FAR and DFARS › DFARS Part 250

DFARS Part 250: Extraordinary Contractual Actions and the Safety Act

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

In plain English

DFARS Part 250 covers extraordinary contractual actions, meaning government authority to adjust contract terms, pay requests for equitable adjustment or relief under Public Law 85-804, and indemnify contractors against unusually hazardous or nuclear risks. It matters to small-business contractors because such relief is discretionary, runs through delegated approval levels and contract adjustment boards, and has specific dollar and payment limitations that affect how and where requests must be filed.

Key rules

  • Authority to approve actions obligating $90,000 or less under FAR 50.104 may not be delegated below the head of the contracting activity. (250.102-1)
  • Requests to obligate the Government in excess of $90,000 under the delegated authority must be submitted to the USD(A&S) for approval. (250.102-1-70)
  • Indemnification against unusually hazardous or nuclear risks requires USD(A&S) approval before the indemnification clause at FAR 52.250-1 is used. (250.102-1-70, 250.102-1)
  • Congressionally directed payment of a request for equitable adjustment or Public Law 85-804 relief is subject to limitations in 10 U.S.C. 3862. (250.101-2-70)
  • Contractor requests for contract adjustment should be filed with the procuring contracting officer, though an administrative contracting officer or the applicable Office of General Counsel may receive them when filing with the PCO is impractical. (250.103-3)
  • Contract adjustment boards decide cases as expeditiously as practicable, with the Chair signing a dated memorandum of decision that must not contain information classified Confidential or higher. (250.103-5)
  • When a contract includes both research and development work and other work, the contracting officer uses the authority of both 10 U.S.C. 3861 and Public Law 85-804, with Public Law 85-804 limited to work that cannot be indemnified under 10 U.S.C. 3861. (250.104-3-70)
  • Delegations of authority under the Act and the Executive Order must be approved in writing by the Secretary of the military department or the agency director. (250.102-1-70)

Who does what

Contracting officers
  • Insert an appropriate indemnification clause on mixed R&D and other work, citing both 10 U.S.C. 3861 and Public Law 85-804.
  • Receive contractor requests for contract adjustment, or forward them to the cognizant PCO when they were filed elsewhere.
  • Prepare the required case record and forward it to the appropriate official within 30 days after the close of the month in which it is prepared.
Contractors
  • File requests for contract adjustment with the procuring contracting officer, using an alternate filing point only when PCO filing is impractical.
Agencies
  • Specify delegations and levels of authority for actions under the Act and the Executive Order in departmental supplements or agency acquisition guidance.
  • Obtain USD(A&S) approval for requests above $90,000 and for indemnification against unusually hazardous or nuclear risks.

In practice

  • Expect that a request for relief above $90,000 or for indemnification against unusually hazardous or nuclear risks will be decided at a level above the contracting activity, which adds time to the process.
  • Identify early whether a contract mixes R&D and other work, since the indemnification authority and clause depend on that split.
  • Send the request to the PCO first; if you use another filing point, document why PCO filing was impractical.

Common pitfalls

  • Assuming the contracting officer alone can approve indemnification against unusually hazardous or nuclear risks; USD(A&S) approval is required first.
  • Relying on Public Law 85-804 to cover work that can be indemnified under 10 U.S.C. 3861; the text limits Public Law 85-804 to work that cannot be indemnified under 3861.
  • Assuming a request for relief will be paid without limitation; payment is subject to 10 U.S.C. 3862.

Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.

Rule changes for DFARS Part 250

Subparts and sections

Subpart 250.1: Extraordinary Contractual Actions

← Part 249: Termination of ContractsPart 251: Use of Government Sources by Contractors →

All DFARS parts

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.