FAR and DFARS › FAR Part 49: Termination of Contracts › Subpart 49.2

FAR 49.206-2 Bases for settlement proposals.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section explains the two main ways contractors can submit settlement proposals after a contract termination: the inventory basis, which is preferred, and the total cost basis, which requires advance approval. It matters because it tells contractors what costs they can claim and how to format their proposals to get reimbursed for terminated work.

Applies to: Contractors submitting settlement proposals for terminated contracts.

What it requires

  • Use the inventory basis for settlement proposals unless it is not practicable or would unduly delay settlement.
  • Under the inventory basis, itemize separately the specified cost categories and deduct advance/progress payments and credits.
  • Under the total cost basis, itemize all costs incurred up to the termination date, add subcontractor settlements and settlement expenses, make profit/loss adjustments, and deduct contract price for delivered items and advance/progress payments and credits.
  • For a complete termination of a construction or lump-sum professional services contract, use the total cost basis, omit Line 10 from SF-1436, and reduce the gross settlement by all progress and other payments.

Key terms: inventory basis · total cost basis · settlement proposal · TCO · SF-1436

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) Inventory basis. (1) Use of the inventory basis for settlement proposals is preferred. Under this basis, the contractor may propose only costs allocable to the terminated portion of the contract, and the settlement proposal must itemize separately—

(i) Metals, raw materials, purchased parts, work in process, finished parts, components, dies, jigs, fixtures, and tooling, at purchase or manufacturing cost;

(ii) Charges such as engineering costs, initial costs, and general administrative costs;

(iii) Costs of settlements with subcontractors;

(iv) Settlement expenses; and

(v) Other proper charges.

(2) An allowance for profit (49.202) or adjustment for loss (49.203(b)) must be made to complete the gross settlement proposal. All unliquidated advance and progress payments and all disposal and other credits known when the proposal is submitted must then be deducted.

(3) This inventory basis is also appropriate for use under the following circumstances:

(i) The partial termination of a construction or related professional services contract.

(ii) The partial or complete termination of supply orders under any terminated construction contract.

(iii) The complete termination of a unit-price (as distinguished from a lump-sum) professional services contract.

(b) Total cost basis. (1) When use of the inventory basis is not practicable or will unduly delay settlement, the total-cost basis (SF-1436) may be used if approved in advance by the TCO as in the following examples:

(i) If production has not commenced and the accumulated costs represent planning and preproduction or get ready expenses.

(ii) If, under the contractor's accounting system, unit costs for work in process and finished products cannot readily be established.

(iii) If the contract does not specify unit prices.

(iv) If the termination is complete and involves a letter contract.

(2) When the total-cost basis is used under a complete termination, the contractor must itemize all costs incurred under the contract up to the effective date of termination. The costs of settlements with subcontractors and applicable settlement expenses must also be added. An allowance for profit (49.202) or adjustment for loss (49.203(c)) must be made. The contract price for all end items delivered or to be delivered and accepted must be deducted. All unliquidated advance and progress payments and disposal and other credits known when the proposal is submitted must also be deducted.

(3) When the total-cost basis is used under a partial termination, the settlement proposal shall not be submitted until completion of the continued portion of the contract. The settlement proposal must be prepared as in subparagraph (2) above, except that all costs incurred to the date of completion of the continued portion of the contract must be included.

(4) If a construction contract or a lump-sum professional services contract is completely terminated, the contractor shall—

(i) Use the total cost basis of settlement;

(ii) Omit Line 10 “Deduct-Finished Product Invoiced or to be Invoiced” from Section II of Standard Form-1436) Settlement Proposal (Total Cost Basis); and

(iii) Reduce the gross amount of the settlement by the total of all progress and other payments.

(c) Other basis. Settlement proposals may not be submitted on any basis other than paragraph (a) or (b) above without the prior approval of the chief of the contracting or contract administration office.

Sections it refers to

Sections that refer to it

  • 49.203 Adjustment for loss.
  • 49.602-1 Termination settlement proposal forms.

← 49.206-1 Submission of settlement proposals. · 49.206-3 Submission of inventory disposal schedules. →

Rule changes for FAR Part 49

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 49.206-2 Bases for settlement proposals · SpendQuery