FAR and DFARS › DFARS Part 243

DFARS Part 243: Contract Modifications

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

In plain English

DFARS Part 243 governs changes to existing defense contracts, including how modifications are priced, how unpriced change orders must be controlled, and how equitable adjustment requests are certified. For a small business, it matters because changes that add work or shift costs must be properly priced, documented, and certified before the government will pay for them, and unpriced changes carry strict timing and funding limits.

Key rules

  • Unpriced change orders with an estimated value over $5 million must include a not-to-exceed price. (243.204-70-1, 243.204-70-2)
  • Unpriced change orders must have a definitization schedule, with definitization by the earlier of 180 days after issuance (extendable, but not beyond 180 days after a qualifying proposal) or the point at which obligated funds exceed 50 percent of the not-to-exceed price. (243.204-70-3)
  • Submitting a timely qualifying proposal under the definitization schedule is a material element of the contract, and failure to do so may lead to suspended or reduced progress payments. (243.204-70-3)
  • Before definitization, the government generally may not obligate more than 50 percent of the not-to-exceed price, which may rise to 75 percent if a qualifying proposal is submitted before the 50 percent point is reached. (243.204-70-4)
  • A request for equitable adjustment above the simplified acquisition threshold may not be paid unless it is certified under the clause at 252.243-7002. (243.204-71, 243.205-71)
  • To check whether the certification threshold is met, add the absolute value of every cost increase and every cost decrease together. (243.204-71)
  • Profit on an unpriced change order negotiated after substantial performance must reflect reduced cost risk, and the risk assessment must be documented in the price negotiation memorandum. (243.204-70-6)
  • Fixed-price contracts anticipating modifications use the clause at 252.243-7001, Pricing of Contract Modifications. (243.205-70)

Who does what

Contracting officers
  • Include a not-to-exceed price and a definitization schedule in each unpriced change order over $5 million.
  • Limit obligations on undefinitized changes to the 50 or 75 percent thresholds and keep them consistent with the contractor's requirements.
  • Apply the unpriced change order policy to foreign military sales and special access programs where practicable, and give prior notice to Contract Policy if it is impracticable.
Contractors
  • Submit a qualifying proposal within the definitization schedule, since a late submission is a material failure of the contract.
  • Certify any request for equitable adjustment above the simplified acquisition threshold under 252.243-7002.
  • Use the separate certification required under FAR subpart 33.2 if converting an adjustment request into a Contract Disputes Act claim.
Agencies
  • Include planned and actual definitization actions and each unpriced change order over $5 million in the Consolidated UCA Management Plan and Report.
  • Head of the agency may waive the price ceiling, schedule, and obligation limits for contingency or humanitarian/peacekeeping operations.

In practice

  • If you receive an unpriced change order over $5 million, track the 180-day clock and the 50 percent obligation point from day one, and plan to submit your qualifying proposal well before the deadline.
  • Keep cost records by change so you can add up the absolute value of all increases and decreases and determine whether the certification threshold applies.
  • Expect profit on an undefinitized change to be adjusted downward if much of the work was done before final pricing, because the government considers your reduced risk.

Common pitfalls

  • Assuming the 180-day definitization period can run indefinitely; extensions are capped at 180 days after your qualifying proposal.
  • Netting cost increases against cost decreases when testing the certification threshold; the text requires adding absolute values, so offsetting amounts do not cancel out.
  • Missing the qualifying proposal deadline, which the text treats as a material element of the contract and can trigger suspended or reduced progress payments.

Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.

Rule changes for DFARS Part 243

Subparts and sections

Subpart 243.1: General

Subpart 243.2: Change Orders

← Part 242: Contract Administration and Audit ServicesPart 244: Subcontracting Policies and Procedures →

All DFARS parts

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.