FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2
DFARS 252.217-7016 Plant protection.
In plain English: This clause requires the contractor to provide reasonable safeguards for its plant and work in process against hazards such as unauthorized entry, theft, vandalism, and fire, plus any additional safeguards needed against espionage, sabotage, and enemy action. The Government reimburses the allocable cost of those additional safeguards (without overhead unless tied to installing security devices), and title to any device or equipment the Government pays for vests in the Government, subject to its disposition instructions. It matters because contractors must budget for baseline security and can recover certain extra security costs, but must follow Government instructions on security equipment i (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 217.7104(a), which says when contracting officers use it.
Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.217-7016 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.217-7016 · Ask the AI chat about it
In more detail
Applies to: contractors performing work at their plant under a DFARS-clause contract
What it requires
- Provide reasonable safeguards for the plant and work in process against unauthorized entry, malicious mischief, theft, vandalism, and fire
- Provide any additional safeguards necessary to protect the plant and work in process from espionage, sabotage, and enemy action
- Comply with the Contracting Officer's instructions on identification and disposition of Government-titled devices or equipment
Key terms: plant · work in process · safeguards · espionage, sabotage, and enemy action · allocable
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 217.7104(a), use the following clause:
Plant Protection (DEC 1991)
(a) The Contractor shall provide, for the plant and work in process, reasonable safeguards against all hazards, including unauthorized entry, malicious mischief, theft, vandalism, and fire.
(b) The Contractor shall also provide whatever additional safeguards are necessary to protect the plant and work in process from espionage, sabotage, and enemy action.
(1) The Government shall reimburse the Contractor for that portion of the costs of the additional safeguards that is allocable to the contract in the same manner as if the Contracting Officer had issued a change order for the additional safeguards.
(2) The costs reimbursed shall not include any overhead allowance, unless the overhead is incident to the construction or installation of necessary security devices or equipment.
(c) Upon payment by the Government of the cost of any device or equipment required or approved under paragraph (b) of this clause, title shall vest in the Government.
(1) The Contractor shall comply with the instructions of the Contracting Officer concerning its identification and disposition.
(2) No such device or equipment shall become a fixture as a result of its being affixed to realty not owned by the Government.
(End of clause)
Related DFARS 252.217 sections
- 252.217-7008 Bonds.
- 252.217-7009 Default.
- 252.217-7010 Performance.
- 252.217-7011 Access to vessel.
- 252.217-7012 Liability and insurance.
- 252.217-7013 Guarantees.
- 252.217-7014 Discharge of liens.
- 252.217-7015 Safety and health.
- 252.217-7017—252.217-7025 [Reserved]
- 252.217-7026 Identification of Sources of Supply.
- 252.217-7027 Contract Definitization.
- 252.217-7028 Over and above work.
← 252.217-7015 Safety and health. · 252.217-7017—252.217-7025 [Reserved] →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.