The FAR overhaul, side by side
FAR Part 12: Acquisition of Commercial Products and Commercial Services
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 38 sections, 8,759 words (Part 12 as in force, eCFR as of Oct 29, 2026). Overhaul text: 26 sections, 6,211 words (on acquisition.gov ↗, issued Aug 14, 2025, updated Apr 20, 2026). By number: 0 the same, 16 changed, 22 not in the overhaul (5 with the same heading under another number), 10 new.
12.402: Changed (11% alike)
Today: Acceptance.
(a) The acceptance paragraph in 52.212-4 is based upon the assumption that the Government will rely on the contractor's assurances that the commercial product or commercial service tendered for acceptance conforms to the contract requirements. The Government inspection of commercial products or commercial services will not prejudice its other rights under the acceptance paragraph. Additionally, although the paragraph does not address the issue of rejection, the Government always has the right to refuse acceptance of nonconforming items. This paragraph is generally appropriate when the Government is acquiring noncomplex commercial products and commercial services.
(b) Other acceptance procedures may be more appropriate for the acquisition of complex commercial products or commercial services, or commercial products or commercial services used in critical applications. In such cases, the contracting officer shall include alternative inspection procedure(s) in an addendum and ensure these procedures and the postaward remedies adequately protect the interests of the Government. The contracting officer must carefully examine the terms and conditions of any express warranty with regard to the effect it may have on the Government's available postaward remedies (see 12.404).
(c) The acquisition of commercial products or commercial services under other circumstances such as on an “as is” basis may also require acceptance procedures different from those contained in 52.212-4. The contracting officer should consider the effect the specific circumstances will have on the acceptance paragraph as well as other paragraphs of the clause.
Overhaul text: Purchase guidelines.
(a) To the extent practicable, distribute micro-purchases equitably among qualified suppliers.
(b) Micro-purchases may be awarded without soliciting competitive quotations if the contracting officer or individual appointed in accordance with 1.403-2(b) considers the price to be reasonable.
(c) The administrative cost of verifying the reasonableness of the price for purchases may more than offset potential savings from detecting instances of overpricing. Therefore, action to verify price reasonableness need only be taken if there is—
(1) A lack of understanding of competitive pricing; or
(2) Reason to suspect that a price is not reasonable.
(d) If the contracting officer solicited competitive quotations and made award to a supplier that did not provide the lowest quote, documentation of the award must include identification of the suppliers solicited and a brief explanation of the award decision.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 12.000 | Scope of part. | Scope. | Changed · 46% alike | 67 → 58 |
| 12.001 | Definition. | Applicability. | Changed · 7% alike | 30 → 293 |
| 12.101 | Policy. | Preference. | Changed · 63% alike | 81 → 58 |
| 12.102 | Applicability. | Restricting competition. | Changed · 8% alike | 338 → 139 |
| 12.103 | Commercially available off-the-shelf (COTS) items. | Small business. | Changed · 12% alike | 47 → 39 |
| 12.104 | none | Contract type. | New number Same heading as today's 12.207 | – → 371 |
| 12.105 | none | Quality requirements. | New number | – → 101 |
| 12.106 | none | Technical data. | New number Same heading as today's 12.211 | – → 64 |
| 12.107 | none | Computer software. | New number Same heading as today's 12.212 | – → 150 |
| 12.108 | none | Contract financing. | New number Same heading as today's 12.210 | – → 29 |
| 12.109 | none | Cost Accounting Standards. | New number Same heading as today's 12.214 | – → 24 |
| 12.200 | none | Applicability. | New number | – → 92 |
| 12.201 | General. | Solicitation procedures. | Changed · 0% alike | 47 → 0 |
| 12.201-1 | none | Simplified procedures. | New number | – → 994 |
| 12.201-2 | none | Other procedures. | New number | – → 60 |
| 12.202 | Market research and description of agency need. | Publicizing. | Changed · 11% alike | 219 → 340 |
| 12.203 | Procedures for solicitation, evaluation, and award. | Evaluation. | Changed · 8% alike | 141 → 392 |
| 12.204 | Solicitation/contract form. | Award. | Changed · 11% alike | 93 → 204 |
| 12.205 | Offers. | Solicitation provisions and contract clauses. | Changed · 4% alike | 143 → 1740 |
| 12.206 | Use of past performance. | none | Not in the overhaul | 57 → – |
| 12.207 | Contract type. | none | Not in the overhaul Same heading at 12.104 | 832 → – |
| 12.208 | Contract quality assurance. | none | Not in the overhaul | 86 → – |
| 12.209 | Determination of price reasonableness. | none | Not in the overhaul | 98 → – |
| 12.210 | Contract financing. | none | Not in the overhaul Same heading at 12.108 | 32 → – |
| 12.211 | Technical data. | none | Not in the overhaul Same heading at 12.106 | 95 → – |
| 12.212 | Computer software. | none | Not in the overhaul Same heading at 12.107 | 150 → – |
| 12.213 | Other commercial practices. | none | Not in the overhaul | 114 → – |
| 12.214 | Cost Accounting Standards. | none | Not in the overhaul Same heading at 12.109 | 99 → – |
| 12.215 | Notification of overpayment. | none | Not in the overhaul | 27 → – |
| 12.216 | Unenforceability of unauthorized obligations. | none | Not in the overhaul | 112 → – |
| 12.300 | Scope of subpart. | none | Not in the overhaul | 16 → – |
| 12.301 | Solicitation provisions and contract clauses for the acquisition of commercial products and commercial services. | Notifications. | Changed · 2% alike | 1356 → 140 |
| 12.302 | Tailoring of provisions and clauses for the acquisition of commercial products and commercial services. | Subcontracts. | Changed · 3% alike | 417 → 13 |
| 12.303 | Contract format. | Cancellations. | Changed · 7% alike | 205 → 89 |
| 12.304 | none | Terminations. | New number | – → 225 |
| 12.401 | General. | General. | Changed · 18% alike | 72 → 132 |
| 12.402 | Acceptance. | Purchase guidelines. | Changed · 11% alike | 240 → 137 |
| 12.403 | Termination. | Methods. | Changed · 5% alike | 675 → 327 |
| 12.404 | Warranties. | none | Not in the overhaul | 440 → – |
| 12.500 | Scope of subpart. | none | Not in the overhaul | 96 → – |
| 12.501 | Applicability. | none | Not in the overhaul | 107 → – |
| 12.502 | Procedures. | none | Not in the overhaul | 160 → – |
| 12.503 | Applicability of certain laws to Executive agency contracts for the acquisition of commercial products and commercial services. | none | Not in the overhaul | 461 → – |
| 12.504 | Applicability of certain laws to subcontracts for the acquisition of commercial products and commercial services. | none | Not in the overhaul | 407 → – |
| 12.505 | Applicability of certain laws to contracts for the acquisition of COTS items. | none | Not in the overhaul | 211 → – |
| 12.601 | General. | none | Not in the overhaul | 62 → – |
| 12.602 | Streamlined evaluation of offers. | none | Not in the overhaul | 322 → – |
| 12.603 | Streamlined solicitation for commercial products or commercial services. | none | Not in the overhaul | 604 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress