DFARS 252.216-7001 Economic Price Adjustment-Nonstandard Steel Items.
In plain English: This clause lets the contract unit price for nonstandard steel items go up or down each month delivery is due, based on changes in the labor index and the steel price index measured against base values set at bid opening. The contractor must fill in the labor and steel percentages and the base steel price, and must provide supporting price and earnings statements after final delivery. Any upward adjustment is capped at ten percent of the original unit price. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 216.203-4, which says when contracting officers use it.
Last amended 2023-01-31 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.216-7001 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.216-7001 · Ask the AI chat about it
In more detail
Applies to: contractors on DoD contracts for nonstandard steel items with economic price adjustment
What it requires
- Within 30 days after final delivery (or another period the Contracting Officer authorizes), furnish a statement of the labor earnings and established steel prices used in the index computations.
- Make all records used to compute the labor indices available to the Contracting Officer on request.
- Accept payment at the existing contract unit price for deliveries pending any price revision.
Key terms: base steel index · current steel index · base labor index · current labor index · established price
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 216.203-4-70(b), use the following clause:
Economic Price Adjustment—Nonstandard Steel Items (JAN 2023)
(a) Definitions. As used in this clause—
Base labor index means the average of the labor indices for the three months which consist of the month of bid opening (or offer submission) and the months immediately preceding and following that month.
Base steel index means the Contractor's established price (see note 6) including all applicable extras of $________ per __________ (see note 1) for __________ (see note 2) on the date set for bid opening (or the date of submission of the offer).
Current labor index means the average of the labor indices for the month in which delivery of supplies is required to be made and the month preceding.
Current steel index means the Contractor's established price (see note 6) for that item, including all applicable extras in effect ________ days (see note 3) prior to the first day of the month in which delivery is required.
Established price is—
(1) A price which is an established catalog or market price of a commercial product sold in substantial quantities to the general public; and
(2) The net price after applying any applicable standard trade discounts offered by the Contractor from its catalog, list, or schedule price. (But see Note 6.)
Labor index means the average straight time hourly earnings of the Contractor's employees in the ________ shop of the Contractor's __________ plant (see note 4) for any particular month.
Month means calendar month. However, if the Contractor's accounting period does not coincide with the calendar month, then that accounting period shall be used in lieu of month.
(b) Each contract unit price shall be subject to revision, under the terms of this clause, to reflect changes in the cost of labor and steel. For purpose of this price revision, the proportion of the contract unit price attributable to costs of labor not otherwise included in the price of the steel item identified under the base steel index definition in paragraph (a) shall be ______ percent, and the proportion of the contract unit price attributable to the cost of steel shall be ______ percent. (See note 5.)
(c)(1) Unless otherwise specified in this contract, the labor index shall be computed by dividing the total straight time earnings of the Contractor's employees in the shop identified in paragraph (a) for any given month by the total number of straight time hours worked by those employees in that month.
(2) Any revision in a contract unit price to reflect changes in the cost of labor shall be computed solely by reference to the “base labor index” and the “current labor index.”
(d) Any revision in a contract unit price to reflect changes in the cost of steel shall be computed solely by reference to the “base steel index” and the “current steel index.”
(e)(1) Each contract unit price shall be revised for each month in which delivery of supplies is required to be made.
(2) The revised contract unit price shall apply to the deliveries of those quantities required to be made in that month regardless of when actual delivery is made.
(3) Each revised contract unit price shall be computed by adding—
(i) The adjusted cost of labor (obtained by multiplying ______ percent of the contract unit price by a fraction, of which the numerator shall be the current labor index and the denominator shall be the base labor index);
(ii) The adjusted cost of steel (obtained by multiplying ______ percent of the contract unit price by a fraction, of which the numerator shall be the current steel index and the denominator shall be the base steel index); and
(iii) The amount equal to ______ percent of the original contract unit price (representing that portion of the unit price which relates neither to the cost of labor nor the cost of steel, and which is therefore not subject to revision (see note 5)).
(4) The aggregate of the increases in any contract unit price under this contract shall not exceed ten percent of the original contract unit price.
(5) Computations shall be made to the nearest one-hundredth of one cent.
(f)(1) Pending any revisions of the contract unit prices, the Contractor shall be paid the contract unit price for deliveries made.
(2) Within 30 days after final delivery (or such other period as may be authorized by the Contracting Officer), the Contractor shall furnish a statement identifying the correctness of—
(i) The average straight time hourly earnings of the Contractor's employees in the shop identified in paragraph (a) that are relevant to the computations of the base labor index and the current labor index; and
(ii) The Contractor's established prices (see note 6), including all applicable extras for like quantities of the item that are relevant to the computation of the base steel index and the current steel index.
(3) Upon request of the Contracting Officer, the Contractor shall make available all records used in the computation of the labor indices.
(4) Upon receipt of the statement, the Contracting Officer will compute the revised contract unit prices and modify the contract accordingly. No modification to this contract will be made pursuant to this clause until the Contracting Officer has verified the revised established price (see note 6).
(g)(1) In the event any item of this contract is subject to a total or partial termination for convenience, the month in which the Contractor receives notice of the termination, if prior to the month in which delivery is required, shall be considered the month in which delivery of the terminated item is required for the purposes of determining the current labor and steel indices under paragraphs (c) and (d).
(2) For any item which is not terminated for convenience, the month in which delivery is required under the contract shall continue to apply for determining those indices with respect to the quantity of the non-terminated item.
(3) If this contract is terminated for default, any price revision shall be limited to the quantity of the item which has been delivered by the Contractor and accepted by the Government prior to receipt by the Contractor of the notice of termination.
(h) If the Contractor's failure to make delivery of any required quantity arises out of causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the clause of this contract entitled “Default,” the quantity not delivered shall be delivered as promptly as possible after the cessation of the cause of the failure, and the delivery schedule set forth in this contract shall be amended accordingly.
Notes:
1 Offeror insert the unit price and unit measure of the standard steel mill item to be used in the manufacture of the contract item.
2 Offeror identify the standard steel mill item to be used in the manufacture of the contract item.
3 Offeror insert best estimate of the number of days required for processing the standard steel mill item in the shop identified under the labor index definition.
4 Offeror identify the shop and plant in which the standard steel mill item identified under the base steel index definition will be finally fabricated or processed into the contract item.
5 Offeror insert the same percentage figures for the corresponding blanks in paragraphs (b), (e)(3)(i), and (e)(3)(ii). In paragraph (e)(3)(iii), insert the percentage representing the difference between the sum of the percentages inserted in paragraph (b) and 100 percent.
6 In negotiated acquisitions of nonstandard steel items, when there is no established price or when it is not desirable to use this price, this paragraph may refer to another appropriate price basis, e.g., an established interplant price.
(End of clause)
Sections it refers to
- 216.203-4 Contract clauses.
Sections that refer to it
- 216.203-4-70 Additional provisions and clauses.
Related DFARS 252.216 sections
- 252.216-7000 Economic Price Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products.
- 252.216-7002 Alternate A, Time-and-Materials/Labor-Hour Proposal Requirements—Other Than Commercial Acquisition with Adequate Price Competition.
- 252.216-7003 Economic price adjustment—wage rates or material prices controlled by a foreign government.
- 252.216-7004 Award Fee Reduction or Denial for Jeopardizing the Health or Safety of Government Personnel.
- 252.216-7006 [Reserved]
- 252.216-7007 Economic price adjustment—basic steel, aluminum, brass, bronze, or copper mill products-representation.
- 252.216-7008 Economic price adjustment—wage rates or material prices controlled by a foreign government—representation.
- 252.216-7009 Allowability of Legal Costs Incurred in Connection with a Whistleblower Proceeding.
- 252.216-7010 Postaward Debriefings for Task Orders and Delivery Orders.
← 252.216-7000 Economic Price Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products. · 252.216-7002 Alternate A, Time-and-Materials/Labor-Hour Proposal Requirements—Other Than Commercial Acquisition with Adequate Price Competition. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.