Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 30 sections, 8,190 words (Part 30 as in force, eCFR as of Oct 29, 2026). Overhaul text: 19 sections, 7,406 words (on acquisition.gov ↗, issued Aug 28, 2025). By number: 0 the same, 5 changed, 25 not in the overhaul (10 with the same heading under another number), 14 new.

30.202: Changed (0% alike)

Today: Disclosure requirements.

This section in plain English

Overhaul text: Waiver.

On acquisition.gov ↗

(a) The head of the agency-

(1) May waive the applicability of CAS for a particular contract or subcontract under the conditions listed in paragraph (b) below; and

(2) Must not delegate this waiver authority to any official in the agency below the senior contract policymaking level.

(b) The head of the agency may grant a waiver when one of the following conditions exists:

(1) The contract or subcontract value is less than 15 million, and the head of the agency determines, in writing, that the segment of the contractor or subcontractor that will perform the contract or subcontract-

(i) Is primarily engaged in the sale of commercial products or commercial services; and

(ii) Has no contracts or subcontracts that are subject to CAS.

(2) The head of the agency determines that exceptional circumstances exist whereby a waiver of CAS is necessary to meet the needs of the agency. Exceptional circumstances exist only when the benefits to be derived from waiving the CAS outweigh the risk associated with the waiver. The determination that exceptional circumstances exist must-

(i) Be in writing; and

(ii) Include a statement of the specific circumstances that justify granting the waiver.

(c) When one of the conditions in paragraph (b) of this section exists, the request for waiver must include the following:

(1) The amount of the proposed award.

(2) The contract or subcontract type.

(3) Whether the segment(s) that will perform the contract or subcontract has CAS-covered contracts or subcontracts.

(4) A description of the item(s) being procured.

(5) A statement why the contractor or subcontractor will not accept the contract or subcontract if CAS applies.

(6) Whether certified cost or pricing data will be obtained, and if so, a discussion of how the data will be used in negotiating the contract or subcontract price.

(7) The benefits to the Government of waiving CAS.

(8) The potential risk to the Government of waiving CAS.

(9) The date by which the waiver is needed.

(10) Any other information that may be useful in evaluating the request.

(d) When neither of the conditions in paragraph (b) of this section exists, the waiver request must be prepared in accordance with 48 CFR 9903.201-5(e) and submitted to the CAS Board.

(e) Each agency must report any waivers granted under paragraph (a) of this subsection to the CAS Board, on a fiscal year basis, not later than 90 days after the close of the Government’s fiscal year.

Section by section

SectionTodayOverhaul textStatusWords
30.000Scope of part.Scope of part.Changed · 63% alike56 → 26
30.001Definitions.Definitions.Changed · 89% alike496 → 532
30.101Cost Accounting Standards.Cost Accounting Standards.Changed · 65% alike92 → 186
30.102Cost Accounting Standards Board publication.noneNot in the overhaul51 → –
30.201Contract requirements.Applicability.Changed · 26% alike66 → 128
30.201-1CAS applicability.noneNot in the overhaul51 → –
30.201-2Types of CAS coverage.noneNot in the overhaul5 → –
30.201-3Solicitation provisions.noneNot in the overhaul
Same heading at 30.204
124 → –
30.201-4Contract clauses.noneNot in the overhaul
Same heading at 30.205
491 → –
30.201-5Waiver.noneNot in the overhaul430 → –
30.201-6Findings.noneNot in the overhaul5 → –
30.201-7Cognizant Federal agency responsibilities.noneNot in the overhaul5 → –
30.202Disclosure requirements.Waiver.Changed · 0% alike0 → 413
30.202-1General requirements.noneNot in the overhaul5 → –
30.202-2Impracticality of submission.noneNot in the overhaul5 → –
30.202-3Amendments and revisions.noneNot in the overhaul5 → –
30.202-4Privileged and confidential information.noneNot in the overhaul5 → –
30.202-5Filing disclosure statements.noneNot in the overhaul5 → –
30.202-6Responsibilities.noneNot in the overhaul176 → –
30.202-7Determinations.noneNot in the overhaul299 → –
30.202-8Subcontractor disclosure statements.noneNot in the overhaul70 → –
30.203noneExemption.New number– → 29
30.204noneSolicitation provisions.New number
Same heading as today's 30.201-3
– → 53
30.205noneContract clauses.New number
Same heading as today's 30.201-4
– → 472
30.301noneContractor disclosure statements.New number– → 130
30.302noneChanges to disclosed or established cost accounting practices.New number
Same heading as today's 30.603
– → 0
30.302-1noneRequired changes.New number
Same heading as today's 30.603-1
– → 454
30.302-2noneUnilateral and desirable changes.New number
Same heading as today's 30.603-2
– → 561
30.302-3noneProcessing changes to disclosed or established cost accounting practices.New number
Same heading as today's 30.604
– → 339
30.401noneCAS administration.New number– → 148
30.402noneMateriality.New number
Same heading as today's 30.602
– → 153
30.403noneChanges to disclosed or established cost accounting practices.New number
Same heading as today's 30.603
– → 1028
30.404noneProcessing noncompliances.New number
Same heading as today's 30.605
– → 1602
30.405noneResolving cost impacts.New number
Same heading as today's 30.606
– → 1066
30.406noneSubcontract administration.New number
Same heading as today's 30.607
– → 86
30.601Responsibility.noneNot in the overhaul155 → –
30.602Materiality.noneNot in the overhaul
Same heading at 30.402
155 → –
30.603Changes to disclosed or established cost accounting practices.noneNot in the overhaul
Same heading at 30.302
0 → –
30.603-1Required changes.noneNot in the overhaul
Same heading at 30.302-1
450 → –
30.603-2Unilateral and desirable changes.noneNot in the overhaul
Same heading at 30.302-2
557 → –
30.604Processing changes to disclosed or established cost accounting practices.noneNot in the overhaul
Same heading at 30.302-3
1422 → –
30.605Processing noncompliances.noneNot in the overhaul
Same heading at 30.404
1713 → –
30.606Resolving cost impacts.noneNot in the overhaul
Same heading at 30.405
1208 → –
30.607Subcontract administration.noneNot in the overhaul
Same heading at 30.406