FAR 49.202 Profit.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section explains how profit is determined for the terminated portion of a contract. It allows profit on preparations and work done, but not on settlement expenses, anticipatory profits, or consequential damages. It lists factors to consider in negotiating profit and provides special rules for construction contracts.
Applies to: Contractors with terminated contracts and the terminating contracting officer (TCO).
What it requires
- The TCO shall allow profit on preparations made and work done by the contractor for the terminated portion of the contract but not on settlement expenses.
- Anticipatory profits and consequential damages shall not be allowed.
- Profit shall not be allowed for material or services not delivered by a subcontractor as of the effective date of termination.
- When computing profit on a terminated construction contract, the contracting officer shall comply with paragraphs (a) and (b), allow profit on settlements with construction subcontractors for actual work in place, and exclude profit on settlements for materials on hand and preparations made to compl
Key terms: TCO · terminated portion · settlement expenses · anticipatory profits · consequential damages
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) The TCO shall allow profit on preparations made and work done by the contractor for the terminated portion of the contract but not on the settlement expenses. Anticipatory profits and consequential damages shall not be allowed (but see 49.108-5). Profit for the contractor's efforts in settling subcontractor proposals shall not be based on the dollar amount of the subcontract settlement agreements but the contractor's efforts will be considered in determining the overall rate of profit allowed the contractor. Profit shall not be allowed the contractor for material or services that, as of the effective date of termination, have not been delivered by a subcontractor, regardless of the percentage of completion. The TCO may use any reasonable method to arrive at a fair profit.
(b) In negotiating or determining profit, factors to be considered include—
(1) Extent and difficulty of the work done by the contractor as compared with the total work required by the contract (engineering estimates of the percentage of completion ordinarily should not be required, but if available should be considered);
(2) Engineering work, production scheduling, planning, technical study and supervision, and other necessary services;
(3) Efficiency of the contractor, with particular regard to—
(i) Attainment of quantity and quality production;
(ii) Reduction of costs;
(iii) Economic use of materials, facilities, and manpower; and
(iv) Disposition of termination inventory;
(4) Amount and source of capital and extent of risk assumed;
(5) Inventive and developmental contributions, and cooperation with the Government and other contractors in supplying technical assistance;
(6) Character of the business, including the source and nature of materials and the complexity of manufacturing techniques;
(7) The rate of profit that the contractor would have earned had the contract been completed;
(8) The rate of profit both parties contemplated at the time the contract was negotiated; and
(9) Character and difficulty of subcontracting, including selection, placement, and management of subcontracts, and effort in negotiating settlements of terminated subcontracts.
(c) When computing profit on the terminated portion of a construction contract, the contracting officer shall—
(1) Comply with paragraphs (a) and (b) above;
(2) Allow profit on the prime contractor's settlements with construction subcontractors for actual work in place at the job site; and
(3) Exclude profit on the prime contractor's settlements with construction subcontractors for materials on hand and for preparations made to complete the work.
Sections it refers to
- 49.108-5 Recognition of judgments and arbitration awards.
← 49.201 General. · 49.203 Adjustment for loss. →
Rule changes for FAR Part 49
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.