DFARS 252.216-7000 Economic Price Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products.

In plain English: This clause lets a contractor's price for basic steel, aluminum, brass, bronze, or copper mill products move with the contractor's own established (catalog or market) price. The contractor certifies its offered price is not above its established price at bid opening, must promptly report any decrease and pass it on proportionally, and may request a proportional increase (capped at 10 percent of the original unit price) if its established price rises. Contractors should watch the notice deadlines, the 10-percent cap, and the cancellation rights tied to an increase request. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 216.203-4, which says when contracting officers use it.

Last amended 2023-01-31 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.216-7000 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.216-7000 · Ask the AI chat about it

In more detail

Applies to: Contractors supplying basic steel, aluminum, brass, bronze, or copper mill products under DoD contracts

What it requires

  • Promptly notify the Contracting Officer of the amount and effective date of each decrease in an established price
  • Submit a written request to the Contracting Officer to obtain an increase in the contract unit price after an established price increase
  • Within ten days of an established price change, submit the written increase request so the increase takes effect on the change date
  • Continue deliveries on the contract schedule while any cancellation under paragraph (e) is pending

Key terms: Established price · Unit price · Economic price adjustment · Contracting Officer · Standard steel supply item

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 216.203-4-70(a)(1), use the following clause:

Economic Price Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products (JAN 2023)

(a) Definitions. As used in this clause—

Established price means a price which is an established catalog or market price for a commercial product sold in substantial quantities to the general public.

Unit price excludes any part of the price which reflects requirements for preservation, packaging, and packing beyond standard commercial practice.

(b) As represented by the Contractor in its offer, the unit price stated for ________________ (Identify the item) is not in excess of the Contractor's established price in effect on the date set for opening of bids (or the contract date if this is a negotiated contract) for like quantities of the same item. This price is the net price after applying any applicable standard trade discounts offered by the Contractor from its catalog, list, or schedule price.

(c) The Contractor shall promptly notify the Contracting Officer of the amount and effective date of each decrease in any established price.

(1) Each corresponding contract unit price shall be decreased by the same percentage that the established price is decreased.

(2) This decrease shall apply to items delivered on or after the effective date of the decrease in the Contractor's established price.

(3) This contract shall be modified accordingly.

(d) If the Contractor's established price is increased after the date set for opening of bids (or the contract date if this is a negotiated contract), upon the Contractor's written request to the Contracting Officer, the corresponding contract unit price shall be increased by the same percentage that the established price is increased, and this contract shall be modified accordingly, provided—

(1) The aggregate of the increases in any contract unit price under this contract shall not exceed 10 percent of the original contract unit price;

(2) The increased contract unit price shall be effective on the effective date of the increase in the applicable established price if the Contractor's written request is received by the Contracting Officer within ten days of the change. If it is not, the effective date of the increased unit price shall be the date of receipt of the request by the Contracting Officer; and

(3) The increased contract unit price shall not apply to quantities scheduled for delivery before the effective date of the increased contract unit price unless the Contractor's failure to deliver before that date results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the Default clause of this contract.

(4) The Contracting Officer shall not execute a modification incorporating an increase in a contract unit price under this clause until the increase is verified.

(e) Within 30 days after receipt of the Contractor's written request, the Contracting Officer may cancel, without liability to either party, any portion of the contract affected by the requested increase and not delivered at the time of such cancellation, except as follows—

(1) The Contractor may, after that time, deliver any items that were completed or in the process of manufacture at the time of receipt of the cancellation notice, provided the Contractor notifies the Contracting Officer of such items within 10 days after the Contractor receives the cancellation notice.

(2) The Government shall pay for those items at the contract unit price increased to the extent provided by paragraph (d) of this clause.

(3) Any standard steel supply item shall be deemed to be in the process of manufacture when the steel for that item is in the state of processing after the beginning of the furnace melt.

(f) Pending any cancellation of this contract under paragraph (e) of this clause, or if there is no cancellation, the Contractor shall continue deliveries according to the delivery schedule of the contract. The Contractor shall be paid for those deliveries at the contract unit price increased to the extent provided by paragraph (d) of this clause.

(End of clause)

Sections it refers to

Sections that refer to it

  • 216.203-4-70 Additional provisions and clauses.
  • 252.216-7007 Economic price adjustment—basic steel, aluminum, brass, bronze, or copper mill products-representation.

Related DFARS 252.216 sections

← 252.215-7016 Notification to Offerors—Postaward Debriefings. · 252.216-7001 Economic Price Adjustment-Nonstandard Steel Items. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.