FAR and DFARS › FAR Part 33: Protests, Disputes, and Appeals › Subpart 33.2
FAR 33.208 Interest on claims.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section requires the Government to pay interest on a contractor's claim for an amount found due and unpaid, starting from the date the contracting officer receives the claim (or when payment would otherwise be due, if later) until payment. Interest is simple and paid at Treasury rates that can change every six months. For claims with defective certifications, interest generally starts from the later of the initial receipt or October 29, 1992, unless a proper certificate was provided earlier.
Applies to: Government contractors with claims against the Government
Key terms: interest · contractor's claim · certified · simple interest · defective certifications
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) The Government shall pay interest on a contractor's claim on the amount found due and unpaid from the date that—
(1) The contracting officer receives the claim (certified if required by 33.207(a)); or
(2) Payment otherwise would be due, if that date is later, until the date of payment.
(b) Simple interest on claims shall be paid at the rate, fixed by the Secretary of the Treasury as provided in the Disputes statute, which is applicable to the period during which the contracting officer receives the claim and then at the rate applicable for each 6-month period as fixed by the Treasury Secretary during the pendency of the claim. (See the clause at 52.232-17 for the right of the Government to collect interest on its claims against a contractor).
(c) With regard to claims having defective certifications, interest shall be paid from either the date that the contracting officer initially receives the claim or October 29, 1992, whichever is later. However, if a contractor has provided a proper certificate prior to October 29, 1992, after submission of a defective certificate, interest shall be paid from the date of receipt by the Government of a proper certificate.
← 33.207 Contractor certification. · 33.209 Suspected fraudulent claims. →
Rule changes for FAR Part 33
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2025-05-12 · effective 2025-06-11
- Federal Acquisition Regulation: Controlled Unclassified Information ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment ↗ · final rule 2025-01-03 · effective 2025-01-17
- Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment ↗ · proposed 2024-01-09 · comments due 2024-03-11
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.