The FAR overhaul, side by side

FAR Part 41: Acquisition of Utility Services

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 17 sections, 4,921 words (Part 41 as in force, eCFR as of Oct 29, 2026). Overhaul text: 17 sections, 4,557 words (on acquisition.gov ↗, issued Sep 25, 2025). By number: 0 the same, 17 changed, 0 not in the overhaul, 0 new.

41.402: Changed (96% alike)

Today: Rate changes and regulatory intervention.

This section in plain English

(a) When a change is proposed to rates or terms and conditions of service to the Government, the agency shall promptly determine whether the proposed change is reasonable, justified, and not discriminatory.

(b) If a change is proposed to rates or terms and conditions of service that may be of interest to other Federal agencies, and intervention before a regulatory body is considered justified, the matter shall be referred to GSA. The agency may request from GSA a delegation of authority for the agency to intervene on behalf of the consumer interests of the Federal executive agencies (see 41.301).

(c) Pursuant to 52.241-7, Change in Rates or Terms and Conditions of Service for Regulated Services, if a regulatory body approves a rate change, any rate change shall be made a part of the contract by unilateral contract modification or otherwise documented in accordance with agency procedures. The approved applicable rate shall be effective on the date determined by the regulatory body and resulting rates and charges shall be paid promptly to avoid late payment provisions. Copies of the modification containing the approved rate change shall be sent to the agency's paying office or office responsible for verifying billed amounts (see 41.401).

(d) If the utility supplier is not regulated and the rates, terms, and conditions of service are subject to negotiation pursuant to the clause at 52.241-8, Change in Rates or Terms and Conditions of Service for Unregulated Services, any rate change shall be made a part of the contract by contract modification, with copies sent to the agency's paying office or office responsible for verifying billed amounts.

Overhaul text: Rate changes and regulatory intervention.

On acquisition.gov ↗

(a) When a change is proposed to rates or terms and conditions of service to the Government, the agency must promptly determine whether the proposed change is reasonable, justified, and not discriminatory.

(b) If a change is proposed to rates or terms and conditions of service that may be of interest to other Federal agencies, and intervention before a regulatory body is considered justified, the matter must be referred to GSA. The agency may request from GSA a delegation of authority for the agency to intervene on behalf of the consumer interests of the Federal executive agencies.

(c) Pursuant to 52.241-7, Change in Rates or Terms and Conditions of Service for Regulated Services, if a regulatory body approves a rate change, any rate change must be made a part of the contract by unilateral contract modification or otherwise documented in accordance with agency procedures. The approved applicable rate must be effective on the date determined by the regulatory body and resulting rates and charges must be paid promptly to avoid late payment provisions. Copies of the modification containing the approved rate change must be sent to the agency's paying office or office responsible for verifying billed amounts.

(d) If the utility supplier is not regulated and the rates, terms, and conditions of service are subject to negotiation pursuant to the clause at 52.241-8, Change in Rates or Terms and Conditions of Service for Unregulated Services, any rate change must be made a part of the contract by contract modification, with copies sent to the agency's paying office or office responsible for verifying billed amounts.

Section by section

SectionTodayOverhaul textStatusWords
41.100Scope of part.Scope of part.Changed · 72% alike25 → 14
41.101Definitions.Definitions.Changed · 79% alike418 → 417
41.102Applicability.Applicability.Changed · 79% alike193 → 130
41.103Statutory and delegated authority.Statutory and delegated authority.Changed · 98% alike326 → 322
41.201Policy.Policy.Changed · 94% alike599 → 545
41.202Procedures.Procedures.Changed · 91% alike569 → 507
41.203GSA assistance.GSA assistance.Changed · 99% alike73 → 73
41.204GSA areawide contracts.GSA areawide contracts.Changed · 89% alike540 → 473
41.205Separate contracts.Separate contracts.Changed · 94% alike250 → 235
41.206Interagency agreements.Interagency agreements.Changed · 71% alike38 → 24
41.301Requirements.Requirements.Changed · 94% alike677 → 637
41.401Monthly and annual review.Monthly and annual review.Changed · 97% alike149 → 149
41.402Rate changes and regulatory intervention.Rate changes and regulatory intervention.Changed · 96% alike274 → 268
41.501Solicitation provision and contract clauses.Solicitation provision and contract clauses.Changed · 98% alike552 → 529
41.601Utility services forms.Utility services forms.Changed · 96% alike56 → 56
41.701Formats for utility service specifications.Formats for utility service specifications.Changed · 96% alike121 → 119
41.702Formats for annual utility service review.Formats for annual utility service review.Changed · 93% alike61 → 59