The FAR overhaul, side by side
FAR Part 35: Research and Development Contracting
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 25 sections, 5,546 words (Part 35 as in force, eCFR as of Oct 29, 2026). Overhaul text: 16 sections, 2,826 words (on acquisition.gov ↗, issued Jul 24, 2025). By number: 0 the same, 3 changed, 22 not in the overhaul (10 with the same heading under another number), 13 new.
35.014: Not in the overhaul
Today: Government property and title.
(a) The requirements in part 45 for establishing and maintaining control over Government property apply to all R&D contracts.
(b) In implementing 31 U.S.C. 6306, and unless an agency head provides otherwise, the policies in subparagraphs (1) through (4) following, regarding title to equipment (and other tangible personal property) purchased by the contractor using Government funds provided for the conduct of basic or applied scientific research, apply to contracts with nonprofit institutions of higher education and nonprofit organizations whose primary purpose is the conduct of scientific research:
(1) If the contractor obtains the contracting officer's advance approval, the contractor shall automatically acquire and retain title to any item of equipment costing less than $5,000 (or a lesser amount established by agency regulations) acquired on a reimbursable basis.
(2) If purchased equipment costs $5,000 (or a lesser amount established by agency regulations) or more, and as the parties specifically agree in the contract, title may—
(i) Vest in the contractor upon acquisition without further obligation to the Government;
(ii) Vest in the contractor, subject to the Government's right to direct transfer of the title to the Government or to a third party within 12 months after the contract's completion or termination (transfer of title to the Government or third party shall not be the basis for any claim by the contractor); or
(iii) Vest in the Government, if the contracting officer determines that vesting of title in the contractor would not further the objectives of the agency's research program.
(3) If title to equipment is vested in the contractor, depreciation, amortization, or use charges are not allowable with respect to that equipment under any existing or future Government contract or subcontract.
(4) If the contract is performed at a Government installation and there is a continuing need for the equipment following contract completion, title need not be transferred to the contractor.
(c) The absence of an agreement covering title to equipment acquired by the contractor with Government funds that cost $1,000 or more does not limit an agency's right to act to vest title in a contractor as authorized by 31 U.S.C. 6306.
(d)(1) Vesting title under paragraph (b) above is subject to civil rights legislation, 42 U.S.C. 2000d. Before title is vested, the contractor must agree that—
“No person in the United States or its outlying areas shall, on the ground of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under this contemplated financial assistance (title to equipment).”
(2) By signing the contract, the contractor accepts and agrees to comply with this requirement.
(e) The policies in paragraphs (b)(1) through (b)(3) and paragraph (d) of this section are implemented in the Government Property clauses.
Overhaul text
No section with this number.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 35.000 | Scope of part. | Scope of part. | Changed · 85% alike | 42 → 40 |
| 35.001 | Definitions. | Definitions. | Changed · 86% alike | 209 → 175 |
| 35.002 | General. | Policy. | Changed · 8% alike | 124 → 84 |
| 35.003 | Policy. | none | Not in the overhaul | 98 → – |
| 35.004 | Publicizing requirements and expanding research and development sources. | none | Not in the overhaul | 121 → – |
| 35.005 | Work statement. | none | Not in the overhaul | 402 → – |
| 35.006 | Contracting methods and contract type. | none | Not in the overhaul | 396 → – |
| 35.007 | Solicitations. | none | Not in the overhaul Same heading at 35.101 | 679 → – |
| 35.008 | Evaluation for award. | none | Not in the overhaul Same heading at 35.201 | 202 → – |
| 35.009 | Subcontracting research and development effort. | none | Not in the overhaul | 127 → – |
| 35.010 | Scientific and technical reports. | none | Not in the overhaul Same heading at 35.301 | 116 → – |
| 35.011 | Data. | none | Not in the overhaul | 94 → – |
| 35.012 | Patent rights. | none | Not in the overhaul | 12 → – |
| 35.013 | Insurance. | none | Not in the overhaul | 49 → – |
| 35.014 | Government property and title. | none | Not in the overhaul | 470 → – |
| 35.015 | Contracts for research with educational institutions and nonprofit organizations. | none | Not in the overhaul | 309 → – |
| 35.016 | Broad agency announcement. | none | Not in the overhaul Same heading at 35.102 | 358 → – |
| 35.017 | Federally Funded Research and Development Centers. | none | Not in the overhaul | 448 → – |
| 35.017-1 | Sponsoring agreements. | none | Not in the overhaul Same heading at 35.403 | 473 → – |
| 35.017-2 | Establishing or changing an FFRDC. | none | Not in the overhaul Same heading at 35.404 | 242 → – |
| 35.017-3 | Using an FFRDC. | none | Not in the overhaul Same heading at 35.405 | 127 → – |
| 35.017-4 | Reviewing FFRDC's. | none | Not in the overhaul Same heading at 35.407 | 248 → – |
| 35.017-5 | Terminating FFRDC. | none | Not in the overhaul | 40 → – |
| 35.017-6 | Master list of FFRDC's. | none | Not in the overhaul Same heading at 35.409 | 44 → – |
| 35.017-7 | Limitation on the creation of new FFRDC's. | none | Not in the overhaul Same heading at 35.406 | 116 → – |
| 35.101 | none | Solicitations. | New number Same heading as today's 35.007 | – → 626 |
| 35.102 | none | Broad agency announcement. | New number Same heading as today's 35.016 | – → 292 |
| 35.201 | none | Evaluation for award. | New number Same heading as today's 35.008 | – → 109 |
| 35.301 | none | Scientific and technical reports. | New number Same heading as today's 35.010 | – → 87 |
| 35.401 | none | Definitions. | New number | – → 107 |
| 35.402 | none | Policy. | New number | – → 275 |
| 35.403 | none | Sponsoring agreements. | New number Same heading as today's 35.017-1 | – → 311 |
| 35.404 | none | Establishing or changing an FFRDC. | New number Same heading as today's 35.017-2 | – → 224 |
| 35.405 | none | Using an FFRDC. | New number Same heading as today's 35.017-3 | – → 97 |
| 35.406 | none | Limitation on the creation of new FFRDC’s. | New number Same heading as today's 35.017-7 | – → 112 |
| 35.407 | none | Reviewing FFRDC’s. | New number Same heading as today's 35.017-4 | – → 207 |
| 35.408 | none | Terminating an FFRDC. | New number | – → 37 |
| 35.409 | none | Master list of FFRDC’s. | New number Same heading as today's 35.017-6 | – → 43 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress