The FAR overhaul, side by side
FAR Part 41: Acquisition of Utility Services
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 17 sections, 4,921 words (Part 41 as in force, eCFR as of Oct 29, 2026). Overhaul text: 17 sections, 4,557 words (on acquisition.gov ↗, issued Sep 25, 2025). By number: 0 the same, 17 changed, 0 not in the overhaul, 0 new.
41.202: Changed (91% alike)
Today: Procedures.
(a) Prior to executing a utility service contract, the contracting officer shall comply with parts 6 and 7 and 41.201 (d) and (e). In accordance with parts 6 and 7, agencies shall conduct market surveys and perform acquisition planning in order to promote and provide for full and open competition provided that the contracting officer determines that any resultant contract would not be inconsistent with applicable state law governing the provision of electric utility services. If competition for an entire utility service is not available, the market survey may be used to determine the availability of competitive sources for certain portions of the requirement. The scope of the term “entire utility service” includes the provision of the utility service capacity, energy, water, sewage, transportation, standby or back-up service, transmission and/or distribution service, quality assurance, system reliability, system operation and maintenance, metering, and billing.
(b) In performing a market survey (see 7.101), the contracting officer shall consider, in addition to alternative competitive sources, use of the following:
(1) GSA areawide contracts (see 41.204);
(2) Separate contracts (see 41.205); and
(3) Interagency agreements (see 41.206).
(c) When a utility supplier refuses to execute a tendered contract as outlined in 41.201(b), the agency shall obtain a written definite and final refusal signed by a corporate officer or other responsible official of the supplier (or if unobtainable, document any unwritten refusal), and transmit this document, along with statements of the reasons for the refusal and the record of negotiations, to GSA at the address specified at 41.301(a). Unless urgent and compelling circumstances exist, the contracting officer shall notify GSA prior to acquiring utility services without executing a tendered contract. After such notification, the agency may proceed with the acquisition and pay for the utility service under the provisions of 31 U.S.C. 1501(a)(8)—
(1) By issuing a purchase order in accordance with 13.302; or
(2) By ordering the necessary utility service and paying for it upon the presentation of an invoice, provided that a determination is approved by the head of the contracting activity that a written contract cannot be obtained and that the issuance of a purchase order is not feasible.
(d) When obtaining service without a bilateral written contract, the contracting officer shall establish a utility history file on each acquisition of utility service provided by a contractor. This utility history file shall contain, in addition to applicable documents in 4.803, the following information:
(1) The unsigned, tendered contract and any related letter of transmittal.
(2) The reasons stated by the utility supplier for not executing the tendered contract, the record of negotiations, and a written definite and final refusal by a corporate officer or other responsible official of the supplier (or if unobtainable, documentation of unwritten refusal).
(3) Services to be furnished and the estimated annual cost.
(4) Historical record of any applicable connection charges.
(5) Historical record of any applicable ongoing capital credits.
(6) A copy of the applicable rate schedule.
(e) If the Government obtains utility service pursuant to paragraph (c) of this section, the contracting officer shall, on an annual basis beginning from the date of final refusal, take action to execute a bilateral written contract. The contracting officer shall document the utility history file with the efforts made and the agency shall notify GSA, in writing, if the utility continues to refuse to execute a bilateral contract.
Overhaul text: Procedures.
(a) Agencies must conduct market surveys and perform acquisition planning in order to promote and provide for full and open competition provided that the contracting officer determines that any resultant contract would not be inconsistent with applicable state law governing the provision of electric utility services. If competition for an entire utility service is not available, the market survey may be used to determine the availability of competitive sources for certain portions of the requirement. The scope of the term “entire utility service” includes the provision of the utility service capacity, energy, water, sewage, transportation, standby or back-up service, transmission and/or distribution service, quality assurance, system reliability, system operation and maintenance, metering, and billing.
(b) In performing a market survey, the contracting officer must consider, in addition to alternative competitive sources, use of the following:
(1) GSA areawide contracts;
(2) Separate contracts; and
(3) Interagency agreements.
(c) When a utility supplier refuses to execute a tendered contract, the agency must obtain a written definite and final refusal signed by a corporate officer or other responsible official of the supplier (or if unobtainable, document any unwritten refusal), and transmit this document, along with statements of the reasons for the refusal and the record of negotiations, to GSA at [email protected] . Unless urgent and compelling circumstances exist, the contracting officer must notify GSA prior to acquiring utility services without executing a tendered contract. After such notification, the agency may proceed with the acquisition and pay for the utility service under the provisions of31 U.S.C. 1501(a)(8)—
(1) By issuing a purchase order; or
(2) By ordering the necessary utility service and paying for it upon the presentation of an invoice, provided that a determination is approved by the head of the contracting activity that a written contract cannot be obtained and that the issuance of a purchase order is not feasible.
(d) When obtaining service without a bilateral written contract, the contracting officer must establish a utility history file on each acquisition of utility service provided by a contractor. This utility history file must contain the following information:
(1) The unsigned, tendered contract and any related letter of transmittal.
(2) The reasons stated by the utility supplier for not executing the tendered contract, the record of negotiations, and a written definite and final refusal by a corporate officer or other responsible official of the supplier (or if unobtainable, documentation of unwritten refusal).
(3) Services to be furnished and the estimated annual cost.
(4) Historical record of any applicable connection charges.
(5) Historical record of any applicable ongoing capital credits.
(6) A copy of the applicable rate schedule.
(e) If the Government obtains utility service pursuant toparagraph (c) of this section, on an annual basis beginning from the date of final refusal, take action to execute a bilateral written contract. The contracting officer must document the utility history file with the efforts made and the agency must notify GSA, in writing at [email protected] , if the utility continues to refuse to execute a bilateral contract.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 41.100 | Scope of part. | Scope of part. | Changed · 72% alike | 25 → 14 |
| 41.101 | Definitions. | Definitions. | Changed · 79% alike | 418 → 417 |
| 41.102 | Applicability. | Applicability. | Changed · 79% alike | 193 → 130 |
| 41.103 | Statutory and delegated authority. | Statutory and delegated authority. | Changed · 98% alike | 326 → 322 |
| 41.201 | Policy. | Policy. | Changed · 94% alike | 599 → 545 |
| 41.202 | Procedures. | Procedures. | Changed · 91% alike | 569 → 507 |
| 41.203 | GSA assistance. | GSA assistance. | Changed · 99% alike | 73 → 73 |
| 41.204 | GSA areawide contracts. | GSA areawide contracts. | Changed · 89% alike | 540 → 473 |
| 41.205 | Separate contracts. | Separate contracts. | Changed · 94% alike | 250 → 235 |
| 41.206 | Interagency agreements. | Interagency agreements. | Changed · 71% alike | 38 → 24 |
| 41.301 | Requirements. | Requirements. | Changed · 94% alike | 677 → 637 |
| 41.401 | Monthly and annual review. | Monthly and annual review. | Changed · 97% alike | 149 → 149 |
| 41.402 | Rate changes and regulatory intervention. | Rate changes and regulatory intervention. | Changed · 96% alike | 274 → 268 |
| 41.501 | Solicitation provision and contract clauses. | Solicitation provision and contract clauses. | Changed · 98% alike | 552 → 529 |
| 41.601 | Utility services forms. | Utility services forms. | Changed · 96% alike | 56 → 56 |
| 41.701 | Formats for utility service specifications. | Formats for utility service specifications. | Changed · 96% alike | 121 → 119 |
| 41.702 | Formats for annual utility service review. | Formats for annual utility service review. | Changed · 93% alike | 61 → 59 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress