DFARS 252.217-7010 Performance.

In plain English: This clause governs ship repair and alteration work under job orders: the contractor must promptly start and diligently finish awarded work, and the Government delivers and accepts the vessel at the times and places set in the job order. It also requires the contractor, at no charge, to provide certain shipboard support (lavatories, brows and gangways, offices and telephones), to treat salvaged ship's material as Government property, and to pay for damage to the vessel's equipment caused by its own use of that equipment. Dock and sea trials are conducted under the job order's terms, with unauthorized trials at the contractor's expense and risk. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 217.7104(a), which says when contracting officers use it.

Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.217-7010 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.217-7010 · Ask the AI chat about it

In more detail

Applies to: contractors performing vessel repair or alteration job orders for the Government

What it requires

  • Promptly start awarded work and diligently prosecute it to completion, and do not start before the job order is awarded except for emergency work ordered by the Contracting Officer
  • Without charge, supply and maintain suitable brows and gangways and make sanitary facilities available to vessel personnel while the vessel is in dry dock or on a marine railway
  • Treat salvage, scrap, or other ship's material resulting from the work as Government-furnished property under the Government Property clause
  • Perform, or pay the cost of, repair, reconditioning, or replacement of the vessel's machinery, equipment, or fittings damaged by the contractor's use of them

Key terms: job order · dock and sea trials · brows and gangways · salvage, scrap or other ship's material · Contracting Officer

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 217.7104(a), use the following clause:

Performance (JUL 2009)

(a) Upon the award of a job order, the Contractor shall promptly start the work specified and shall diligently prosecute the work to completion. The Contractor shall not start work until the job order has been awarded except in the case of emergency work ordered by the Contracting Officer under the Job Orders and Compensation clause of the Master Agreement.

(b) The Government shall deliver the vessel described in the job order at the time and location specified in the job order. Upon completion of the work, the Government shall accept delivery of the vessel at the time and location specified in the job order.

(c) The Contractor shall, without charge and without specific requirement in a job order,—

(1) Make available at the plant to personnel of the vessel while in dry dock or on a marine railway, sanitary lavatory and similar facilities acceptable to the Contracting Officer;

(2) Supply and maintain suitable brows and gangways from the pier, dry dock, or marine railway to the vessel;

(3) Treat salvage, scrap or other ship's material of the Government resulting from performance of the work as items of Government-furnished property, in accordance with the Government Property clause;

(4) Perform, or pay the cost of, any repair, reconditioning or replacement made necessary as the result of the use by the Contractor of any of the vessel's machinery, equipment or fittings, including, but not limited to, winches, pumps, rigging, or pipe lines; and

(5) Furnish suitable offices, office equipment and telephones at or near the site of the work for the Government's use.

(d) The job order will state whether dock and sea trials are required to determine whether or not the Contractor has satisfactorily performed the work.

(1) If dock and sea trials are required, the vessel shall be under the control of the vessel's commander and crew.

(2) The Contractor shall not conduct dock and sea trials not specified in the job order without advance approval of the Contracting Officer. Dock and sea trials not specified in the job order shall be at the Contractor's expense and risk.

(3) The Contractor shall provide and install all fittings and appliances necessary for dock and sea trials. The Contractor shall be responsible for care, installation, and removal of instruments and apparatus furnished by the Government for use in the trials.

(End of clause)

Sections it refers to

Sections that refer to it

Related DFARS 252.217 sections

← 252.217-7009 Default. · 252.217-7011 Access to vessel. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.