The FAR overhaul, side by side
FAR Part 43: Contract Modifications
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 14 sections, 2,489 words (Part 43 as in force, eCFR as of Oct 29, 2026). Overhaul text: 13 sections, 2,141 words (on acquisition.gov ↗, issued Jun 12, 2025). By number: 0 the same, 7 changed, 7 not in the overhaul (1 with the same heading under another number), 6 new.
43.204: Changed (7% alike)
Today: Administration.
(a) Change order documentation. When change orders are not forward priced, they require two documents: the change order and a supplemental agreement reflecting the resulting equitable adjustment in contract terms. If an equitable adjustment in the contract price or delivery terms or both can be agreed upon in advance, only a supplemental agreement need be issued, but administrative changes and changes issued pursuant to a clause giving the Government a unilateral right to make a change (e.g., an option clause) initially require only one document.
(b) Definitization. (1)(i) Contracting officers shall negotiate equitable adjustments resulting from change orders in the shortest practicable time.
(ii) Agencies shall, in accordance with agency procedures, record and maintain data regarding the time required to definitize equitable adjustments associated with change orders for construction. The definitization of an equitable adjustment begins upon receipt of an adequate change order definitization proposal by the contracting officer, and ends upon the contracting officer's execution of a contractual action to definitize the change order. The contracting officer shall ensure the data is recorded promptly in accordance with agency procedures. See 36.211(b).
(2) Administrative contracting officers negotiating equitable adjustments by delegation under 42.302(b)(1), shall obtain the contracting officer's concurrence before adjusting the contract delivery schedule.
(3) Contracting offices and contract administration offices, as appropriate, shall establish suspense systems adequate to ensure accurate identification and prompt definitization of unpriced change orders.
(4) The contracting officer shall ensure that a cost analysis is made, if appropriate, under 15.404-1(c) and shall consider the contractor's segregable costs of the change, if available. If additional funds are required as a result of the change, the contracting officer shall secure the funds before making any adjustment to the contract.
(5) When the contracting officer requires a field pricing review of requests for equitable adjustment, the contracting officer shall provide a list of any significant contract events which may aid in the analysis of the request. This list should include—
(i) Date and dollar amount of contract award and/or modification;
(ii) Date of submission of initial contract proposal and dollar amount;
(iii) Date of alleged delays or disruptions;
(iv) Performance dates as scheduled at date of award and/or modification;
(v) Actual performance dates;
(vi) Date entitlement to an equitable adjustment was determined or contracting officer decision was rendered, if applicable;
(vii) Date of certification of the request for adjustment if certification is required; and
(viii) Dates of any pertinent Government actions or other key events during contract performance which may have an impact on the contractor's request for equitable adjustment.
(c) Complete and final equitable adjustments. To avoid subsequent controversies that may result from a supplemental agreement containing an equitable adjustment as the result of a change order, the contracting officer should—
(1) Ensure that all elements of the equitable adjustment have been presented and resolved; and
(2) Include, in the supplemental agreement, a release similar to the following:
CONTRACTOR'S STATEMENT OF RELEASE
In consideration of the modification(s) agreed to herein as complete equitable adjustments for the Contractor's ________________ (describe) __________________ “proposal(s) for adjustment,” the Contractor hereby releases the Government from any and all liability under this contract for further equitable adjustments attributable to such facts or circumstances giving rise to the “proposal(s) for adjustment” (except for ____________________ ).
Overhaul text: Notification of contract changes.
When a contractor determines that the Government has made or may make a change in the contract that is not in writing and is not signed by the contracting officer, the contractor shall notify the Government in writing as soon as possible. This will permit the Government to evaluate the alleged change and—
(a) Confirm that it is a change, direct the mode of further performance, and plan for its funding;
(b) Countermand the alleged change; or
(c) Notify the contractor that no change is considered to have occurred.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 43.000 | Scope of part. | 43.100 Scope of part. | Changed · 49% alike | 61 → 46 |
| 43.101 | Definitions. | none | Not in the overhaul | 197 → – |
| 43.102 | Policy. | none | Not in the overhaul | 130 → – |
| 43.103 | Types of contract modifications. | none | Not in the overhaul | 121 → – |
| 43.104 | Notification of contract changes. | none | Not in the overhaul | 156 → – |
| 43.105 | Availability of funds. | none | Not in the overhaul | 173 → – |
| 43.106 | [Reserved] | none | Not in the overhaul | 0 → – |
| 43.107 | Contract clause. | none | Not in the overhaul Same heading at 43.206 | 103 → – |
| 43.201 | General. | Definitions. | Changed · 14% alike | 146 → 194 |
| 43.202 | Authority to issue change orders. | Policy. | Changed · 4% alike | 23 → 128 |
| 43.203 | Change order accounting procedures. | Types of contract modifications. | Changed · 12% alike | 122 → 121 |
| 43.204 | Administration. | Notification of contract changes. | Changed · 7% alike | 557 → 89 |
| 43.205 | Contract clauses. | Availability of funds. | Changed · 5% alike | 484 → 175 |
| 43.206 | none | Contract clause. | New number Same heading as today's 43.107 | – → 98 |
| 43.301 | Use of forms. | General. | Changed · 17% alike | 216 → 152 |
| 43.302 | none | Authority to issue change orders. | New number | – → 23 |
| 43.303 | none | Change order accounting procedures. | New number | – → 72 |
| 43.304 | none | Administration. | New number | – → 350 |
| 43.305 | none | Contract clauses. | New number | – → 484 |
| 43.401 | none | Use of forms. | New number | – → 209 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress