FAR and DFARS › FAR Part 43

FAR Part 43: Contract Modifications

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

In plain English

FAR Part 43 sets the rules for changing an existing government contract after award, including who may authorize changes, the types of modifications (bilateral supplemental agreements versus unilateral change orders and administrative changes), notice duties when a contractor thinks a change has occurred, funding certification, and the standard forms used. It matters to a contractor because every change to price, scope, or schedule must go through these channels, and unauthorized or unwritten changes may not be paid for.

Key rules

  • Only a contracting officer acting within the scope of their authority may execute contract modifications on the Government's behalf. (43.102)
  • Modifications should be priced before execution if this can be done without adversely affecting the Government; if time is short and a significant cost increase is possible, at least a ceiling price should be negotiated unless impractical. (43.102)
  • Modifications are either bilateral (signed by both parties, such as supplemental agreements) or unilateral (signed only by the contracting officer, such as change orders and administrative changes). (43.103)
  • If a contractor believes the Government has changed the contract without a signed written change, the contractor must notify the Government in writing as soon as possible. (43.104)
  • A contracting officer may not execute a modification that increases funds without first obtaining a certification of fund availability, subject to listed exceptions. (43.105)
  • The contractor must continue performance as changed, except that in cost-reimbursement or incrementally funded contracts it need not continue beyond the limits set by the Limitation of Cost or Limitation of Funds clause. (43.201)
  • Changes are generally issued as written change orders on Standard Form 30 (SF 30), and change order accounting requires the contractor to segregate costs of changed work under the Change Order Accounting clause. (43.201, 43.203, 43.301)

Who does what

Contracting officers
  • Issue change orders and supplemental agreements and negotiate equitable adjustments in the shortest practicable time.
  • Obtain fund availability certification before executing modifications that increase funds.
  • Advise prospective contractors of the possible need to revise accounting procedures for cost segregation before offers are submitted.
Contractors
  • Notify the Government in writing promptly when you believe a change has occurred that was not identified in a signed writing from the contracting officer.
  • Continue performing as changed, subject to the funding limits in cost-reimbursement or incrementally funded contracts.
  • Segregate the costs of changed work so they can be accounted for under the Change Order Accounting clause.
Agencies
  • Record and maintain data on the time required to definitize equitable adjustments for construction change orders, per agency procedures.
  • Use the prescribed clauses (such as 52.243-1, 52.243-2, and 52.243-7) in solicitations and contracts as applicable.

In practice

  • Do not act on an informal direction from anyone other than the contracting officer; get the change in a signed writing or document your written notice to the Government promptly.
  • When bidding, consider whether your accounting system can separately track the cost of changed work, since change order costs must be segregable.
  • Expect change orders to be followed by a supplemental agreement reflecting the equitable adjustment unless the price and delivery terms were agreed in advance.

Common pitfalls

  • Performing extra work based on a verbal or informal instruction from non-contracting personnel, which the policy says they cannot authorize and which may leave you unpaid.
  • Waiting too long to give written notice of a perceived change, when the regulation calls for notice as soon as possible.
  • Assuming a change order alone settles the price; the equitable adjustment is typically documented in a separate supplemental agreement.

Written by AI from this part's codified text (2026-10-19); cited sections are checked against the part. A guide, not legal advice: the regulation text, the solicitation and your contract rule.

Rule changes for FAR Part 43

Subparts and sections

Subpart 43.1: General

Subpart 43.2: Change Orders

Subpart 43.3: Forms

← Part 42: Contract Administration and Audit ServicesPart 44: Subcontracting Policies and Procedures →

All FAR parts

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗.