The FAR overhaul, side by side

FAR Part 43: Contract Modifications

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 14 sections, 2,489 words (Part 43 as in force, eCFR as of Oct 29, 2026). Overhaul text: 13 sections, 2,141 words (on acquisition.gov ↗, issued Jun 12, 2025). By number: 0 the same, 7 changed, 7 not in the overhaul (1 with the same heading under another number), 6 new.

43.204: Changed (7% alike)

Today: Administration.

This section in plain English

(a) Change order documentation. When change orders are not forward priced, they require two documents: the change order and a supplemental agreement reflecting the resulting equitable adjustment in contract terms. If an equitable adjustment in the contract price or delivery terms or both can be agreed upon in advance, only a supplemental agreement need be issued, but administrative changes and changes issued pursuant to a clause giving the Government a unilateral right to make a change (e.g., an option clause) initially require only one document.

(b) Definitization. (1)(i) Contracting officers shall negotiate equitable adjustments resulting from change orders in the shortest practicable time.

(ii) Agencies shall, in accordance with agency procedures, record and maintain data regarding the time required to definitize equitable adjustments associated with change orders for construction. The definitization of an equitable adjustment begins upon receipt of an adequate change order definitization proposal by the contracting officer, and ends upon the contracting officer's execution of a contractual action to definitize the change order. The contracting officer shall ensure the data is recorded promptly in accordance with agency procedures. See 36.211(b).

(2) Administrative contracting officers negotiating equitable adjustments by delegation under 42.302(b)(1), shall obtain the contracting officer's concurrence before adjusting the contract delivery schedule.

(3) Contracting offices and contract administration offices, as appropriate, shall establish suspense systems adequate to ensure accurate identification and prompt definitization of unpriced change orders.

(4) The contracting officer shall ensure that a cost analysis is made, if appropriate, under 15.404-1(c) and shall consider the contractor's segregable costs of the change, if available. If additional funds are required as a result of the change, the contracting officer shall secure the funds before making any adjustment to the contract.

(5) When the contracting officer requires a field pricing review of requests for equitable adjustment, the contracting officer shall provide a list of any significant contract events which may aid in the analysis of the request. This list should include—

(i) Date and dollar amount of contract award and/or modification;

(ii) Date of submission of initial contract proposal and dollar amount;

(iii) Date of alleged delays or disruptions;

(iv) Performance dates as scheduled at date of award and/or modification;

(v) Actual performance dates;

(vi) Date entitlement to an equitable adjustment was determined or contracting officer decision was rendered, if applicable;

(vii) Date of certification of the request for adjustment if certification is required; and

(viii) Dates of any pertinent Government actions or other key events during contract performance which may have an impact on the contractor's request for equitable adjustment.

(c) Complete and final equitable adjustments. To avoid subsequent controversies that may result from a supplemental agreement containing an equitable adjustment as the result of a change order, the contracting officer should—

(1) Ensure that all elements of the equitable adjustment have been presented and resolved; and

(2) Include, in the supplemental agreement, a release similar to the following:

CONTRACTOR'S STATEMENT OF RELEASE

In consideration of the modification(s) agreed to herein as complete equitable adjustments for the Contractor's ________________ (describe) __________________ “proposal(s) for adjustment,” the Contractor hereby releases the Government from any and all liability under this contract for further equitable adjustments attributable to such facts or circumstances giving rise to the “proposal(s) for adjustment” (except for ____________________ ).

Overhaul text: Notification of contract changes.

On acquisition.gov ↗

When a contractor determines that the Government has made or may make a change in the contract that is not in writing and is not signed by the contracting officer, the contractor shall notify the Government in writing as soon as possible. This will permit the Government to evaluate the alleged change and—

(a) Confirm that it is a change, direct the mode of further performance, and plan for its funding;

(b) Countermand the alleged change; or

(c) Notify the contractor that no change is considered to have occurred.

Section by section

SectionTodayOverhaul textStatusWords
43.000Scope of part.43.100 Scope of part.Changed · 49% alike61 → 46
43.101Definitions.noneNot in the overhaul197 → –
43.102Policy.noneNot in the overhaul130 → –
43.103Types of contract modifications.noneNot in the overhaul121 → –
43.104Notification of contract changes.noneNot in the overhaul156 → –
43.105Availability of funds.noneNot in the overhaul173 → –
43.106[Reserved]noneNot in the overhaul0 → –
43.107Contract clause.noneNot in the overhaul
Same heading at 43.206
103 → –
43.201General.Definitions.Changed · 14% alike146 → 194
43.202Authority to issue change orders.Policy.Changed · 4% alike23 → 128
43.203Change order accounting procedures.Types of contract modifications.Changed · 12% alike122 → 121
43.204Administration.Notification of contract changes.Changed · 7% alike557 → 89
43.205Contract clauses.Availability of funds.Changed · 5% alike484 → 175
43.206noneContract clause.New number
Same heading as today's 43.107
– → 98
43.301Use of forms.General.Changed · 17% alike216 → 152
43.302noneAuthority to issue change orders.New number– → 23
43.303noneChange order accounting procedures.New number– → 72
43.304noneAdministration.New number– → 350
43.305noneContract clauses.New number– → 484
43.401noneUse of forms.New number– → 209