The FAR overhaul, side by side

FAR Part 35: Research and Development Contracting

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 25 sections, 5,546 words (Part 35 as in force, eCFR as of Oct 29, 2026). Overhaul text: 16 sections, 2,826 words (on acquisition.gov ↗, issued Jul 24, 2025). By number: 0 the same, 3 changed, 22 not in the overhaul (10 with the same heading under another number), 13 new.

35.006: Not in the overhaul

Today: Contracting methods and contract type.

This section in plain English

(a) In R&D acquisitions, the precise specifications necessary for sealed bidding are generally not available, thus making negotiation necessary. However, the use of negotiation in R&D contracting does not change the obligation to comply with part 6.

(b) Selecting the appropriate contract type is the responsibility of the contracting officer. However, because of the importance of technical considerations in R&D, the choice of contract type should be made after obtaining the recommendations of technical personnel. Although the Government ordinarily prefers fixed-price arrangements in contracting, this preference applies in R&D contracting only to the extent that goals, objectives, specifications, and cost estimates are sufficient to permit such a preference. The precision with which the goals, performance objectives, and specifications for the work can be defined will largely determine the type of contract employed. The contract type must be selected to fit the work required.

(c) Because the absence of precise specifications and difficulties in estimating costs with accuracy (resulting in a lack of confidence in cost estimates) normally precludes using fixed-price contracting for R&D, the use of cost-reimbursement contracts is usually appropriate (see subpart 16.3). The nature of development work often requires a cost-reimbursement completion arrangement (see 16.306(d)). When the use of cost and performance incentives is desirable and practicable, fixed-price incentive and cost-plus-incentive-fee contracts should be considered in that order of preference.

(d) When levels of effort can be specified in advance, a short-duration fixed-price contract may be useful for developing system design concepts, resolving potential problems, and reducing Government risks. Fixed-price contracting may also be used in minor projects when the objectives of the research are well defined and there is sufficient confidence in the cost estimate for price negotiations. (See 16.207.)

(e) Projects having production requirements as a follow-on to R&D efforts normally should progress from cost-reimbursement contracts to fixed-price contracts as designs become more firmly established, risks are reduced, and production tooling, equipment, and processes are developed and proven. When possible, a final commitment to undertake specific product development and testing should be avoided until (1) preliminary exploration and studies have indicated a high degree of probability that development is feasible and (2) the Government has determined both its minimum requirements and desired objectives for product performance and schedule completion.

Overhaul text

No section with this number.

Section by section

SectionTodayOverhaul textStatusWords
35.000Scope of part.Scope of part.Changed · 85% alike42 → 40
35.001Definitions.Definitions.Changed · 86% alike209 → 175
35.002General.Policy.Changed · 8% alike124 → 84
35.003Policy.noneNot in the overhaul98 → –
35.004Publicizing requirements and expanding research and development sources.noneNot in the overhaul121 → –
35.005Work statement.noneNot in the overhaul402 → –
35.006Contracting methods and contract type.noneNot in the overhaul396 → –
35.007Solicitations.noneNot in the overhaul
Same heading at 35.101
679 → –
35.008Evaluation for award.noneNot in the overhaul
Same heading at 35.201
202 → –
35.009Subcontracting research and development effort.noneNot in the overhaul127 → –
35.010Scientific and technical reports.noneNot in the overhaul
Same heading at 35.301
116 → –
35.011Data.noneNot in the overhaul94 → –
35.012Patent rights.noneNot in the overhaul12 → –
35.013Insurance.noneNot in the overhaul49 → –
35.014Government property and title.noneNot in the overhaul470 → –
35.015Contracts for research with educational institutions and nonprofit organizations.noneNot in the overhaul309 → –
35.016Broad agency announcement.noneNot in the overhaul
Same heading at 35.102
358 → –
35.017Federally Funded Research and Development Centers.noneNot in the overhaul448 → –
35.017-1Sponsoring agreements.noneNot in the overhaul
Same heading at 35.403
473 → –
35.017-2Establishing or changing an FFRDC.noneNot in the overhaul
Same heading at 35.404
242 → –
35.017-3Using an FFRDC.noneNot in the overhaul
Same heading at 35.405
127 → –
35.017-4Reviewing FFRDC's.noneNot in the overhaul
Same heading at 35.407
248 → –
35.017-5Terminating FFRDC.noneNot in the overhaul40 → –
35.017-6Master list of FFRDC's.noneNot in the overhaul
Same heading at 35.409
44 → –
35.017-7Limitation on the creation of new FFRDC's.noneNot in the overhaul
Same heading at 35.406
116 → –
35.101noneSolicitations.New number
Same heading as today's 35.007
– → 626
35.102noneBroad agency announcement.New number
Same heading as today's 35.016
– → 292
35.201noneEvaluation for award.New number
Same heading as today's 35.008
– → 109
35.301noneScientific and technical reports.New number
Same heading as today's 35.010
– → 87
35.401noneDefinitions.New number– → 107
35.402nonePolicy.New number– → 275
35.403noneSponsoring agreements.New number
Same heading as today's 35.017-1
– → 311
35.404noneEstablishing or changing an FFRDC.New number
Same heading as today's 35.017-2
– → 224
35.405noneUsing an FFRDC.New number
Same heading as today's 35.017-3
– → 97
35.406noneLimitation on the creation of new FFRDC’s.New number
Same heading as today's 35.017-7
– → 112
35.407noneReviewing FFRDC’s.New number
Same heading as today's 35.017-4
– → 207
35.408noneTerminating an FFRDC.New number– → 37
35.409noneMaster list of FFRDC’s.New number
Same heading as today's 35.017-6
– → 43