FAR and DFARS › FAR Part 33

FAR Part 33: Protests, Disputes, and Appeals

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

In plain English

FAR Part 33 covers how contract protests are filed and resolved (with the agency, GAO, or the Court of Federal Claims) and how contract disputes and claims are submitted, decided, appealed, and paid interest. It matters to small-business contractors because it sets the deadlines, certification requirements, and procedures they must follow if they challenge a solicitation or award or pursue a claim against the Government.

Key rules

  • Contractor claims must be submitted in writing to the contracting officer for a decision within 6 years after the claim accrues, unless the parties agreed to a shorter period. (33.206, 33.201)
  • A contractor submitting a claim over $100,000 must include the prescribed certification that the claim is made in good faith, the supporting data are accurate and complete, and the signer is authorized to certify on the contractor's behalf. (33.207)
  • Interest on a contractor's claim runs from the date the contracting officer receives the claim (or the date payment otherwise would be due, if later) until payment. (33.208)
  • The contracting officer's written final decision must describe the claim, cite pertinent contract terms, state the factual areas of agreement and disagreement, and give the decision with its rationale, including notice of appeal rights. (33.211)
  • Protests must be concise and logically presented; a protester must furnish a complete copy of a GAO protest to the designated official or contracting officer within 1 day after filing with GAO. (33.103, 33.104)
  • Alternative dispute resolution is encouraged, and a contracting officer who rejects a contractor's ADR request must give a written explanation citing a specific reason. (33.204, 33.214)
  • A contractor may be required to continue performance pending final resolution of a claim arising under or relating to the contract, as directed by the contracting officer's decision. (33.213, 33.215)

Who does what

Contracting officers
  • Consider all protests and seek legal advice, whether filed before or after award and wherever filed.
  • Review the facts, secure legal and other advice, and issue a written decision on claims that cannot be settled by agreement.
  • Refer suspected fraudulent claims to the agency official responsible for investigating fraud.
  • Provide data and support needed by the agency board of contract appeals on a pending appeal.
Contractors
  • Attempt to resolve concerns with the contracting officer through open discussion before filing a protest.
  • Submit claims in writing within the 6-year limit, with the required certification when the claim exceeds $100,000.
  • Continue performance as directed by the contracting officer's decision while a claim is pending, where the contract so requires.
  • Furnish a complete copy of a GAO protest to the designated official within 1 day of filing.
Agencies
  • Provide inexpensive, informal, and expeditious protest resolution, including ADR where appropriate.
  • Decide whether to use ADR procedures and establish agency policies governing contracting officer contacts with the agency board.

In practice

  • Track the protest venue's deadlines and filing rules, since the regulation sets them in part by reference to 4 CFR Part 21 and the Court of Federal Claims rules.
  • Document claim accrual dates and keep records supporting the amount claimed, because the certification and interest run from specific receipt dates.
  • When a claim is near $100,000, count the aggregate of increased and decreased costs to determine whether certification is required.
  • Ask in writing for ADR when a dispute cannot be settled at the contracting officer level; a rejection must come with a written reason.

Common pitfalls

  • Missing the 6-year claim submission deadline, or the 1-day GAO copy requirement for a protest.
  • Submitting a claim over $100,000 with a certification that deviates from the prescribed language or is signed by someone not authorized to bind the company, which the regulation treats as a defective certification.
  • Assuming a claim is not subject to the certification rule because the amount is only disputed; the rule applies to claims submitted, not merely issues discussed.
  • Stopping performance while a claim is pending when the contracting officer has directed continued performance.

Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.

Rule changes for FAR Part 33

Subparts and sections

Subpart 33.1: Protests

Subpart 33.2: Disputes and Appeals

← Part 32: Contract FinancingPart 34: Major System Acquisition →

All FAR parts

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.