responsibility Matters.Updates of Publicly Available Information Regarding Responsibility Matters.Changed · 92% alike452 → 435
52.209-10Prohibition on Contracting With Inverted Domestic Corporations.Prohibition on Contracting With Inverted Domestic Corporations.Changed · 96% alike236 → 238
52.209-11Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law.Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law.Changed · 94% alike301 → 269
52.209-12Certification Regarding Tax Matters.Certification Regarding Tax Matters.Same179 → 179
52.209-13Violation of Arms Control Treaties or Agreements—Certification.Violation of Arms Control Treaties or Agreements-Certification.Changed · 98% alike917 → 921
52.209-14Reserve Officer Training Corps and Military Recruiting on Campus.Reserve Officer Training Corps and Military Recruiting on Campus.Changed · 99% alike474 → 476
52.210none[Reserved]New number– → 0
52.210-1Market Research.Market Research.Changed · 60% alike157 → 141
52.211none[Reserved]New number– → 0
52.211-1Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29.[Reserved]Changed · 0% alike113 → 2
52.211-2Availability of Defense Specifications, Standards, and Data Item Descriptions in the Acquisition Streamlining and Standardization Information System (ASSIST) website.[Reserved]Changed · 0% alike95 → 2
52.211-3Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions.[Reserved]Changed · 3% alike67 → 2
52.211-4Availability for Examination of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions.[Reserved]Changed · 0% alike59 → 2
52.211-5Material Requirements.Material Requirements.Changed · 62% alike299 → 142
52.211-6Brand name or equal.[Reserved]Changed · 0% alike246 → 2
52.211-7Alternatives to Government-unique standards.[Reserved]Changed · 0% alike175 → 2
52.211-8Time of Delivery.[Reserved]Changed · 0% alike744 → 2
52.211-9Desired and Required Time of Delivery.[Reserved]Changed · 0% alike763 → 2
52.211-10Commencement, Prosecution, and Completion of Work.[Reserved]Changed · 1% alike260 → 2
52.211-11Liquidated Damages—Supplies, Services, or Research and Development.Liquidated Damages-Supplies, Services, or Research and Development.Changed · 99% alike173 → 173
52.211-12Liquidated Damages—Construction.Liquidated Damages-Construction.Changed · 98% alike104 → 104
52.211-13Time Extensions.Time Extensions.Changed · 98% alike105 → 105
52.211-14Notice of Priority Rating for National Defense, Emergency Preparedness, and Energy Program Use.Notice of Priority Rating for National Defense, Emergency Preparedness, and Energy Program Use.Changed · 95% alike85 → 85
52.211-15Defense Priority and Allocation Requirements.Defense Priority and Allocation Requirements.Changed · 98% alike55 → 55
52.211-16Variation in Quantity.[Reserved]Changed · 0% alike147 → 2
52.211-17Delivery of Excess Quantities.[Reserved]Changed · 0% alike135 → 2
52.211-18Variation in Estimated Quantity.[Reserved]Changed · 1% alike222 → 2
52.212none[Reserved]New number– → 0
52.212-1Instructions to Offerors—Commercial Products and Commercial Services.Instructions to Offerors—Commercial Products and Commercial Services.Changed · 45% alike1748 → 636
52.212-2Evaluation—Commercial Products and Commercial Services.Evaluation—Commercial Products and Commercial Services.Changed · 76% alike280 → 252
52.212-3Offeror Representations and Certifications—Commercial Products and Commercial Services.[Reserved]Changed · 0% alike7486 → 2
52.212-4Contract Terms and Conditions—Commercial Products and Commercial Services.Terms and Conditions—Commercial Products and Commercial Services.Changed · 80% alike6035 → 5966
52.212-5Contract Terms and Conditions Required To Implement Statutes or Executive Orders—Commercial Products and Commercial Services.[Reserved]Changed · 0% alike4003 → 2
52.213none[Reserved]New number– → 0
52.213-1Fast Payment Procedure.[Reserved]Changed · 0% alike659 → 2
52.213-2Invoices.[Reserved]Changed · 0% alike79 → 2
52.213-3Notice to Supplier.[Reserved]Changed · 0% alike67 → 2
52.213-4Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services).Terms and Conditions—Simplified Acquisitions (Noncommercial).Changed · 33% alike2432 → 594
52.214none[Reserved]New number– → 0
52.214-1none[Reserved]New number– → 0
52.214-1-52.214-2[Reserved]noneNot in the overhaul0 → –
52.214-2none[Reserved]New number– → 0
52.214-3Amendments to Invitations for Bids.Amendments to Invitations for Bids.Changed · 91% alike123 → 111
52.214-4False Statements in Bids.False Statements in Bids.Changed · 88% alike55 → 50
52.214-5Submission of Bids.Submission of Bids.Changed · 91% alike146 → 130
52.214-6Explanation to Prospective Bidders.Explanation to Prospective Bidders.Changed · 96% alike116 → 115
52.214-7Late submissions, modifications, and withdrawals of bids.Late Submissions, Modifications, and Withdrawals of Bids.Changed · 95% alike476 → 437
52.214-8none[Reserved]New number– → 0
52.214-8-52.214-9[Reserved]noneNot in the overhaul0 → –
52.214-9none[Reserved]New number– → 0
52.214-10Contract Award—Sealed Bidding.Contract Award-Sealed Bidding.Changed · 99% alike301 → 300
52.214-11[Reserved][Reserved]Same0 → 0
52.214-12Preparation of Bids.Preparation of Bids.Changed · 98% alike251 → 250
52.214-13[Reserved][Reserved]Same0 → 0
52.214-14Place of Performance—Sealed Bidding.Place of Performance-Sealed Bidding.Changed · 82% alike85 → 112
52.214-15Period for Acceptance of Bids.Period for Acceptance of Bids.Changed · 97% alike90 → 89
52.214-16Minimum Bid Acceptance Period.Minimum Bid Acceptance Period.Changed · 91% alike201 → 184
52.214-17[Reserved][Reserved]Same0 → 0
52.214-18Preparation of Bids—Construction.Preparation of Bids-Construction.Changed · 96% alike157 → 160
52.214-19Contract Award—Sealed Bidding—Construction.Contract Award-Sealed Bidding-Construction.Changed · 99% alike209 → 208
52.214-20Bid Samples.Bid Samples.Changed · 98% alike489 → 486
52.214-21Descriptive Literature.Descriptive Literature.Changed · 96% alike391 → 409
52.214-22Evaluation of Bids for Multiple Awards.Evaluation of Bids for Multiple Awards.Changed · 98% alike108 → 107
52.214-23Late submissions, modifications, revisions, and withdrawals of technical proposals under two-step sealed bidding.Late Submissions, Modifications, Revisions, and Withdrawals of Technical Proposals under Two-Step Sealed Bidding.Changed · 95% alike538 → 495
52.214-24Multiple Technical Proposals.Multiple Technical Proposals.Changed · 96% alike58 → 57
52.214-25Step Two of Two-Step Sealed Bidding.Step Two of Two-Step Sealed Bidding.Changed · 95% alike128 → 127
52.214-26Audit and Records—Sealed Bidding.Audit and Records-Sealed Bidding.Changed · 82% alike568 → 412
52.214-27Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding.Price Reduction for Defective Certified Cost or Pricing Data-Modifications-Sealed Bidding.Changed · 99% alike822 → 818
52.214-28Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding.Subcontractor Certified Cost or Pricing Data-Modifications-Sealed Bidding.Changed · 98% alike598 → 587
52.214-29Order of Precedence—Sealed Bidding.Order of Precedence-Sealed Bidding.Changed · 98% alike61 → 60
52.214-30[Reserved][Reserved]Same0 → 0
52.214-31Facsimile Bids.[Reserved]Changed · 0% alike279 → 2
52.214-32none[Reserved]New number– → 0
52.214-32-52.214-33[Reserved]noneNot in the overhaul0 → –
52.214-33none[Reserved]New number– → 0
52.214-34Submission of Offers in the English Language.Submission of Offers in the English Language.Changed · 94% alike44 → 43
52.214-35Submission of Offers in U.S. Currency.Submission of Offers in U.S. Currency.Changed · 94% alike45 → 44
52.215none[Reserved]New number– → 0
52.215-1Instructions to Offerors—Competitive Acquisition.Instructions to Offerors-Competitive Acquisition.Changed · 91% alike2078 → 2097
52.215-2Audit and Records—Negotiation.Audit and Records-Negotiation.Changed · 88% alike1121 → 935
52.215-3Request for Information or Solicitation for Planning Purposes.[Reserved]Changed · 0% alike109 → 2
52.215-4[Reserved][Reserved]Same0 → 0
52.215-5Facsimile Proposals.[Reserved]Changed · 1% alike236 → 2
52.215-6Place of Performance.Place of Performance.Changed · 83% alike95 → 125
52.215-7[Reserved][Reserved]Same0 → 0
52.215-8Order of Precedence—Uniform Contract Format.Order of Precedence-Uniform Contract Format.Changed · 92% alike61 → 63
52.215-9Changes or Additions to Make-or-Buy Program.Changes or Additions to Make-or-Buy Program.Changed · 96% alike430 → 431
52.215-10Price Reduction for Defective Certified Cost or Pricing Data.Price Reduction for Defective Certified Cost or Pricing Data.Changed · 100% alike732 → 731
52.215-11Price Reduction for Defective Certified Cost or Pricing Data—Modifications.Price Reduction for Defective Certified Cost or Pricing Data-Modifications.Changed · 99% alike832 → 829
52.215-12Subcontractor Certified Cost or Pricing Data.Subcontractor Certified Cost or Pricing Data.Changed · 90% alike535 → 486
52.215-13Subcontractor Certified Cost or Pricing Data—Modifications.Subcontractor Certified Cost or Pricing Data-Modifications.Changed · 92% alike640 → 609
52.215-14Integrity of Unit Prices.Integrity of Unit Prices.Changed · 98% alike264 → 263
52.215-15Pension adjustments and asset reversions.Pension Adjustments and Asset Reversions.Changed · 98% alike299 → 299
52.215-16Facilities Capital Cost of Money.Facilities Capital Cost of Money.Changed · 98% alike89 → 89
52.215-17Waiver of Facilities Capital Cost of Money.Waiver of Facilities Capital Cost of Money.Changed · 96% alike47 → 47
52.215-18Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions.Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions.Changed · 97% alike205 → 205
52.215-19Notification of Ownership Changes.Notification of Ownership Changes.Changed · 97% alike222 → 222
52.215-20Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.Changed · 96% alike895 → 894
52.215-21Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data—Modifications.Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications.Changed · 96% alike1107 → 1102
52.215-22Limitations on Pass-Through Charges—Identification of Subcontract Effort.Limitations on Pass-Through Charges-Identification of Subcontract Effort.Changed · 97% alike300 → 304
52.215-23Limitations on Pass-Through Charges.Limitations on Pass-Through Charges.Changed · 97% alike753 → 757
52.215-24-52.215-42[Reserved]noneNot in the overhaul0 → –
52.216none[Reserved]New number– → 0
52.216-1Type of Contract.Type of Contract.Changed · 69% alike36 → 62
52.216-2Economic Price Adjustment—Standard Supplies.Economic Price Adjustment-Standard Supplies.Changed · 99% alike506 → 510
52.216-3Economic Price Adjustment—Semistandard Supplies.Economic Price Adjustment-Semistandard Supplies.Changed · 99% alike591 → 595
52.216-4Economic Price Adjustment—Labor and Material.Economic Price Adjustment-Labor and Material.Changed · 99% alike629 → 637
52.216-5Price Redetermination—Prospective.Price Redetermination-Prospective.Changed · 97% alike1632 → 1672
52.216-6Price Redetermination—Retroactive.Price Redetermination-Retroactive.Changed · 97% alike1093 → 1120
52.216-7Allowable Cost and Payment.Allowable Cost and Payment.Changed · 99% alike2802 → 2785
52.216-8Fixed Fee.Fixed Fee.Changed · 94% alike202 → 180
52.216-9Fixed Fee—Construction.Fixed Fee-Construction.Changed · 95% alike224 → 212
52.216-10Incentive Fee.Incentive Fee.Changed · 97% alike978 → 976
52.216-11Cost Contract—No Fee.Cost Contract-No Fee.Changed · 70% alike195 → 118
52.216-12Cost-Sharing Contract—No Fee.Cost-Sharing Contract-No Fee.Changed · 76% alike194 → 131
52.216-13none[Reserved]New number– → 0
52.216-13-52.216-14[Reserved]noneNot in the overhaul0 → –
52.216-14none[Reserved]New number– → 0
52.216-15Predetermined Indirect Cost Rates.Predetermined Indirect Cost Rates.Changed · 100% alike507 → 507
52.216-16Incentive Price Revision—Firm Target.Incentive Price Revision-Firm Target.Changed · 97% alike1955 → 1998
52.216-17Incentive Price Revision—Successive Targets.Incentive Price Revision-Successive Targets.Changed · 97% alike2799 → 2852
52.216-18Ordering.Ordering.Changed · 100% alike210 → 210
52.216-19Order Limitations.Order Limitations.Changed · 96% alike255 → 264
52.216-20Definite Quantity.Definite Quantity.Changed · 99% alike210 → 210
52.216-21Requirements.Requirements.Changed · 92% alike943 → 860
52.216-22Indefinite Quantity.Indefinite Quantity.Changed · 61% alike255 → 562
52.216-23Execution and Commencement of Work.Execution and Commencement of Work.Changed · 86% alike92 → 69
52.216-24Limitation of Government Liability.Limitation of Government Liability.Changed · 92% alike66 → 56
52.216-25Contract Definitization.Contract Definitization.Changed · 97% alike450 → 451
52.216-26Payments of Allowable Costs Before Definitization.Payments of Allowable Costs Before Definitization.Changed · 98% alike560 → 566
52.216-27Single or Multiple Awards.Single or Multiple Awards.Changed · 98% alike60 → 60
52.216-28Multiple Awards for Advisory and Assistance Services.Multiple Awards for Advisory and Assistance Services.Changed · 99% alike69 → 69
52.216-29Time-and-Materials/Labor-Hour Proposal Requirements—Other Than Commercial Acquisition With Adequate Price Competition.Time-and-Materials/Labor-Hour Proposal Requirements—Other Than Commercial Acquisition With Adequate Price Competition.Changed · 99% alike226 → 226
52.216-30Time-and-Materials/Labor-Hour Proposal Requirements—Other Than Commercial Acquisition Without Adequate Price Competition.Time-and-Materials/Labor-Hour Proposal Requirements—Other Than Commercial Acquisition Without Adequate Price Competition.Changed · 99% alike226 → 226
52.216-31Time-and-Materials/Labor-Hour Proposal Requirements—Commercial Acquisition.Time-and-Materials/Labor-Hour Proposal Requirements—Commercial Acquisition.Changed · 98% alike102 → 102
52.216-32Task-Order and Delivery-Order Ombudsman.Task-Order and Delivery-Order Ombudsman.Changed · 98% alike353 → 356
52.217none[Reserved]New number– → 0
52.217-1[Reserved][Reserved]Same0 → 0
52.217-2Cancellation Under Multiyear Contracts.Cancellation Under Multiyear Contracts.Changed · 100% alike665 → 665
52.217-3Evaluation Exclusive of Options.Evaluation Exclusive of Options.Changed · 80% alike75 → 52
52.217-4Evaluation of Option Exercised at Time of Contract Award.Evaluation of Options Exercised at Time of Contract Award.Changed · 94% alike70 → 70
52.217-5Evaluation of Options.Evaluation of Options.Changed · 95% alike80 → 80
52.217-6Option for Increased Quantity.Option for Increased Quantity.Changed · 99% alike99 → 99
52.217-7Option for Increased Quantity—Separately Priced Line Item.Option for Increased Quantity-Separately Priced Line Item.Changed · 99% alike114 → 114
52.217-8Option To Extend Services.Option to Extend Services.Changed · 98% alike114 → 114
52.217-9Option To Extend the Term of the Contract.Option to Extend the Term of the Contract.Changed · 98% alike142 → 141
52.217-10Reverse Auction.Reverse AuctionChanged · 100% alike369 → 369
52.217-11Reverse Auction—Orders.Reverse Auction—Orders.Changed · 100% alike473 → 473
52.217-12Reverse Auction Services.Reverse Auction Services.Changed · 100% alike768 → 769
52.218[Reserved][Reserved]Same0 → 0
52.219none[Reserved]New number– → 0
52.219-1Small Business Program Representations.Small Business Program Representations.Changed · 75% alike2127 → 1395
52.219-2Equal Low Bids.Equal Low Bids.Changed · 98% alike169 → 169
52.219-3Notice of HUBZone Set-Aside or Sole-Source Award.Notice of HUBZone Set-Aside or Sole-Source Award.Changed · 93% alike349 → 327
52.219-4Notice of Price Evaluation Preference for HUBZone Small Business Concerns.Notice of Price Evaluation Preference for HUBZone Small Business Concerns.Changed · 72% alike260 → 170
52.219-5[Reserved][Reserved]Same0 → 0
52.219-6Notice of Total Small Business Set-Aside.Notice of Total Small Business Set-Aside.Changed · 95% alike315 → 313
52.219-7Notice of Partial Small Business Set-Aside.Notice of Partial Small Business Set-Aside.Changed · 98% alike424 → 427
52.219-8Utilization of Small Business Concerns.Utilization of Small Business Concerns.Changed · 77% alike1301 → 958
52.219-9Small Business Subcontracting Plan.Small Business Subcontracting Plan.Changed · 94% alike8758 → 8428
52.219-10Incentive Subcontracting Program.Incentive Subcontracting Program.Changed · 98% alike241 → 240
52.219-11Special 8(a) Contract Conditions.Special 8(a) Contract Conditions.Changed · 99% alike301 → 301
52.219-12Special 8(a) Subcontract Conditions.Special 8(a) Subcontract Conditions.Changed · 99% alike233 → 234
52.219-13Notice of Set-Aside of Orders.Notice of Set-Aside of Orders.Changed · 76% alike161 → 106
52.219-14Limitations on Subcontracting.Limitations on Subcontracting.Changed · 94% alike881 → 818
52.219-15[Reserved][Reserved]Same0 → 0
52.219-16Liquidated Damages—Subcontracting Plan.Liquidated Damages-Subcontracting Plan.Changed · 85% alike443 → 392
52.219-17Section 8(a) Award.Section 8(a) Award.Changed · 99% alike278 → 278
52.219-18Notification of Competition Limited to Eligible 8(a) Participants.Notification of Competition Limited to Eligible 8(a) Participants.Changed · 100% alike424 → 424
52.219-19none[Reserved]New number– → 0
52.219-19-52.219-26[Reserved]noneNot in the overhaul0 → –
52.219-20none[Reserved]New number– → 0
52.219-21none[Reserved]New number– → 0
52.219-22none[Reserved]New number– → 0
52.219-23none[Reserved]New number– → 0
52.219-24none[Reserved]New number– → 0
52.219-25none[Reserved]New number– → 0
52.219-26none[Reserved]New number– → 0
52.219-27Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program.Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program.Changed · 83% alike619 → 525
52.219-28Postaward Small Business Program Rerepresentation.Postaward Small Business Program Rerepresentation.Changed · 72% alike1652 → 1167
52.219-29Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns.Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns.Changed · 89% alike432 → 378
52.219-30Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program.Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program.Changed · 88% alike476 → 421
52.219-31Notice of Small Business Reserve.Notice of Small Business Reserve.Changed · 97% alike89 → 88
52.219-32Orders Issued Directly Under Small Business Reserves.[Reserved]Changed · 0% alike86 → 2
52.219-33Nonmanufacturer Rule.Nonmanufacturer Rule.Changed · 88% alike482 → 418
52.220none[Reserved]New number– → 0
52.221[Reserved][Reserved]Same0 → 0
52.222none[Reserved]New number– → 0
52.222-1Notice to the Government of Labor Disputes.Notice to the Government of Labor Disputes.Changed · 92% alike60 → 60
52.222-2Payment for Overtime Premiums.Payment for Overtime Premiums.Changed · 94% alike283 → 283
52.222-3Convict Labor.Convict Labor.Changed · 98% alike300 → 300
52.222-4Contract Work Hours and Safety Standards—Overtime Compensation.Contract Work Hours and Safety Standards -Overtime Compensation.Changed · 96% alike531 → 537
52.222-5Construction Wage Rate Requirements—Secondary Site of the Work.Construction Wage Rate Requirements-Secondary Site of the Work.Changed · 96% alike168 → 169
52.222-6Construction Wage Rate Requirements.Construction Wage Rate Requirements.Changed · 83% alike1348 → 1083
52.222-7Withholding of Funds.Withholding of Funds.Changed · 97% alike191 → 193
52.222-8Payrolls and Basic Records.Payrolls and Basic Records.Changed · 98% alike898 → 902
52.222-9Apprentices and Trainees.Apprentices and Trainees.Changed · 98% alike809 → 813
52.222-10Compliance With Copeland Act Requirements.Compliance with Copeland Act Requirements.Changed · 88% alike40 → 42
52.222-11Subcontracts (Labor Standards).Subcontracts (Labor Standards).Changed · 98% alike496 → 498
52.222-12Contract Termination—Debarment.Contract Termination-Debarment.Changed · 96% alike86 → 89
52.222-13Compliance With Construction Wage Rate Requirements and Related Regulations.Compliance with Construction Wage Rate Requirements and Related Regulations.Changed · 96% alike53 → 55
52.222-14Disputes Concerning Labor Standards.Disputes Concerning Labor Standards.Changed · 95% alike93 → 95
52.222-15Certification of Eligibility.Certification of Eligibility.Changed · 97% alike122 → 125
52.222-16Approval of Wage Rates.Approval of Wage Rates.Changed · 98% alike153 → 154
52.222-17[Reserved][Reserved]Same0 → 0
52.222-18Certification Regarding Knowledge of Child Labor for Listed End Products.Certification Regarding Knowledge of Child Labor for Listed End Products.Changed · 96% alike302 → 315
52.222-19Child Labor—Cooperation with Authorities and Remedies.Child Labor-Cooperation with Authorities and Remedies.Changed · 97% alike465 → 463
52.222-20Contracts for Materials, Supplies, Articles, and Equipment.Contracts for Materials, Supplies, Articles, and Equipment.Changed · 97% alike203 → 205
52.222-21Prohibition of segregated facilities.[Reserved]Changed · 0% alike277 → 2
52.222-22Previous Contracts and Compliance Reports.[Reserved]Changed · 0% alike75 → 2
52.222-23Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity for Construction.[Reserved]Changed · 0% alike455 → 2
52.222-24Preaward On-Site Equal Opportunity Compliance Evaluation.[Reserved]Changed · 0% alike97 → 0
52.222-25Affirmative Action Compliance.[Reserved]Changed · 0% alike88 → 2
52.222-26Equal Opportunity.[Reserved]Changed · 0% alike1437 → 2
52.222-27Affirmative Action Compliance Requirements for Construction.[Reserved]Changed · 0% alike2252 → 2
52.222-28[Reserved][Reserved]Same0 → 0
52.222-29Notification of visa denial.[Reserved]Changed · 0% alike259 → 2
52.222-30Construction Wage Rate Requirements—Price Adjustment (None or Separately Specified Method).Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Method).Changed · 98% alike163 → 164
52.222-31Construction Wage Rate Requirements—Price Adjustment (Percentage Method).Construction Wage Rate Requirements-Price Adjustment (Percentage Method).Changed · 99% alike307 → 309
52.222-32Construction Wage Rate Requirements—Price Adjustment (Actual Method).Construction Wage Rate Requirements-Price Adjustment (Actual Method).Changed · 91% alike709 → 812
52.222-33Notice of Requirement for Project Labor Agreement.Notice of Requirement for Project Labor Agreement.Changed · 96% alike563 → 569
52.222-34Project Labor Agreement.Project Labor Agreement.Changed · 97% alike856 → 863
52.222-35Equal Opportunity for Veterans.Equal Opportunity for Veterans.Changed · 88% alike232 → 230
52.222-36Equal Opportunity for Workers with Disabilities.Equal Opportunity for Workers with Disabilities.Changed · 94% alike219 → 226
52.222-37Employment Reports on Veterans.Employment Reports on Veterans.Changed · 89% alike468 → 405
52.222-38Compliance with Veterans' Employment Reporting Requirements.[Reserved]Changed · 0% alike72 → 2
52.222-39[Reserved][Reserved]Same0 → 0
52.222-40Notification of Employee Rights Under the National Labor Relations Act.Notification of Employee Rights Under the National Labor Relations Act.Changed · 98% alike673 → 676
52.222-41Service Contract Labor Standards.Service Contract Labor Standards.Changed · 97% alike3689 → 3717
52.222-42Statement of Equivalent Rates for Federal Hires.Statement of Equivalent Rates for Federal Hires.Changed · 93% alike97 → 104
52.222-43Fair Labor Standards Act and Service Contract Labor Standards—Price Adjustment (Multiple Year and Option Contracts).Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts).Changed · 97% alike620 → 619
52.222-44Fair Labor Standards Act and Service Contract Labor Standards—Price Adjustment.Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment.Changed · 97% alike414 → 414
52.222-45[Reserved][Reserved]Same0 → 0
52.222-46Evaluation of Compensation for Professional Employees.[Reserved]Changed · 0% alike409 → 2
52.222-47[Reserved][Reserved]Same0 → 0
52.222-48Exemption From Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Certification.Changed · 98% alike542 → 543
52.222-49Service Contract Labor Standards—Place of Performance Unknown.Service Contract Labor Standards-Place of Performance Unknown.Changed · 97% alike163 → 164
52.222-50Combating Trafficking in Persons.Combating Trafficking in Persons.Changed · 98% alike3211 → 3237
52.222-51Exemption From Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Requirements.Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements.Changed · 98% alike389 → 390
52.222-52Exemption From Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Certification.Changed · 99% alike577 → 578
52.222-53Exemption From Application of the Service Contract Labor Standards to Contracts for Certain Services—Requirements.Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements.Changed · 97% alike546 → 547
52.222-54Employment Eligibility Verification.Employment Eligibility Verification.Changed · 97% alike1286 → 1302
52.222-55Minimum Wages for Contractor Workers Under Executive Order 14026.Minimum Wages for Contractor Workers Under Executive Order 14026.Changed · 99% alike1913 → 1913
52.222-56Certification Regarding Trafficking in Persons Compliance Plan.Certification Regarding Trafficking in Persons Compliance Plan.Changed · 98% alike246 → 247
52.222-57none[Reserved]New number– → 0
52.222-57-52.222-61[Reserved]noneNot in the overhaul0 → –
52.222-58none[Reserved]New number– → 0
52.222-59none[Reserved]New number– → 0
52.222-60none[Reserved]New number– → 0
52.222-61none[Reserved]New number– → 0
52.222-62Paid Sick Leave Under Executive Order 13706.Paid Sick Leave Under Executive Order 13706.Changed · 98% alike2524 → 2542
52.222-90noneAddressing DEI Discrimination by Federal Contractors.New number– → 333
52.223none[Reserved]New number– → 0
52.223-1Biobased Product Certification.Biobased Product Certification.Changed · 92% alike115 → 113
52.223-2Reporting of Biobased Products Under Service and Construction Contracts.Reporting of Biobased Products Under Service and Construction Contracts.Changed · 90% alike248 → 244
52.223-3Hazardous Material Identification and Material Safety Data.Hazardous Material Identification and Safety Data.Changed · 98% alike680 → 682
52.223-4Recovered Material Certification.Recovered Material Certification.Changed · 99% alike81 → 81
52.223-5Pollution Prevention and Right-to-Know Information.Pollution Prevention and Right-to-Know Information.Changed · 97% alike170 → 171
52.223-6[Reserved][Reserved]Same0 → 0
52.223-7Notice of Radioactive Materials.Notice of Radioactive Materials.Changed · 88% alike420 → 410
52.223-8[Reserved][Reserved]Same0 → 0
52.223-9Estimate of Percentage of Recovered Material Content for EPA-Designated Items.Estimate of Percentage of Recovered Material Content for EPA-Designated Items.Changed · 99% alike285 → 286
52.223-10Waste Reduction Program.[Reserved]Changed · 0% alike203 → 2
52.223-11Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons.Ozone-Depleting Substances.Changed · 62% alike293 → 153
52.223-12Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners.Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners.Changed · 29% alike332 → 65
52.223-13none[Reserved]New number– → 0
52.223-13—52.223-18[Reserved]noneNot in the overhaul0 → –
52.223-14none[Reserved]New number– → 0
52.223-15none[Reserved]New number– → 0
52.223-16none[Reserved]New number– → 0
52.223-17none[Reserved]New number– → 0
52.223-18none[Reserved]New number– → 0
52.223-19Compliance with Environmental Management Systems.[Reserved]Changed · 0% alike65 → 2
52.223-20Aerosols.[Reserved]Changed · 0% alike247 → 2
52.223-21Foams.[Reserved]Changed · 0% alike245 → 2
52.223-22Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation.[Reserved]Changed · 0% alike253 → 2
52.223-23Sustainable Products and Services.Sustainable Products.Changed · 41% alike675 → 263
52.224none[Reserved]New number– → 0
52.224-1Privacy Act Notification.Privacy Act Notification.Changed · 84% alike93 → 71
52.224-2Privacy Act.Privacy Act.Changed · 97% alike450 → 429
52.224-3Privacy Training.Privacy Training.Changed · 100% alike554 → 555
52.225none[Reserved]New number– → 0
52.225-1Buy American—Supplies.Buy American-SuppliesChanged · 99% alike1055 → 1054
52.225-2Buy American Certificate.Buy American Certificate.Changed · 96% alike230 → 249
52.225-3Buy American—Free Trade Agreements—Israeli Trade Act.Buy American-Free Trade Agreements-Israeli Trade Act.Changed · 99% alike2169 → 2165
52.225-4Buy American—Free Trade Agreements—Israeli Trade Act Certificate.Buy American-Free Trade Agreements-Israeli Trade Act Certificate.Changed · 88% alike500 → 447
52.225-5Trade Agreements.Trade Agreements.Changed · 99% alike1200 → 1202
52.225-6Trade Agreements Certificate.Trade Agreements Certificate.Changed · 98% alike179 → 185
52.225-7Waiver of Buy American Statute for Civil Aircraft and Related Articles.Waiver of Buy American Statute for Civil Aircraft and Related Articles.Changed · 99% alike326 → 327
52.225-8Duty-Free Entry.Duty-Free Entry.Changed · 100% alike769 → 770
52.225-9Buy American—Construction Materials.Buy American-Construction Materials.Changed · 99% alike2045 → 2068
52.225-10Notice of Buy American Requirement—Construction Materials.Notice of Buy American Requirement-Construction Materials.Changed · 99% alike554 → 557
52.225-11Buy American—Construction Materials Under Trade Agreements.Buy American-Construction Materials under Trade Agreements.Changed · 94% alike2930 → 2680
52.225-12Notice of Buy American Requirement—Construction Materials Under Trade Agreements.Notice of Buy American Requirement-Construction Materials Under Trade Agreements.Changed · 99% alike830 → 833
52.225-13Restrictions on Certain Foreign Purchases.[Reserved]Changed · 0% alike219 → 2
52.225-14Inconsistency between English Version and Translation of Contract.Inconsistency between English Version and Translation of Contract.Changed · 94% alike45 → 44
52.225-15none[Reserved]New number– → 0
52.225-15-52.225-16[Reserved]noneNot in the overhaul0 → –
52.225-16none[Reserved]New number– → 0
52.225-17Evaluation of Foreign Currency Offers.Evaluation of Foreign Currency Offers.Changed · 98% alike103 → 103
52.225-18Place of Manufacture.Place of Manufacture.Changed · 99% alike233 → 234
52.225-19Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission Outside the United States.Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission Outside the United States.Changed · 99% alike2172 → 2192
52.225-20Prohibition on Conducting Restricted Business Operations in Sudan—Certification.[Reserved]Changed · 0% alike316 → 2
52.225-21Required Use of American Iron, Steel, and Manufactured Goods—Buy American Statute—Construction Materials.[Reserved]Changed · 0% alike1104 → 2
52.225-22Notice of Required Use of American Iron, Steel, and Manufactured Goods—Buy American Statute—Construction Materials.[Reserved]Changed · 0% alike727 → 2
52.225-23Required Use of American Iron, Steel, and Manufactured Goods—Buy American Statute—Construction Materials Under Trade Agreements.[Reserved]Changed · 0% alike2210 → 2
52.225-24Notice of Required Use of American Iron, Steel, and Manufactured Goods—Buy American Statute—Construction Materials Under Trade Agreements.[Reserved]Changed · 0% alike1018 → 2
52.225-25Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications.[Reserved]Changed · 0% alike540 → 2
52.225-26Contractors Performing Private Security Functions Outside the United States.Contractors Performing Private Security Functions Outside the United States.Changed · 99% alike1092 → 1095
52.226[Reserved][Reserved]Same0 → 0
52.226-1Utilization of Indian Organizations and Indian-Owned Economic Enterprises.Utilization of Indian Organizations and Indian-Owned Economic Enterprises.Changed · 86% alike606 → 571
52.226-2Historically Black College or University and Minority Institution Representation.Historically Black College or University and Minority Institution Representation.Changed · 93% alike119 → 121
52.226-3Disaster or Emergency Area Representation.Disaster or Emergency Area Representation.Changed · 100% alike333 → 334
52.226-4Notice of Disaster or Emergency Area Set-Aside.Notice of Disaster or Emergency Area Set-Aside.Changed · 98% alike73 → 74
52.226-5Restrictions on Subcontracting Outside Disaster or Emergency Area.Restrictions on Subcontracting Outside Disaster or Emergency Area.Changed · 97% alike273 → 280
52.226-6Promoting Excess Food Donation to Nonprofit Organizations.Promoting Excess Food Donation to Nonprofit Organizations.Changed · 76% alike371 → 283
52.226-7Drug-Free Workplace.Drug-Free Workplace.Changed · 99% alike707 → 709
52.226-8Encouraging Contractor Policies To Ban Text Messaging While Driving.Encouraging Contractor Policies to Ban Text Messaging While Driving.Changed · 99% alike356 → 359
52.227none[Reserved]New number– → 0
52.227-1Authorization and Consent.Authorization and Consent.Changed · 100% alike465 → 466
52.227-2Notice and Assistance Regarding Patent and Copyright Infringement.Notice and Assistance Regarding Patent and Copyright Infringement.Same197 → 197
52.227-3Patent Indemnity.Patent Indemnity.Changed · 100% alike464 → 466
52.227-4Patent Indemnity—Construction Contracts.Patent Indemnity-Construction Contracts.Changed · 99% alike157 → 158
52.227-5Waiver of Indemnity.Waiver of Indemnity.Changed · 90% alike67 → 82
52.227-6Royalty Information.Royalty Information.Changed · 99% alike241 → 243
52.227-7Patents—Notice of Government Licensee.[Reserved]Changed · 0% alike111 → 2
52.227-8[Reserved][Reserved]Same0 → 0
52.227-9Refund of Royalties.Refund of Royalties.Changed · 99% alike335 → 339
52.227-10Filing of Patent Applications—Classified Subject Matter.Filing of Patent Applications-Classified Subject Matter.Same429 → 429
52.227-11Patent Rights—Ownership by the Contractor.Patent Rights-Ownership by the Contractor.Changed · 100% alike2981 → 2983
52.227-12[Reserved][Reserved]Same0 → 0
52.227-13Patent Rights—Ownership by the Government.Patent Rights-Ownership by the Government.Changed · 100% alike2644 → 2645
52.227-14Rights in Data—General.Rights in Data-General.Changed · 100% alike3372 → 3372
52.227-15Representation of Limited Rights Data and Restricted Computer Software.Representation of Limited Rights Data and Restricted Computer Software.Same297 → 297
52.227-16Additional Data Requirements.Additional Data Requirements.Changed · 100% alike229 → 229
52.227-17Rights in Data—Special Works.Rights in Data-Special Works.Changed · 99% alike754 → 757
52.227-18Rights in Data—Existing Works.[Reserved]Changed · 0% alike250 → 2
52.227-19Commercial Computer Software License.[Reserved]Changed · 0% alike342 → 2
52.227-20Rights in Data—SBIR Program.Rights in Data-SBIR Program.Changed · 100% alike1682 → 1683
52.227-21Technical Data Declaration, Revision, and Withholding of Payment—Major Systems.Technical Data Declaration, Revision, and Withholding of Payment-Major Systems.Same527 → 527
52.227-22Major System—Minimum Rights.Major System-Minimum Rights.Changed · 99% alike111 → 111
52.227-23Rights to Proposal Data (Technical).[Reserved]Changed · 0% alike82 → 2
52.228none[Reserved]New number– → 0
52.228-1Bid Guarantee.Bid Guarantee.Changed · 100% alike262 → 262
52.228-2Additional Bond Security.Additional Bond Security.Same161 → 161
52.228-3Workers' Compensation Insurance (Defense Base Act).Workers’ Compensation Insurance (Defense Base Act).Changed · 99% alike429 → 429
52.228-4Workers' Compensation and War-Hazard Insurance Overseas.Workers’ Compensation and War-Hazard Insurance Overseas.Changed · 98% alike395 → 395
52.228-5Insurance—Work on a Government Installation.Insurance-Work on a Government Installation.Same217 → 217
52.228-6[Reserved][Reserved]Same0 → 0
52.228-7Insurance—Liability to Third Persons.Insurance-Liability to Third Persons.Changed · 100% alike745 → 745
52.228-8Liability and Insurance—Leased Motor Vehicles.Liability and Insurance-Leased Motor Vehicles.Same333 → 333
52.228-9Cargo Insurance.Cargo Insurance.Same205 → 205
52.228-10Vehicular and General Public Liability Insurance.Vehicular and General Public Liability Insurance.Same141 → 141
52.228-11Individual Surety—Pledge of Assets.Individual Surety—Pledge of Assets.Changed · 100% alike438 → 439
52.228-12Prospective Subcontractor Requests for Bonds.Prospective Subcontractor Requests for Bonds.Same104 → 104
52.228-13Alternative Payment Protections.Alternative Payment Protections.Changed · 99% alike162 → 162
52.228-14Irrevocable Letter of Credit.Irrevocable Letter of Credit.Changed · 97% alike1444 → 1510
52.228-15Performance and Payment Bonds—Construction.Performance and Payment Bonds-Construction.Changed · 98% alike470 → 473
52.228-16Performance and Payment Bonds—Other Than Construction.Performance and Payment Bonds-Other Than Construction.Changed · 99% alike401 → 401
52.228-17Individual Surety—Pledge of Assets (Bid Guarantee).Individual Surety—Pledge of Assets (Bid Guarantee).Changed · 99% alike145 → 143
52.229none[Reserved]New number– → 0
52.229-1State and Local Taxes.State and Local Taxes.Same95 → 95
52.229-2North Carolina State and Local Sales and Use Tax.North Carolina State and Local Sales and Use Tax.Changed · 94% alike623 → 618
52.229-3Federal, State, and Local Taxes.Federal, State, and Local Taxes.Changed · 96% alike542 → 543
52.229-4Federal, State, and Local Taxes (State and Local Adjustments).Federal, State, and Local Taxes (State and Local Adjustments).Changed · 98% alike780 → 781
52.229-5[Reserved][Reserved]Same0 → 0
52.229-6Taxes—Foreign Fixed-Price Contracts.Taxes-Foreign Fixed-Price Contracts.Changed · 95% alike1027 → 1036
52.229-7Taxes—Fixed-Price Contracts With Foreign Governments.Taxes-Fixed-Price Contracts with Foreign Governments.Changed · 94% alike250 → 257
52.229-8Taxes—Foreign Cost-Reimbursement Contracts.Taxes-Foreign Cost-Reimbursement Contracts.Changed · 94% alike149 → 150
52.229-9Taxes—Cost-Reimbursement Contracts With Foreign Governments.Taxes-Cost-Reimbursement Contracts with Foreign Governments.Changed · 92% alike145 → 146
52.229-10State of New Mexico Gross Receipts and Compensating Tax.State of New Mexico Gross Receipts and Compensating Tax.Changed · 87% alike554 → 556
52.229-11Tax on Certain Foreign Procurements—Notice and Representation.Tax on Certain Foreign Procurements—Notice and Representation.Changed · 98% alike648 → 649
52.229-12Tax on Certain Foreign Procurements.Tax on Certain Foreign Procurements.Changed · 98% alike738 → 737
52.229-13Taxes—Foreign Contracts in Afghanistan.[Reserved]Changed · 0% alike314 → 2
52.229-14Taxes—Foreign Contracts in Afghanistan (North Atlantic Treaty Organization Status of Forces Agreement).[Reserved]Changed · 0% alike308 → 2
52.230none[Reserved]New number– → 0
52.230-1Cost Accounting Standards Notices and Certification.Cost Accounting Standards Notices and Certification.Changed · 92% alike1149 → 1072
52.230-2Cost Accounting Standards.Cost Accounting Standards.Changed · 99% alike964 → 962
52.230-3Disclosure and Consistency of Cost Accounting Practices.Disclosure and Consistency of Cost Accounting Practices.Changed · 99% alike668 → 666
52.230-4Disclosure and Consistency of Cost Accounting Practices—Foreign Concerns.Disclosure and Consistency of Cost Accounting Practices-Foreign Concerns.Changed · 98% alike663 → 662
52.230-5Cost Accounting Standards—Educational Institution.Cost Accounting Standards-Educational Institution.Changed · 99% alike1137 → 1135
52.230-6Administration of Cost Accounting Standards.Administration of Cost Accounting Standards.Changed · 98% alike3076 → 3120
52.230-7Proposal Disclosure—Cost Accounting Practice Changes.Proposal Disclosure-Cost Accounting Practice Changes.Changed · 99% alike115 → 114
52.231[Reserved][Reserved]Same0 → 0
52.232none[Reserved]New number– → 0
52.232-1Payments.Payments.Changed · 85% alike143 → 106
52.232-2Payments Under Fixed-Price Research and Development Contracts.Payments under Fixed-Price Research and Development Contracts.Changed · 86% alike112 → 84
52.232-3Payments Under Personal Services Contracts.Payments under Personal Services Contracts.Changed · 90% alike155 → 135
52.232-4Payments Under Transportation Contracts and Transportation-Related Services Contracts.Payments under Transportation Contracts and Transportation-Related Services Contracts.Changed · 82% alike77 → 54
52.232-5Payments Under Fixed-Price Construction Contracts.Payments under Fixed-Price Construction Contracts.Changed · 98% alike1140 → 1150
52.232-6Payment Under Communication Service Contracts With Common Carriers.Payment under Communication Service Contracts with Common Carriers.Changed · 86% alike95 → 71
52.232-7Payments under Time-and-Materials and Labor-Hour Contracts.Payments under Time-and-Materials and Labor-Hour Contracts.Changed · 100% alike2106 → 2113
52.232-8Discounts for Prompt Payment.Discounts for Prompt Payment.Same225 → 225
52.232-9Limitation on Withholding of Payments.Limitation on Withholding of Payments.Changed · 79% alike191 → 129
52.232-10Payments Under Fixed-Price Architect-Engineer Contracts.Payments under Fixed-Price Architect-Engineer Contracts.Same409 → 409
52.232-11Extras.Extras.Changed · 74% alike78 → 46
52.232-12Advance Payments.Advance Payments.Changed · 98% alike6388 → 6442
52.232-13Notice of Progress Payments.Notice of Progress Payments.Changed · 95% alike140 → 126
52.232-14Notice of Availability of Progress Payments Exclusively for Small Business Concerns.Notice of Availability of Progress Payments Exclusively for Small Business Concerns.Changed · 79% alike103 → 67
52.232-15Progress Payments Not Included.Progress Payments Not Included.Changed · 85% alike82 → 61
52.232-16Progress Payments.Progress Payments.Changed · 100% alike3156 → 3168
52.232-17Interest.Interest.Changed · 100% alike448 → 449
52.232-18Availability of Funds.Availability of Funds.Same94 → 94
52.232-19Availability of Funds for the Next Fiscal Year.Availability of Funds for the Next Fiscal Year.Same112 → 112
52.232-20Limitation of Cost.Limitation of Cost.Changed · 96% alike643 → 606
52.232-21[Reserved][Reserved]Same0 → 0
52.232-22Limitation of Funds.Limitation of Funds.Changed · 98% alike1053 → 1016
52.232-23Assignment of Claims.Assignment of Claims.Changed · 99% alike274 → 272
52.232-24Prohibition of Assignment of Claims.Prohibition of Assignment of Claims.Changed · 96% alike42 → 41
52.232-25Prompt payment.Prompt Payment.Changed · 99% alike2125 → 2129
52.232-26Prompt Payment for Fixed-Price Architect-Engineer Contracts.Prompt Payment for Fixed-Price Architect-Engineer Contracts.Changed · 99% alike1635 → 1644
52.232-27Prompt Payment for Construction Contracts.Prompt Payment for Construction Contracts.Changed · 99% alike3284 → 3314
52.232-28Invitation To Propose Performance-Based Payments.Invitation to Propose Performance-Based Payments.Same459 → 459
52.232-29Terms for Financing of Purchases of Commercial Products and Commercial Services.Terms for Financing of Purchases of Commercial Products and Commercial Services.Changed · 98% alike640 → 647
52.232-30Installment Payments for Commercial Products and Commercial Services.Installment Payments for Commercial Products and Commercial Services.Changed · 98% alike1018 → 1029
52.232-31Invitation To Propose Financing Terms.Invitation to Propose Financing Terms.Same385 → 385
52.232-32Performance-Based Payments.Performance-Based Payments.Changed · 99% alike1933 → 1942
52.232-33Payment by Electronic Funds Transfer—System for Award Management.Payment by Electronic Funds Transfer-System for Award Management.Changed · 99% alike863 → 871
52.232-34Payment by Electronic Funds Transfer—Other than System for Award Management.Payment by Electronic Funds Transfer-Other than System for Award Management.Changed · 99% alike1345 → 1352
52.232-35Designation of Office for Government Receipt of Electronic Funds Transfer Information.Designation of Office for Government Receipt of Electronic Funds Transfer Information.Same162 → 162
52.232-36Payment by Third Party.Payment by Third Party.Changed · 97% alike529 → 535
52.232-37Multiple Payment Arrangements.Multiple Payment Arrangements.Same67 → 67
52.232-38Submission of Electronic Funds Transfer Information with Offer.Submission of Electronic Funds Transfer Information with Offer.Same228 → 228
52.232-39Unenforceability of Unauthorized Obligations.Unenforceability of Unauthorized Obligations.Same232 → 232
52.232-40Providing Accelerated Payments to Small Business Subcontractors.Providing Accelerated Payments to Small Business Subcontractors.Same170 → 170
52.232-90noneFast Payment Procedure.New number– → 663
52.233none[Reserved]New number– → 0
52.233-1Disputes.Disputes.Changed · 87% alike765 → 811
52.233-2Service of Protest.Service of Protest.Changed · 78% alike111 → 90
52.233-3Protest After Award.Protest after Award.Changed · 90% alike590 → 515
52.233-4Applicable Law for Breach of Contract Claim.Applicable Law for Breach of Contract Claim.Changed · 90% alike35 → 36
52.234none[Reserved]New number– → 0
52.234-1Industrial Resources Developed Under Title III, Defense Production Act.Industrial Resources Developed Under Title III of the Defense Production Act.Changed · 71% alike242 → 245
52.234-2Notice of Earned Value Management System—Preaward Integrated Baseline Review.[Reserved]Changed · 0% alike368 → 2
52.234-3Notice of Earned Value Management System—Postaward Integrated Baseline Review.[Reserved]Changed · 0% alike297 → 2
52.234-4Earned Value Management System.Earned Value Management System.Changed · 73% alike384 → 329
52.235[Reserved][Reserved]Same0 → 0
52.236none[Reserved]New number– → 0
52.236-1Performance of Work by the Contractor.[Reserved]Changed · 0% alike126 → 2
52.236-2Differing Site Conditions.Differing Site Conditions.Changed · 83% alike236 → 199
52.236-3Site Investigation and Conditions Affecting the Work.Site Investigation and Conditions Affecting the Work.Changed · 98% alike303 → 302
52.236-4Physical Data.[Reserved]Changed · 0% alike195 → 2
52.236-5Material and Workmanship.Material and Workmanship.Changed · 96% alike314 → 320
52.236-6Superintendence by the Contractor.Superintendence by the Contractor.Changed · 89% alike65 → 63
52.236-7Permits and Responsibilities.Permits and Responsibilities.Changed · 94% alike115 → 118
52.236-8Other Contracts.Other Contracts.Changed · 69% alike103 → 94
52.236-9Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.Changed · 70% alike247 → 220
52.236-10Operations and Storage Areas.Operations and Storage Areas.Changed · 83% alike252 → 224
52.236-11Use and Possession Prior to Completion.Use and Possession Prior to Completion.Changed · 94% alike221 → 226
52.236-12Cleaning Up.Cleaning Up.Changed · 69% alike85 → 68
52.236-13Accident Prevention.Accident Prevention.Changed · 96% alike499 → 498
52.236-14Availability and Use of Utility Services.Availability and Use of Utility Services.Changed · 57% alike250 → 118
52.236-15Schedules for Construction Contracts.Schedules for Construction Contracts.Changed · 73% alike366 → 329
52.236-16Quantity Surveys.Quantity Surveys.Changed · 90% alike349 → 328
52.236-17Layout of Work.Layout of Work.Changed · 78% alike197 → 157
52.236-18Work Oversight in Cost-Reimbursement Construction Contracts.Work Oversight in Cost-Reimbursement Construction Contracts.Changed · 86% alike59 → 50
52.236-19Organization and Direction of the Work.[Reserved]Changed · 0% alike172 → 2
52.236-20[Reserved][Reserved]Same0 → 0
52.236-21Specifications and Drawings for Construction.Specifications and Drawings for Construction.Changed · 94% alike797 → 812
52.236-22Design Within Funding Limitations.Design Within Funding Limitations.Changed · 94% alike343 → 354
52.236-23Responsibility of the Architect-Engineer Contractor.Responsibility of the Architect-Engineer Contractor.Changed · 95% alike204 → 205
52.236-24Work Oversight in Architect-Engineer Contracts.Work Oversight in Architect-Engineer Contracts.Changed · 95% alike49 → 50
52.236-25Requirements for Registration of Designers.Requirements for Registration of Designers.Changed · 96% alike67 → 68
52.236-26Preconstruction Conference.[Reserved]Changed · 3% alike69 → 2
52.236-27Site Visit (Construction).[Reserved]Changed · 1% alike135 → 2
52.236-28Preparation of Proposals—Construction.[Reserved]Changed · 0% alike169 → 2
52.237none[Reserved]New number– → 0
52.237-1Site Visit.Site Visit.Changed · 89% alike93 → 78
52.237-2Protection of Government Buildings, Equipment, and Vegetation.Protection of Government Buildings, Equipment, and Vegetation.Changed · 99% alike120 → 121
52.237-3Continuity of Services.Continuity of Services.Changed · 100% alike326 → 327
52.237-4Payment by Government to Contractor.Payment by Government to Contractor.Changed · 99% alike509 → 512
52.237-5Payment by Contractor to Government.Payment by Contractor to Government.Changed · 100% alike328 → 329
52.237-6Incremental Payment by Contractor to Government.Incremental Payment by Contractor to Government.Changed · 99% alike348 → 349
52.237-7Indemnification and Medical Liability Insurance.Indemnification and Medical Liability Insurance.Changed · 98% alike507 → 500
52.237-8Restriction on Severance Payments to Foreign Nationals.Restriction on Severance Payments to Foreign Nationals.Changed · 96% alike227 → 227
52.237-9Waiver of Limitation on Severance Payments to Foreign Nationals.Waiver of Limitation on Severance Payments to Foreign Nationals.Changed · 91% alike69 → 69
52.237-10Identification of Uncompensated Overtime.Identification of Uncompensated Overtime.Changed · 99% alike343 → 346
52.238[Reserved][Reserved]Same0 → 0
52.239none[Reserved]New number– → 0
52.239-1Privacy or Security Safeguards.[Reserved]Changed · 0% alike147 → 2
52.240[Reserved][Reserved]Same0 → 0
52.240-1Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act—Covered Foreign Entities.[Reserved]Changed · 0% alike454 → 2
52.240-90noneSecurity Prohibitions and Exclusions Representations and Certifications.New number– → 1671
52.240-91noneSecurity Prohibitions and Exclusions.New number– → 4082
52.240-92noneSecurity Requirements.New number– → 758
52.240-93noneBasic Safeguarding of Covered Contractor Information Systems.New number– → 576
52.241Utility Services Provisions and Clauses.[Reserved]Same0 → 0
52.241-1Electric Service Territory Compliance Representation.Electric Service Territory Compliance Representation.Changed · 97% alike127 → 125
52.241-2Order of Precedence—Utilities.Order of Precedence-Utilities.Same70 → 70
52.241-3Scope and Duration of Contract.Scope and Duration of Contract.Same215 → 215
52.241-4Change in Class of Service.Change in Class of Service.Same98 → 98
52.241-5Contractor's Facilities.Contractor’s Facilities.Changed · 100% alike387 → 386
52.241-6Service Provisions.Service Provisions.Changed · 100% alike481 → 482
52.241-7Change in Rates or Terms and Conditions of Service for Regulated Services.Change in Rates or Terms and Conditions of Service for Regulated Services.Changed · 99% alike357 → 357
52.241-8Change in Rates or Terms and Conditions of Service for Unregulated Services.Change in Rates or Terms and Conditions of Service for Unregulated Services.Same218 → 218
52.241-9Connection Charge.Connection Charge.Changed · 99% alike1010 → 1013
52.241-10Termination Liability.Termination Liability.Changed · 98% alike258 → 262
52.241-11Multiple Service Locations.Multiple Service Locations.Same135 → 135
52.241-12Nonrefundable, Nonrecurring Service Charge.Nonrefundable, Nonrecurring Service Charge.Changed · 99% alike110 → 110
52.241-13Capital Credits.Capital Credits.Same167 → 167
52.242none[Reserved]New number– → 0
52.242-1Notice of Intent To Disallow Costs.Notice of Intent to Disallow Costs.Changed · 89% alike179 → 159
52.242-2Production Progress Reports.Production Progress Reports.Changed · 97% alike76 → 76
52.242-3Penalties for Unallowable Costs.Penalties for Unallowable Costs.Changed · 97% alike430 → 424
52.242-4Certification of Final Indirect Costs.Certification of Final Indirect Costs.Changed · 97% alike232 → 242
52.242-5Payments to Small Business Subcontractors.Payments to Small Business Subcontractors.Changed · 97% alike185 → 188
52.242-6none[Reserved]New number– → 0
52.242-6-52.242-12[Reserved]noneNot in the overhaul0 → –
52.242-7none[Reserved]New number– → 0
52.242-8none[Reserved]New number– → 0
52.242-9none[Reserved]New number– → 0
52.242-10none[Reserved]New number– → 0
52.242-11none[Reserved]New number– → 0
52.242-12none[Reserved]New number– → 0
52.242-13Bankruptcy.Bankruptcy.Changed · 99% alike135 → 135
52.242-14Suspension of Work.Suspension of Work.Changed · 97% alike321 → 306
52.242-15Stop-Work Order.Stop-Work Order.Changed · 98% alike524 → 508
52.242-16[Reserved][Reserved]Same0 → 0
52.242-17Government Delay of Work.Government Delay of Work.Changed · 100% alike274 → 274
52.243none[Reserved]New number– → 0
52.243-1Changes—Fixed-Price.Changes-Fixed-Price.Changed · 77% alike827 → 863
52.243-2Changes—Cost-Reimbursement.Changes-Cost-Reimbursement.Changed · 82% alike722 → 755
52.243-3Changes—Time-and-Materials or Labor-Hours.Changes-Time-and-Materials or Labor-Hours.Changed · 86% alike298 → 299
52.243-4Changes.Changes.Changed · 84% alike440 → 452
52.243-5Changes and Changed Conditions.Changes and Changed Conditions.Changed · 92% alike189 → 201
52.243-6Change Order Accounting.Change Order Accounting.Changed · 97% alike125 → 125
52.243-7Notification of Changes.Notification of Changes.Changed · 96% alike923 → 946
52.244none[Reserved]New number– → 0
52.244-1[Reserved][Reserved]Same0 → 0
52.244-2Subcontracts.Subcontracts.Changed · 99% alike987 → 990
52.244-3[Reserved][Reserved]Same0 → 0
52.244-4Subcontractors and outside associates and consultants (Architect-engineer services).Subcontractors and Outside Associates and Consultants (Architect-Engineer Services).Changed · 98% alike79 → 80
52.244-5Competition in Subcontracting.Competition in Subcontracting.Changed · 98% alike78 → 79
52.244-6Subcontracts for Commercial Products and Commercial Services.Subcontracts for Commercial Products and Commercial Services.Changed · 28% alike922 → 492
52.245none[Reserved]New number– → 0
52.245-1Government Property.Government Property.Changed · 99% alike5274 → 5301
52.245-2Government Property Installation Operation Services.Government Property Installation Operation Services.Same215 → 215
52.245-3none[Reserved]New number– → 0
52.245-3-52.245-8[Reserved]noneNot in the overhaul0 → –
52.245-4none[Reserved]New number– → 0
52.245-5none[Reserved]New number– → 0
52.245-6none[Reserved]New number– → 0
52.245-7none[Reserved]New number– → 0
52.245-8none[Reserved]New number– → 0
52.245-9Use and Charges.Use and Charges.Changed · 98% alike1009 → 1019
52.246none[Reserved]New number– → 0
52.246-1Contractor Inspection Requirements.Contractor Inspection Requirements.Same84 → 84
52.246-2Inspection of Supplies—Fixed-Price.Inspection of Supplies-Fixed-Price.Changed · 99% alike2241 → 2255
52.246-3Inspection of Supplies—Cost-Reimbursement.Inspection of Supplies-Cost-Reimbursement.Changed · 99% alike770 → 774
52.246-4Inspection of Services—Fixed-Price.Inspection of Services-Fixed-Price.Changed · 100% alike331 → 331
52.246-5Inspection of Services—Cost-Reimbursement.Inspection of Services-Cost-Reimbursement.Same297 → 297
52.246-6Inspection—Time-and-Material and Labor-Hour.Inspection-Time-and-Material and Labor-Hour.Changed · 100% alike919 → 923
52.246-7Inspection of Research and Development—Fixed-Price.Inspection of Research and Development-Fixed-Price.Same598 → 598
52.246-8Inspection of Research and Development—Cost-Reimbursement.Inspection of Research and Development-Cost-Reimbursement.Changed · 99% alike1052 → 1058
52.246-9Inspection of Research and Development (Short Form).Inspection of Research and Development (Short Form).Changed · 99% alike102 → 101
52.246-10[Reserved][Reserved]Same0 → 0
52.246-11Higher-Level Contract Quality Requirement.Higher-Level Contract Quality Requirement.Changed · 99% alike139 → 140
52.246-12Inspection of Construction.Inspection of Construction.Changed · 100% alike602 → 604
52.246-13Inspection—Dismantling, Demolition, or Removal of Improvements.Inspection-Dismantling, Demolition, or Removal of Improvements.Same228 → 228
52.246-14Inspection of Transportation.Inspection of Transportation.Changed · 97% alike138 → 137
52.246-15Certificate of Conformance.Certificate of Conformance.Changed · 99% alike332 → 336
52.246-16Responsibility for Supplies.Responsibility for Supplies.Changed · 97% alike211 → 217
52.246-17Warranty of Supplies of a Noncomplex Nature.Warranty of Supplies of a Noncomplex Nature.Changed · 100% alike1460 → 1460
52.246-18Warranty of Supplies of a Complex Nature.Warranty of Supplies of a Complex Nature.Changed · 100% alike1235 → 1236
52.246-19Warranty of Systems and Equipment under Performance Specifications or Design Criteria.Warranty of Systems and Equipment under Performance Specifications or Design Criteria.Changed · 100% alike1576 → 1579
52.246-20Warranty of Services.Warranty of Services.Changed · 100% alike327 → 327
52.246-21Warranty of Construction.Warranty of Construction.Same620 → 620
52.246-22[Reserved][Reserved]Same0 → 0
52.246-23Limitation of Liability.Limitation of Liability.Changed · 99% alike297 → 301
52.246-24Limitation of Liability—High-Value Items.Limitation of Liability-High-Value Items.Changed · 99% alike499 → 503
52.246-25Limitation of Liability—Services.Limitation of Liability-Services.Changed · 99% alike323 → 327
52.246-26Reporting Nonconforming Items.Reporting Nonconforming Items.Changed · 100% alike1100 → 1102
52.247none[Reserved]New number– → 0
52.247-1Commercial Bill of Lading Notations.Commercial Bill of Lading Notations.Changed · 99% alike192 → 193
52.247-2Permits, Authorities, or Franchises.Permits, Authorities, or Franchises.Same100 → 100
52.247-3Capability To Perform a Contract for the Relocation of a Federal Office.[Reserved]Changed · 0% alike576 → 2
52.247-4Inspection of Shipping and Receiving Facilities.[Reserved]Changed · 0% alike98 → 2
52.247-5Familiarization With Conditions.Familiarization with Conditions.Same124 → 124
52.247-6Financial Statement.[Reserved]Changed · 0% alike112 → 2
52.247-7Freight Excluded.[Reserved]Changed · 0% alike100 → 2
52.247-8Estimated Weights or Quantities Not Guaranteed.Estimated Weights or Quantities Not Guaranteed.Same99 → 99
52.247-9Agreed Weight—General Freight.[Reserved]Changed · 0% alike80 → 2
52.247-10Net Weight—General Freight.Net Weight-General Freight.Same154 → 154
52.247-11Net Weight—Household Goods or Office Furniture.Net Weight-Household Goods or Office Furniture.Same238 → 238
52.247-12Supervision, Labor, or Materials.[Reserved]Changed · 0% alike71 → 2
52.247-13Accessorial Services—Moving Contracts.Accessorial Services-Moving Contracts.Same263 → 263
52.247-14Contractor Responsibility for Receipt of Shipment.[Reserved]Changed · 0% alike60 → 2
52.247-15Contractor Responsibility for Loading and Unloading.Contractor Responsibility for Loading and Unloading.Same153 → 153
52.247-16Contractor Responsibility for Returning Undelivered Freight.[Reserved]Changed · 1% alike208 → 2
52.247-17Charges.Charges.Same76 → 76
52.247-18Multiple Shipments.Multiple Shipments.Same93 → 93
52.247-19Stopping in Transit for Partial Unloading.Stopping in Transit for Partial Unloading.Same125 → 125
52.247-20Estimated Quantities or Weights for Evaluation of Offers.[Reserved]Changed · 0% alike91 → 2
52.247-21Contractor Liability for Personal Injury and/or Property Damage.Contractor Liability for Personal Injury and/or Property Damage.Same203 → 203
52.247-22Contractor Liability for Loss of and/or Damage to Freight Other Than Household Goods.Contractor Liability for Loss of and/or Damage to Freight other than Household Goods.Same86 → 86
52.247-23Contractor Liability for Loss of and/or Damage to Household Goods.Contractor Liability for Loss of and/or Damage to Household Goods.Same158 → 158
52.247-24Advance Notification by the Government.[Reserved]Changed · 0% alike111 → 2
52.247-25Government-Furnished Equipment With or Without Operators.[Reserved]Changed · 0% alike80 → 2
52.247-26Government Direction and Marking.[Reserved]Changed · 0% alike81 → 2
52.247-27Contract Not Affected by Oral Agreement.[Reserved]Changed · 0% alike70 → 2
52.247-28Contractor's Invoices.[Reserved]Changed · 0% alike67 → 2
52.247-29F.o.b. Origin.F.o.b. Origin.Changed · 100% alike731 → 731
52.247-30F.o.b. Origin, Contractor's Facility.F.o.b. Origin, Contractor’s Facility.Same453 → 453
52.247-31F.o.b. Origin, Freight Allowed.F.o.b. Origin, Freight Allowed.Changed · 100% alike763 → 764
52.247-32F.o.b. Origin, Freight Prepaid.F.o.b. Origin, Freight Prepaid.Changed · 100% alike747 → 747
52.247-33F.o.b. Origin, With Differentials.F.o.b. Origin, with Differentials.Changed · 100% alike902 → 903
52.247-34F.o.b. Destination.F.o.b. Destination.Changed · 100% alike395 → 395
52.247-35F.o.b. Destination, Within Consignee's Premises.F.o.b. Destination, Within Consignee’s Premises.Same192 → 192
52.247-36F.a.s. Vessel, Port of Shipment.F.a.s. Vessel, Port of Shipment.Same238 → 238
52.247-37F.o.b. Vessel, Port of Shipment.F.o.b. Vessel, Port of Shipment.Same216 → 216
52.247-38F.o.b. Inland Carrier, Point of Exportation.F.o.b. Inland Carrier, Point of Exportation.Same228 → 228
52.247-39F.o.b. Inland Point, Country of Importation.F.o.b. Inland Point, Country of Importation.Same226 → 226
52.247-40Ex Dock, Pier, or Warehouse, Port of Importation.[Reserved]Changed · 0% alike211 → 2
52.247-41C.& f. Destination.[Reserved]Changed · 0% alike223 → 2
52.247-42C.i.f. Destination.[Reserved]Changed · 0% alike256 → 2
52.247-43F.o.b. Designated Air Carrier's Terminal, Point of Exportation.[Reserved]Changed · 1% alike261 → 2
52.247-44F.o.b. Designated Air Carrier's Terminal, Point of Importation.[Reserved]Changed · 0% alike232 → 2
52.247-45F.o.b. Origin and/or F.o.b. Destination Evaluation.[Reserved]Changed · 0% alike94 → 2
52.247-46Shipping Point(s) Used in Evaluation of F.o.b. Origin Offers.[Reserved]Changed · 1% alike225 → 2
52.247-47Evaluation—F.o.b. Origin.[Reserved]Changed · 0% alike153 → 2
52.247-48F.o.b. Destination—Evidence of Shipment.F.o.b. Destination-Evidence of Shipment.Same189 → 189
52.247-49Destination Unknown.[Reserved]Changed · 0% alike32 → 2
52.247-50No Evaluation of Transportation Costs.[Reserved]Changed · 0% alike65 → 2
52.247-51Evaluation of Export Offers.[Reserved]Changed · 0% alike1199 → 2
52.247-52Clearance and Documentation Requirements—Shipments to DOD Air or Water Terminal Transshipment Points.Clearance and Documentation Requirements-Shipments to DoD Air or Water Terminal Transshipment Points.Changed · 99% alike659 → 659
52.247-53Freight Classification Description.Freight Classification Description.Changed · 97% alike175 → 185
52.247-54[Reserved][Reserved]Same0 → 0
52.247-55F.o.b. Point for Delivery of Government-Furnished Property.[Reserved]Changed · 0% alike377 → 2
52.247-56Transit Arrangements.Transit Arrangements.Changed · 95% alike69 → 74
52.247-57Transportation Transit Privilege Credits.[Reserved]Changed · 1% alike365 → 2
52.247-58Loading, Blocking, and Bracing of Freight Car Shipments.Loading, Blocking, and Bracing of Freight Car Shipments.Same178 → 178
52.247-59F.o.b. Origin—Carload and Truckload Shipments.[Reserved]Changed · 1% alike283 → 2
52.247-60Guaranteed Shipping Characteristics.[Reserved]Changed · 0% alike404 → 2
52.247-61F.o.b. Origin—Minimum Size of Shipments.[Reserved]Changed · 1% alike210 → 2
52.247-62Specific Quantities Unknown.[Reserved]Changed · 0% alike123 → 2
52.247-63Preference for U.S.-Flag Air Carriers.Preference for U.S.-Flag Air Carriers.Changed · 99% alike389 → 391
52.247-64Preference for Privately Owned U.S.-Flag Commercial Vessels.Preference for Privately Owned U.S.-Flag Commercial Vessels.Changed · 100% alike1034 → 1032
52.247-65F.o.b. Origin, Prepaid Freight—Small Package Shipments.[Reserved]Changed · 0% alike263 → 2
52.247-66Returnable Cylinders.[Reserved]Changed · 1% alike373 → 2
52.247-67Submission of Transportation Documents for Audit.Submission of Transportation Documents for Audit.Same146 → 146
52.247-68Report of Shipment (REPSHIP).Report of Shipment (REPSHIP).Changed · 100% alike312 → 313
52.247-69Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to Prevent Human Trafficking.Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to Prevent Human Trafficking.Changed · 99% alike397 → 399
52.248none[Reserved]New number– → 0
52.248-1Value Engineering.Value Engineering.Changed · 97% alike3243 → 3336
52.248-2Value Engineering—Architect-Engineer.Value Engineering-Architect-Engineer.Changed · 98% alike605 → 610
52.248-3Value Engineering—Construction.Value Engineering-Construction.Changed · 98% alike1385 → 1405
52.249none[Reserved]New number– → 0
52.249-1Termination for Convenience of the Government (Fixed-Price) (Short Form).Termination for Convenience of the Government (Fixed-Price) (Short Form).Same167 → 167
52.249-2Termination for Convenience of the Government (Fixed-Price).Termination for Convenience of the Government (Fixed-Price).Changed · 99% alike2467 → 2470
52.249-3Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).Changed · 100% alike1897 → 1895
52.249-4Termination for Convenience of the Government (Services) (Short Form).Termination for Convenience of the Government (Services) (Short Form).Same143 → 143
52.249-5Termination for Convenience of the Government (Educational and Other Nonprofit Institutions).Termination for Convenience of the Government (Educational and Other Nonprofit Institutions).Changed · 100% alike949 → 949
52.249-6Termination (Cost-Reimbursement).Termination (Cost-Reimbursement).Changed · 99% alike3149 → 3150
52.249-7Termination (Fixed-Price Architect-Engineer).Termination (Fixed-Price Architect-Engineer).Same282 → 282
52.249-8Default (Fixed-Price Supply and Service).Default (Fixed-Price Supply and Service).Changed · 98% alike914 → 931
52.249-9Default (Fixed-Price Research and Development).Default (Fixed-Price Research and Development).Changed · 99% alike670 → 676
52.249-10Default (Fixed-Price Construction).Default (Fixed-Price Construction).Changed · 100% alike1287 → 1286
52.249-11[Reserved][Reserved]Same0 → 0
52.249-12Termination (Personal Services).Termination (Personal Services).Same75 → 75
52.249-13[Reserved][Reserved]Same0 → 0
52.249-14Excusable Delays.Excusable Delays.Same353 → 353
52.250none[Reserved]New number– → 0
52.250-1Indemnification Under Public Law 85-804.Indemnification Under Public Law 85-804.Changed · 99% alike748 → 748
52.250-2SAFETY Act Coverage Not Applicable.SAFETY Act Coverage Not Applicable.Same149 → 149
52.250-3SAFETY Act Block Designation/Certification.SAFETY Act Block Designation/Certification.Changed · 100% alike1236 → 1237
52.250-4SAFETY Act Pre-qualification Designation Notice.SAFETY Act Pre-qualification Designation Notice.Changed · 100% alike1207 → 1209
52.250-5SAFETY Act—Equitable Adjustment.SAFETY Act-Equitable Adjustment.Changed · 99% alike642 → 643
52.251none[Reserved]New number– → 0
52.251-1Government Supply Sources.[Reserved]Changed · 0% alike78 → 2
52.251-2Interagency Fleet Management System Vehicles and Related Services.[Reserved]Changed · 0% alike83 → 2
52.252none[Reserved]New number– → 0
52.252-1Solicitation Provisions Incorporated by Reference.Solicitation Provisions Incorporated by Reference.Changed · 98% alike125 → 131
52.252-2Clauses Incorporated by Reference.Clauses Incorporated by Reference.Same74 → 74
52.252-3Alterations in Solicitation.Alterations in Solicitation.Changed · 98% alike65 → 65
52.252-4Alterations in Contract.Alterations in Contract.Same70 → 70
52.252-5Authorized Deviations in Provisions.Authorized Deviations in Provisions.Same152 → 152
52.252-6Authorized Deviations in Clauses.Authorized Deviations in Clauses.Same157 → 157
52.253none[Reserved]New number– → 0
52.253-1Computer Generated Forms.Computer Generated Forms.Changed · 99% alike184 → 183
52.300Scope of subpart.noneNot in the overhaul18 → –
52.301Solicitation provisions and contract clauses (Matrix).noneNot in the overhaul20 → –