The FAR overhaul, side by side
FAR Part 32: Contract Financing
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 175 sections, 36,904 words (Part 32 as in force, eCFR as of Oct 29, 2026). Overhaul text: 171 sections, 34,567 words (on acquisition.gov ↗, issued Sep 30, 2025). By number: 52 the same, 115 changed, 8 not in the overhaul, 4 new.
32.1004: Changed (98% alike)
Today: Procedures.
Performance-based payments may be made either on a whole contract or on a deliverable item basis, unless otherwise prescribed by agency regulations. Financing payments to be made on a whole contract basis are applicable to the entire contract, and not to specific deliverable items. Financing payments to be made on a deliverable item basis are applicable to a specific individual deliverable item. (A deliverable item for these purposes is a separate item with a distinct unit price. Thus, a line item for 10 airplanes, with a unit price of $1,000,000 each, has 10 deliverable items-the separate planes. A line item for 1 lot of 10 airplanes, with a lot price of $10,000,000, has only one deliverable item-the lot.)
(a) Establishing performance bases. (1) The basis for performance-based payments may be either specifically described events (e.g., milestones) or some measurable criterion of performance. Each event or performance criterion that will trigger a finance payment shall be an integral and necessary part of contract performance and shall be identified in the contract, along with a description of what constitutes successful performance of the event or attainment of the performance criterion. The signing of contracts or modifications, the exercise of options, the passage of time, or other such occurrences do not represent meaningful efforts or actions and shall not be identified as events or criteria for performance-based payments. An event need not be a critical event in order to trigger a payment, but the Government must be able to readily verify successful performance of each such event or performance criterion.
(2) Events or criteria may be either severable or cumulative. The successful completion of a severable event or criterion is independent of the accomplishment of any other event or criterion. Conversely, the successful accomplishment of a cumulative event or criterion is dependent upon the previous accomplishment of another event. A contract may provide for more than one series of severable and/or cumulative performance events or criteria performed in parallel. The contracting officer shall include the following in the contract:
(i) The contract shall not permit payment for a cumulative event or criterion until the dependent event or criterion has been successfully completed.
(ii) The contract shall specifically identify severable events or criteria.
(iii) The contract shall specifically identify cumulative events or criteria and identify which events or criteria are preconditions for the successful achievement of each event or criterion.
(iv) Because performance-based payments are contract financing, events or criteria shall not serve as a vehicle to reward the contractor for completion of performance levels over and above what is required for successful completion of the contract.
(v) If payment of performance-based finance amounts is on a deliverable item basis, each event or performance criterion shall be part of the performance necessary for that deliverable item and shall be identified to a specific line item or subline item.
(b) Establishing performance-based finance payment amounts. (1) The contracting officer shall establish a complete, fully defined schedule of events or performance criteria and payment amounts when negotiating contract terms. If a contract action significantly affects the price, or event or performance criterion, the contracting officer responsible for pricing the contract modification shall adjust the performance-based payment schedule appropriately.
(2) Total performance-based payments shall—
(i) Reflect prudent contract financing provided only to the extent needed for contract performance (see 32.104(a)); and
(ii) Not exceed 90 percent of the contract price if on a whole contract basis, or 90 percent of the delivery item price if on a delivery item basis.
(3) The contract shall specifically state the amount of each performance-based payment either as a dollar amount or as a percentage of a specifically identified price (e.g., contract price or unit price of the deliverable item). The payment of contract financing has a cost to the Government in terms of interest paid by the Treasury to borrow funds to make the payment. Because the contracting officer has wide discretion as to the timing and amount of the performance-based payments, the contracting officer shall ensure that—
(i) The total contract price is fair and reasonable, all factors considered; and
(ii) Performance-based payment amounts are commensurate with the value of the performance event or performance criterion and are not expected to result in an unreasonably low or negative level of contractor investment in the contract. To confirm sufficient investment, the contracting officer may request expenditure profile information from offerors, but only if other information in the proposal, or information otherwise available to the contracting officer, is expected to be insufficient.
(4) Unless agency procedures prescribe the bases for establishing performance-based payment amounts, contracting officers may establish them on any rational basis, including (but not limited to)—
(i) Engineering estimates of stages of completion;
(ii) Engineering estimates of hours or other measures of effort to be expended in performance of an event or achievement of a performance criterion; or
(iii) The estimated projected cost of performance of particular events.
(5) When subsequent contract modifications are issued, the contracting officer shall adjust the performance-based payment schedule as necessary to reflect the actions required by those contract modifications.
(c) Instructions for multiple appropriations. If there is more than one appropriation account (or subaccount) funding payments on the contract, the contracting officer shall provide instructions to the Government payment office for distribution of financing payments to the respective funds accounts. Distribution instructions shall be consistent with the contract's liquidation provisions.
(d) Liquidating performance-based finance payments. Performance-based amounts shall be liquidated by deducting a percentage or a designated dollar amount from the delivery payments. The contracting officer shall specify the liquidation rate or designated dollar amount in the contract. The method of liquidation shall ensure complete liquidation no later than final payment.
(1) If the contracting officer establishes the performance-based payments on a delivery item basis, the liquidation amount for each line item is the percent of that delivery item price that was previously paid under performance-based finance payments or the designated dollar amount.
(2) If the performance-based finance payments are on a whole contract basis, liquidation is by predesignated liquidation amounts or liquidation percentages.
(e) Competitive negotiated solicitations. (1) If a solicitation requests offerors to propose performance-based payments, the solicitation shall specify—
(i) What, if any, terms shall be included in all offers; and
(ii) The extent to which and how offeror-proposed performance-based payment terms will be evaluated. Unless agencies prescribe other evaluation procedures, if the contracting officer anticipates that the cost of providing performance-based payments would have a significant impact on determining the best value offer, the solicitation should state that the evaluation of the offeror's proposed prices will include an adjustment to reflect the estimated cost to the Government of providing each offeror's proposed performance-based payments (see Alternate I to the provision at 52.232-28).
(2) The contracting officer shall—
(i) Review the proposed terms to ensure they comply with this section; and
(ii) Use the adjustment method at 32.205(c) if the price is to be adjusted for evaluation purposes in accordance with paragraph (e)(1)(ii) of this section.
Overhaul text: Procedures.
Performance-based payments may be made either on a whole contract or on a deliverable item basis, unless otherwise prescribed by agency regulations. Financing payments to be made on a whole contract basis are applicable to the entire contract, and not to specific deliverable items. Financing payments to be made on a deliverable item basis are applicable to a specific individual deliverable item. (A deliverable item for these purposes is a separate item with a distinct unit price. Thus, a line item for 10 airplanes, with a unit price of $1,000,000 each, has 10 deliverable items-the separate planes. A line item for 1 lot of 10 airplanes, with a lot price of $10,000,000, has only one deliverable item-the lot.)
(a) Establishing performance bases.
(1) The basis for performance-based payments may be either specifically described events (e.g., milestones) or some measurable criterion of performance. Each event or performance criterion that will trigger a finance payment must be an integral and necessary part of contract performance and must be identified in the contract, along with a description of what constitutes successful performance of the event or attainment of the performance criterion. The signing of contracts or modifications, the exercise of options, the passage of time, or other such occurrences do not represent meaningful efforts or actions and must not be identified as events or criteria for performance-based payments. An event need not be a critical event in order to trigger a payment, but the Government must be able to readily verify successful performance of each such event or performance criterion.
(2) Events or criteria may be either severable or cumulative. The successful completion of a severable event or criterion is independent of the accomplishment of any other event or criterion. Conversely, the successful accomplishment of a cumulative event or criterion is dependent upon the previous accomplishment of another event. A contract may provide for more than one series of severable and/or cumulative performance events or criteria performed in parallel. The contracting officer must include the following in the contract:
(i) The contract must not permit payment for a cumulative event or criterion until the dependent event or criterion has been successfully completed.
(ii) The contract must specifically identify severable events or criteria.
(iii) The contract must specifically identify cumulative events or criteria and identify which events or criteria are preconditions for the successful achievement of each event or criterion.
(iv) Because performance-based payments are contract financing, events or criteria must not serve as a vehicle to reward the contractor for completion of performance levels over and above what is required for successful completion of the contract.
(v) If payment of performance-based finance amounts is on a deliverable item basis, each event or performance criterion must be part of the performance necessary for that deliverable item and must be identified to a specific line item or subline item.
(b) Establishing performance-based finance payment amounts.
(1) The contracting officer must establish a complete, fully defined schedule of events or performance criteria and payment amounts when negotiating contract terms. If a contract action significantly affects the price, or event or performance criterion, the contracting officer responsible for pricing the contract modification must adjust the performance-based payment schedule appropriately.
(2) Total performance-based payments must—
(i) Reflect prudent contract financing provided only to the extent needed for contract performance (see 32.104(a)); and
(ii) Not exceed 90 percent of the contract price if on a whole contract basis, or 90 percent of the delivery item price if on a delivery item basis.
(3) The contract must specifically state the amount of each performance-based payment either as a dollar amount or as a percentage of a specifically identified price (e.g., contract price or unit price of the deliverable item). The payment of contract financing has a cost to the Government in terms of interest paid by the Treasury to borrow funds to make the payment. Because the contracting officer has wide discretion as to the timing and amount of the performance-based payments, the contracting officer must ensure that—
(i) The total contract price is fair and reasonable, all factors considered; and
(ii) Performance-based payment amounts are commensurate with the value of the performance event or performance criterion and are not expected to result in an unreasonably low or negative level of contractor investment in the contract. To confirm sufficient investment, the contracting officer may request expenditure profile information from offerors, but only if other information in the proposal, or information otherwise available to the contracting officer, is expected to be insufficient.
(4) Unless agency procedures prescribe the bases for establishing performance-based payment amounts, contracting officers may establish them on any rational basis, including (but not limited to)—
(i) Engineering estimates of stages of completion;
(ii) Engineering estimates of hours or other measures of effort to be expended in performance of an event or achievement of a performance criterion; or
(iii) The estimated projected cost of performance of particular events.
(5) When subsequent contract modifications are issued, the contracting officer must adjust the performance-based payment schedule as necessary to reflect the actions required by those contract modifications.
(c) Instructions for multiple appropriations. If there is more than one appropriation account (or subaccount) funding payments on the contract, the contracting officer must provide instructions to the Government payment office for distribution of financing payments to the respective funds accounts. Distribution instructions must be consistent with the contract's liquidation provisions.
(d) Liquidating performance-based finance payments. Performance-based amounts must be liquidated by deducting a percentage or a designated dollar amount from the delivery payments. The contracting officer must specify the liquidation rate or designated dollar amount in the contract. The method of liquidation must ensure complete liquidation no later than final payment.
(1) If the contracting officer establishes the performance-based payments on a delivery item basis, the liquidation amount for each line item is the percent of that delivery item price that was previously paid under performance-based finance payments or the designated dollar amount.
(2) If the performance-based finance payments are on a whole contract basis, liquidation is by predesignated liquidation amounts or liquidation percentages.
(e) Competitive negotiated solicitations.
(1) If a solicitation requests offerors to propose performance-based payments, the solicitation must specify—
(i) What, if any, terms must be included in all offers; and
(ii) The extent to which and how offeror-proposed performance-based payment terms will be evaluated. Unless agencies prescribe other evaluation procedures, if the contracting officer anticipates that the cost of providing performance-based payments would have a significant impact on determining the best value offer, the solicitation should state that the evaluation of the offeror's proposed prices will include an adjustment to reflect the estimated cost to the Government of providing each offeror's proposed performance-based payments (see Alternate I to the provision at 52.232-28).
(2) The contracting officer must—
(i) Review the proposed terms to ensure they comply with this section; and
(ii) Use the adjustment method at 32.205(c) if the price is to be adjusted for evaluation purposes in accordance with paragraph (e)(1)(ii) of this section.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 32.000 | Scope of part. | Scope of part. | Changed · 83% alike | 100 → 132 |
| 32.001 | Definitions. | Definitions. | Changed · 96% alike | 677 → 634 |
| 32.002 | Applicability of subparts. | Applicability of subparts. | Changed · 93% alike | 139 → 135 |
| 32.003 | Simplified acquisition procedures financing. | Simplified acquisition procedures financing. | Changed · 95% alike | 20 → 20 |
| 32.004 | Contract performance in foreign countries. | Contract performance in foreign countries. | Changed · 98% alike | 63 → 63 |
| 32.005 | Consideration for contract financing. | Consideration for contract financing. | Changed · 98% alike | 254 → 256 |
| 32.006 | Reduction or suspension of contract payments upon finding of fraud. | Reduction or suspension of contract payments upon finding of fraud. | Same | 0 → 0 |
| 32.006-1 | General. | General. | Changed · 100% alike | 196 → 197 |
| 32.006-2 | Definition. | Definition. | Same | 52 → 52 |
| 32.006-3 | Responsibilities. | Responsibilities. | Changed · 94% alike | 34 → 34 |
| 32.006-4 | Procedures. | Procedures. | Changed · 95% alike | 489 → 489 |
| 32.006-5 | Reporting. | Reporting. | Changed · 93% alike | 109 → 105 |
| 32.007 | Contract financing payments. | Contract financing payments. | Changed · 40% alike | 271 → 99 |
| 32.008 | Notification of overpayment. | Notification of overpayment. | Changed · 96% alike | 27 → 27 |
| 32.009 | Providing accelerated payments to small business contractors and to prime contractors that subcontract with a small business concern. | Providing accelerated payments to small business contractors and to prime contractors that subcontract with a small business concern. | Same | 0 → 0 |
| 32.009-1 | General. | General. | Changed · 99% alike | 292 → 292 |
| 32.009-2 | Contract clause. | Contract clause. | Same | 16 → 16 |
| 32.100 | Scope of subpart. | Scope of subpart. | Changed · 97% alike | 29 → 29 |
| 32.101 | Authority. | Authority. | Changed · 87% alike | 39 → 37 |
| 32.102 | Description of contract financing methods. | Description of contract financing methods. | Changed · 82% alike | 420 → 304 |
| 32.103 | Progress payments under construction contracts. | Progress payments under construction contracts. | Changed · 94% alike | 158 → 154 |
| 32.104 | Providing contract financing. | Providing contract financing. | Changed · 99% alike | 520 → 523 |
| 32.105 | Uses of contract financing. | Uses of contract financing. | Changed · 99% alike | 123 → 123 |
| 32.106 | Order of preference. | Order of preference. | Same | 96 → 96 |
| 32.107 | Need for contract financing not a deterrent. | Need for contract financing not a deterrent. | Changed · 99% alike | 71 → 71 |
| 32.108 | Financial consultation. | Financial consultation. | Changed · 90% alike | 62 → 72 |
| 32.109 | Termination financing. | Termination financing. | Changed · 96% alike | 54 → 54 |
| 32.110 | Payment of subcontractors under cost-reimbursement prime contracts. | Payment of subcontractors under cost-reimbursement prime contracts. | Same | 157 → 157 |
| 32.111 | Contract clauses for noncommercial purchases. | Contract clauses for noncommercial purchases. | Changed · 99% alike | 495 → 495 |
| 32.112 | Nonpayment of subcontractors under contracts other than for commercial products and commercial services. | Nonpayment of subcontractors under contracts other than for commercial products and commercial services. | Same | 0 → 0 |
| 32.112-1 | Subcontractor assertions of nonpayment. | Subcontractor assertions of nonpayment. | Changed · 94% alike | 293 → 281 |
| 32.112-2 | Subcontractor requests for information. | Subcontractor requests for information. | Changed · 93% alike | 153 → 143 |
| 32.113 | Customary contract financing. | Customary contract financing. | Same | 261 → 261 |
| 32.114 | Unusual contract financing. | Unusual contract financing. | Changed · 97% alike | 35 → 35 |
| 32.200 | Scope of subpart. | Scope of subpart. | Same | 17 → 17 |
| 32.201 | Statutory authority. | Statutory authority. | Changed · 69% alike | 49 → 87 |
| 32.202 | General. | General. | Same | 0 → 0 |
| 32.202-1 | Policy. | Policy. | Changed · 99% alike | 479 → 479 |
| 32.202-2 | Types of payments for commercial product and commercial service purchases. | Types of payments for commercial product and commercial service purchases. | Changed · 88% alike | 107 → 104 |
| 32.202-3 | Conducting market research about financing terms. | Conducting market research about financing terms. | Same | 114 → 114 |
| 32.202-4 | Security for Government financing. | Security for Government financing. | Changed · 98% alike | 617 → 617 |
| 32.203 | Determining contract financing terms. | Determining contract financing terms. | Same | 65 → 65 |
| 32.204 | Procedures for contracting officer-specified commercial contract financing. | Procedures for contracting officer-specified commercial contract financing. | Changed · 96% alike | 131 → 131 |
| 32.205 | Procedures for offeror-proposed commercial contract financing. | Procedures for offeror-proposed commercial contract financing. | Changed · 100% alike | 373 → 373 |
| 32.206 | Solicitation provisions and contract clauses. | Solicitation provisions and contract clauses. | Changed · 94% alike | 1156 → 1077 |
| 32.207 | Administration and payment of commercial financing payments. | Administration and payment of commercial financing payments. | Changed · 95% alike | 142 → 139 |
| 32.300 | Scope of subpart. | Scope of subpart. | Changed · 87% alike | 28 → 25 |
| 32.301 | Definitions. | Definitions. | Changed · 66% alike | 113 → 56 |
| 32.302 | Authority. | Authority. | Changed · 95% alike | 95 → 88 |
| 32.303 | General. | General. | Changed · 73% alike | 430 → 259 |
| 32.304 | Procedures. | [Reserved] | Same | 0 → 0 |
| 32.304-1 | Application for guarantee. | none | Not in the overhaul | 221 → – |
| 32.304-2 | Certificate of eligibility. | none | Not in the overhaul | 637 → – |
| 32.304-3 | Asset formula. | none | Not in the overhaul | 154 → – |
| 32.304-4 | Guarantee amount and maturity. | none | Not in the overhaul | 123 → – |
| 32.304-5 | Assignment of claims under contracts. | none | Not in the overhaul | 263 → – |
| 32.304-6 | Other collateral security. | none | Not in the overhaul | 48 → – |
| 32.304-7 | Contract surety bonds and loan guarantees. | none | Not in the overhaul | 171 → – |
| 32.304-8 | Other borrowing. | none | Not in the overhaul | 156 → – |
| 32.305 | Loan guarantees for terminated contracts. | [Reserved] | Changed · 0% alike | 183 → 0 |
| 32.306 | Loan guarantees for subcontracts. | [Reserved] | Changed · 0% alike | 85 → 0 |
| 32.400 | Scope of subpart. | Scope of subpart. | Changed · 85% alike | 47 → 38 |
| 32.401 | Statutory authority. | Statutory authority. | Changed · 90% alike | 62 → 58 |
| 32.402 | General. | General. | Changed · 94% alike | 444 → 427 |
| 32.403 | Applicability. | [Reserved] | Changed · 0% alike | 238 → 0 |
| 32.404 | Exclusions. | Exclusions. | Changed · 97% alike | 133 → 132 |
| 32.405 | Applying Pub. L. 85-804 to advance payments under sealed bid contracts. | Applying Pub.L.85-804 to advance payments under sealed bid contracts. | Changed · 99% alike | 168 → 168 |
| 32.406 | Letters of credit. | Letters of credit. | Changed · 95% alike | 372 → 355 |
| 32.407 | Interest. | Interest. | Changed · 95% alike | 387 → 389 |
| 32.408 | Application for advance payments. | Application for advance payments. | Changed · 91% alike | 299 → 276 |
| 32.409 | Contracting officer action. | Contracting officer action. | Changed · 97% alike | 34 → 34 |
| 32.409-1 | Recommendation for approval. | Recommendation for approval. | Changed · 99% alike | 159 → 159 |
| 32.409-2 | Recommendation for disapproval. | Recommendation for disapproval. | Changed · 97% alike | 31 → 31 |
| 32.409-3 | Security, supervision, and covenants. | Security, supervision, and covenants. | Changed · 99% alike | 444 → 446 |
| 32.410 | Findings, determination, and authorization. | Findings, determination, and authorization. | Changed · 96% alike | 733 → 729 |
| 32.411 | Agreement for special account at a financial institution. | Agreement for special account at a financial institution. | Changed · 99% alike | 636 → 637 |
| 32.412 | Contract clause. | Contract clause. | Changed · 96% alike | 182 → 178 |
| 32.500 | Scope of subpart. | Scope of subpart. | Changed · 96% alike | 76 → 81 |
| 32.501 | General. | General. | Changed · 98% alike | 81 → 81 |
| 32.501-1 | Customary progress payment rates. | Customary progress payment rates. | Same | 152 → 152 |
| 32.501-2 | Unusual progress payments. | Unusual progress payments. | Same | 124 → 124 |
| 32.501-3 | Contract price. | Contract price. | Changed · 99% alike | 205 → 205 |
| 32.501-4 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 32.501-5 | Other protective terms. | Other protective terms. | Changed · 99% alike | 97 → 95 |
| 32.502 | Preaward matters. | Preaward matters. | Same | 34 → 34 |
| 32.502-1 | Use of customary progress payments. | Use of customary progress payments. | Same | 39 → 39 |
| 32.502-2 | Contract finance office clearance. | Contract finance office clearance. | Changed · 99% alike | 116 → 116 |
| 32.502-3 | Solicitation provisions. | Solicitation provisions. | Changed · 93% alike | 150 → 140 |
| 32.502-4 | Contract clauses. | Contract clauses. | Changed · 100% alike | 334 → 334 |
| 32.503 | Postaward matters. | Postaward matters. | Same | 34 → 34 |
| 32.503-1 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 32.503-2 | Supervision of progress payments. | Supervision of progress payments. | Changed · 100% alike | 257 → 257 |
| 32.503-3 | Initiation of progress payments and review of accounting system. | Initiation of progress payments and review of accounting system. | Changed · 99% alike | 152 → 152 |
| 32.503-4 | Approval of progress payment requests. | Approval of progress payment requests. | Changed · 100% alike | 169 → 168 |
| 32.503-5 | Administration of progress payments. | Administration of progress payments. | Changed · 99% alike | 237 → 236 |
| 32.503-6 | Suspension or reduction of payments. | Suspension or reduction of payments. | Changed · 92% alike | 1099 → 1220 |
| 32.503-7 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 32.503-8 | Liquidation rates—ordinary method. | Liquidation rates-ordinary method. | Same | 77 → 77 |
| 32.503-9 | Liquidation rates—alternate method. | Liquidation rates—alternate method. | Changed · 98% alike | 442 → 442 |
| 32.503-10 | Establishing alternate liquidation rates. | Establishing alternate liquidation rates. | Same | 260 → 260 |
| 32.503-11 | Adjustments for price reduction. | Adjustments for price reduction. | Changed · 98% alike | 97 → 97 |
| 32.503-12 | Maximum unliquidated amount. | Maximum unliquidated amount. | Changed · 98% alike | 158 → 160 |
| 32.503-13 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 32.503-14 | Protection of Government title. | Protection of Government title. | Changed · 100% alike | 210 → 210 |
| 32.503-15 | Application of Government title terms. | Application of Government title terms. | Changed · 99% alike | 256 → 258 |
| 32.503-16 | Risk of loss. | Risk of loss. | Same | 153 → 153 |
| 32.504 | Subcontracts under prime contracts providing progress payments. | Subcontracts under prime contracts providing progress payments. | Changed · 99% alike | 656 → 658 |
| 32.600 | Scope of subpart. | Scope of subpart. | Same | 48 → 48 |
| 32.601 | General. | General. | Same | 260 → 260 |
| 32.602 | Responsibilities. | Responsibilities. | Changed · 99% alike | 109 → 109 |
| 32.603 | Debt determination. | Debt determination. | Changed · 98% alike | 105 → 105 |
| 32.604 | Demand for payment. | Demand for payment. | Changed · 99% alike | 1007 → 1007 |
| 32.605 | Final decisions. | Final decisions. | Changed · 98% alike | 172 → 172 |
| 32.606 | Debt collection. | Debt collection. | Changed · 98% alike | 155 → 155 |
| 32.607 | Installment payments and deferment of collection. | Installment payments and deferment of collection. | Changed · 98% alike | 232 → 231 |
| 32.607-1 | Installment payments. | Installment payments. | Changed · 97% alike | 30 → 30 |
| 32.607-2 | Deferment of collection. | Deferment of collection. | Changed · 69% alike | 649 → 353 |
| 32.608 | Interest. | Interest. | Same | 0 → 0 |
| 32.608-1 | Interest charges. | Interest charges. | Changed · 98% alike | 53 → 53 |
| 32.608-2 | Interest credits. | Interest credits. | Changed · 98% alike | 257 → 257 |
| 32.609 | Delays in receipt of notices or demands. | Delays in receipt of notices or demands. | Changed · 98% alike | 61 → 61 |
| 32.610 | Compromising debts. | Compromising debts. | Same | 40 → 40 |
| 32.611 | Contract clause. | Contract clause. | Changed · 98% alike | 130 → 126 |
| 32.700 | Scope of subpart. | Scope of subpart. | Changed · 97% alike | 33 → 31 |
| 32.701 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 32.702 | Policy. | Policy. | Changed · 97% alike | 71 → 69 |
| 32.703 | Contract funding requirements. | Contract funding requirements. | Same | 0 → 0 |
| 32.703-1 | General. | General. | Same | 55 → 55 |
| 32.703-2 | Contracts conditioned upon availability of funds. | Contracts conditioned upon availability of funds. | Changed · 99% alike | 208 → 209 |
| 32.703-3 | Contracts crossing fiscal years. | Contracts crossing fiscal years. | Changed · 96% alike | 158 → 155 |
| 32.704 | Limitation of cost or funds. | Limitation of cost or funds. | Changed · 97% alike | 353 → 347 |
| 32.705 | Unenforceability of unauthorized obligations. | Unenforceability of unauthorized obligations. | Changed · 99% alike | 100 → 102 |
| 32.706 | Contract clauses. | Contract clauses. | Same | 0 → 0 |
| 32.706-1 | Clauses for contracting in advance of funds. | Clauses for contracting in advance of funds. | Changed · 98% alike | 99 → 95 |
| 32.706-2 | Clauses for limitation of cost or funds. | Clauses for limitation of cost or funds. | Changed · 71% alike | 65 → 96 |
| 32.706-3 | Clause for unenforceability of unauthorized obligations. | Clause for unenforceability of unauthorized obligations. | Changed · 88% alike | 19 → 15 |
| 32.800 | Scope of subpart. | Scope of subpart. | Changed · 97% alike | 34 → 32 |
| 32.801 | Definitions. | Definitions. | Same | 72 → 72 |
| 32.802 | Conditions. | Conditions. | Same | 170 → 170 |
| 32.803 | Policies. | Policies. | Same | 350 → 350 |
| 32.804 | Extent of assignee's protection. | Extent of assignee's protection. | Changed · 99% alike | 238 → 240 |
| 32.805 | Procedure. | Procedure. | Changed · 97% alike | 680 → 707 |
| 32.806 | Contract clauses. | Contract clauses. | Changed · 98% alike | 151 → 151 |
| 32.900 | Scope of subpart. | Scope of subpart. | Same | 23 → 23 |
| 32.901 | Applicability. | Applicability. | Same | 42 → 42 |
| 32.902 | Definitions. | Definitions. | Same | 88 → 88 |
| 32.903 | Responsibilities. | Responsibilities. | Same | 195 → 195 |
| 32.904 | Determining payment due dates. | Determining payment due dates. | Changed · 93% alike | 1949 → 2221 |
| 32.905 | Payment documentation and process. | Payment documentation and process. | Changed · 100% alike | 741 → 741 |
| 32.906 | Making payments. | Making payments. | Same | 467 → 467 |
| 32.907 | Interest penalties. | Interest penalties. | Changed · 100% alike | 588 → 587 |
| 32.908 | Contract clauses. | Contract clauses. | Same | 468 → 468 |
| 32.909 | Contractor inquiries. | Contractor inquiries. | Same | 94 → 94 |
| 32.1000 | Scope of subpart. | Scope of subpart. | Same | 17 → 17 |
| 32.1001 | Policy. | Policy. | Changed · 99% alike | 149 → 149 |
| 32.1002 | Bases for performance-based payments. | Bases for performance-based payments. | Same | 30 → 30 |
| 32.1003 | Criteria for use. | Criteria for use. | Same | 70 → 70 |
| 32.1004 | Procedures. | Procedures. | Changed · 98% alike | 1206 → 1206 |
| 32.1005 | Solicitation provision and contract clause. | Solicitation provision and contract clause. | Same | 91 → 91 |
| 32.1006 | [Reserved] | [Reserved] | Same | 0 → 0 |
| 32.1007 | Administration and payment of performance-based payments. | Administration and payment of performance-based payments. | Changed · 98% alike | 295 → 295 |
| 32.1008 | Suspension or reduction of performance-based payments. | Suspension or reduction of performance-based payments. | Changed · 98% alike | 51 → 51 |
| 32.1009 | Title. | Title. | Changed · 99% alike | 182 → 182 |
| 32.1010 | Risk of loss. | Risk of loss. | Same | 202 → 202 |
| 32.1100 | Scope of subpart. | Scope of subpart. | Same | 20 → 20 |
| 32.1101 | Statutory requirements. | Statutory requirements. | Same | 28 → 28 |
| 32.1102 | Definitions. | Definitions. | Changed · 99% alike | 125 → 125 |
| 32.1103 | Applicability. | Applicability. | Changed · 99% alike | 313 → 313 |
| 32.1104 | Protection of EFT information. | Protection of EFT information. | Changed · 91% alike | 11 → 11 |
| 32.1105 | Assignment of claims. | Assignment of claims. | Same | 73 → 73 |
| 32.1106 | EFT mechanisms. | EFT mechanisms. | Changed · 99% alike | 172 → 172 |
| 32.1107 | Payment information. | Payment information. | Changed · 97% alike | 33 → 33 |
| 32.1108 | Payment by Governmentwide commercial purchase card. | Payment by Governmentwide commercial purchase card. | Changed · 99% alike | 542 → 543 |
| 32.1109 | EFT information submitted by offerors. | EFT information submitted by offerors. | Changed · 98% alike | 58 → 58 |
| 32.1110 | Solicitation provision and contract clauses. | Solicitation provision and contract clauses. | Changed · 97% alike | 721 → 687 |
| 32.1201 | none | General. | New number | – → 128 |
| 32.1202 | none | Conditions for use. | New number | – → 209 |
| 32.1203 | none | Preparation and execution of orders. | New number | – → 129 |
| 32.1204 | none | Contract clause. | New number | – → 59 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress