The FAR overhaul, side by side
FAR Part 36: Construction and Architect-engineer Contracts
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 81 sections, 9,525 words (Part 36 as in force, eCFR as of Oct 29, 2026). Overhaul text: 26 sections, 4,649 words, titled "Construction and Architect-Engineer Contracts" (on acquisition.gov ↗, issued Jul 24, 2025). By number: 0 the same, 7 changed, 74 not in the overhaul (5 with the same heading under another number), 19 new.
36.301: Changed (7% alike)
Today: Use of two-phase design-build selection procedures.
(a) During formal or informal acquisition planning (see part 7), if considering the use of two-phase design-build selection procedures, the contracting officer shall conduct the evaluation in paragraph (b) of this section.
(b) The two-phase design-build selection procedures shall be used when the contracting officer determines that this method is appropriate, based on the following:
(1) Three or more offers are anticipated.
(2) Design work must be performed by offerors before developing price or cost proposals, and offerors will incur a substantial amount of expense in preparing offers.
(3) The following criteria have been considered:
(i) The extent to which the project requirements have been adequately defined.
(ii) The time constraints for delivery of the project.
(iii) The capability and experience of potential contractors.
(iv) The suitability of the project for use of the two-phase selection method.
(v) The capability of the agency to manage the two-phase selection process.
(vi) Other criteria established by the head of the contracting activity.
Overhaul text: Responsibilities of contracting officers.
See part 42 for performing general contract administration functions. For construction and architect-engineer services there are additional functions including:
(a) Performance and Deliverables.
(1) Contracting officers can, in writing, request the removal of any contractor employee deemed incompetent, careless, or otherwise objectionable (see 52.236-5).
(2) Contracting officers must provide the contractor with a list of work remaining to be performed or corrected for any portions of the work the Government intends to possess or use, prior to taking possession or using said work (see 52.236-11).
(3) Regarding schedules for construction contracts:
(i) The contracting officer may withhold approval of progress payments if the contractor fails to submit the required schedule.
(ii)
(A) The contracting officer must determine whether the work is progressing with sufficient diligence to meet the contract's specified completion time; and
(B) May terminate the contractor's right to proceed with the work, or any separable part of it, per the default terms of the contract if the contractor fails to recover lost time (see 52.236-15).
(b) Modifications.
(1) Upon receiving written notice of differing site conditions, the contracting officer must—
(i) Promptly investigate the site; and
(ii) Negotiate an equitable adjustment if the conditions materially differ, leading to an increase or decrease in the contractor's costs or performance time. Requests for an equitable adjustment will be allowed only if prior written notice is received or if submitted before final payment (see 52.236-2).
(2) If repairs are not made promptly to damaged existing vegetation, structures, equipment, utilities, or improvements; contracting officers may have the necessary work performed and charge the cost to the contractor (see 52.236-9).
(3) If stakes and marks are destroyed by the contractor, the contracting officer may replace them and deduct the cost from due or future payments (see 52.236-17).
(4) Regarding specifications and drawings for construction—
(i) The contracting officer must—
(A) Make a written determination in the case of a discrepancy in the figures, in the drawings, or in the specifications; and
(B) Approve or disapprove shop drawings, with reasons for disapproval if applicable.
(ii) If the contracting officer approves a shop drawing variation from the contract requirements that is minor or does not impact price or performance time, a contract modification will not be issued. For all other approved variations, the contracting officer must issue a contract modification (see 52.236-21).
(5) If a construction contract needs a modification due to architect-engineer design errors, the contracting officer must—
(i) Assess the architect-engineer's liability, with the advice of technical personnel and legal counsel;
(ii) Seek cost recovery if the amount exceeds administrative costs or if it benefits the Government; and
(iii) Include in the contract file a written statement detailing the recovery decision (see 52.236-23).
(c) Compliance and Reporting.
(1) Contracting officers must ensure compliance with the labor standards requirement of the contract (e.g., payroll reviews, on-site inspections, and employee interviews to determine compliance).
(2) Contracting officers should advise contractors to promptly execute and return any required payment and performance bonds to ensure a notice to proceed is issued to commence work in a timely manner (see part 28).
(3) Contracting officers must, if appropriate, give written consent for the contractor to abandon, without removal, temporary buildings and utilities. (see 52.236-10).
(4) If the contracting officer becomes aware of noncompliance with requirements or conditions that endanger public or Government personnel health or safety, the contracting officer—
(i) Must notify the contractor orally, then in writing, requesting immediate corrective action; and
(ii) May issue a stop-work order if the contractor fails to promptly take satisfactory corrective action. (see 52.236-13).
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 36.000 | Scope of part. | Scope of part. | Changed · 49% alike | 37 → 20 |
| 36.001 | Definitions. | Definition. | Changed · 14% alike | 81 → 34 |
| 36.002 | none | Policy. | New number | – → 317 |
| 36.101 | Applicability. | Construction. | Changed · 0% alike | 98 → 0 |
| 36.101-1 | none | Acquisition Strategy. | New number | – → 332 |
| 36.101-2 | none | Use of two-phase design-build selection procedures. | New number | – → 343 |
| 36.101-3 | none | Scope of work. | New number Same heading as today's 36.302 | – → 70 |
| 36.101-4 | none | Advance notices and solicitations. | New number | – → 223 |
| 36.101-5 | none | Liquidated damages. | New number Same heading as today's 36.206 | – → 25 |
| 36.101-6 | none | Government cost estimate. | New number | – → 72 |
| 36.101-7 | none | Clauses. | New number | – → 893 |
| 36.102 | Definitions. | Architect-Engineer Services. | Changed · 0% alike | 213 → 0 |
| 36.102-1 | none | Public announcement. | New number Same heading as today's 36.601-1 | – → 18 |
| 36.102-2 | none | Contracting procedures and competition. | New number | – → 168 |
| 36.102-3 | none | Government cost estimate. | New number | – → 47 |
| 36.102-4 | none | Clauses. | New number | – → 183 |
| 36.103 | Methods of contracting. | none | Not in the overhaul | 62 → – |
| 36.104 | Policy. | none | Not in the overhaul | 425 → – |
| 36.201 | Evaluation of contractor performance. | Construction. | Changed · 0% alike | 14 → 0 |
| 36.201-1 | none | Limitations. | New number | – → 75 |
| 36.201-2 | none | Standard and optional forms. | New number | – → 204 |
| 36.202 | Specifications. | Architect and engineering services. | Changed · 0% alike | 74 → 0 |
| 36.202-1 | none | Evaluation. | New number | – → 241 |
| 36.202-2 | none | Selection authority. | New number Same heading as today's 36.602-4 | – → 168 |
| 36.202-3 | none | Award. | New number | – → 210 |
| 36.202-4 | none | Short selection process for contracts not to exceed the simplified acquisition threshold. | New number Same heading as today's 36.602-5 | – → 218 |
| 36.202-5 | none | Standard and optional forms. | New number | – → 164 |
| 36.203 | Government estimate of construction costs. | none | Not in the overhaul | 185 → – |
| 36.204 | Disclosure of the magnitude of construction projects. | none | Not in the overhaul | 107 → – |
| 36.205 | Statutory cost limitations. | none | Not in the overhaul | 218 → – |
| 36.206 | Liquidated damages. | none | Not in the overhaul Same heading at 36.101-5 | 21 → – |
| 36.207 | Pricing fixed-price construction contracts. | none | Not in the overhaul | 198 → – |
| 36.208 | Concurrent performance of firm-fixed-price and other types of construction contracts. | none | Not in the overhaul | 58 → – |
| 36.209 | Construction contracts with architect-engineer firms. | none | Not in the overhaul | 36 → – |
| 36.210 | Inspection of site and examination of data. | none | Not in the overhaul | 165 → – |
| 36.211 | Distribution of advance notices and solicitations. | none | Not in the overhaul | 343 → – |
| 36.212 | Preconstruction orientation. | none | Not in the overhaul | 135 → – |
| 36.213 | Special procedures for sealed bidding in construction contracting. | none | Not in the overhaul | 0 → – |
| 36.213-1 | General. | none | Not in the overhaul | 22 → – |
| 36.213-2 | Presolicitation notices. | none | Not in the overhaul | 192 → – |
| 36.213-3 | Invitations for bids. | none | Not in the overhaul | 345 → – |
| 36.213-4 | Notice of award. | none | Not in the overhaul | 79 → – |
| 36.214 | Special procedures for price negotiation in construction contracting. | none | Not in the overhaul | 225 → – |
| 36.215 | Special procedures for cost-reimbursement contracts for construction. | none | Not in the overhaul | 36 → – |
| 36.300 | Scope of subpart. | none | Not in the overhaul | 26 → – |
| 36.301 | Use of two-phase design-build selection procedures. | Responsibilities of contracting officers. | Changed · 7% alike | 166 → 624 |
| 36.302 | Scope of work. | none | Not in the overhaul Same heading at 36.101-3 | 60 → – |
| 36.303 | Procedures. | none | Not in the overhaul | 41 → – |
| 36.303-1 | Phase One. | none | Not in the overhaul | 281 → – |
| 36.303-2 | Phase Two. | none | Not in the overhaul | 70 → – |
| 36.500 | Scope of subpart. | none | Not in the overhaul | 60 → – |
| 36.501 | Performance of work by the contractor. | none | Not in the overhaul | 220 → – |
| 36.502 | Differing site conditions. | none | Not in the overhaul | 93 → – |
| 36.503 | Site investigation and conditions affecting the work. | none | Not in the overhaul | 97 → – |
| 36.504 | Physical data. | none | Not in the overhaul | 43 → – |
| 36.505 | Material and workmanship. | none | Not in the overhaul | 20 → – |
| 36.506 | Superintendence by the contractor. | none | Not in the overhaul | 94 → – |
| 36.507 | Permits and responsibilities. | none | Not in the overhaul | 39 → – |
| 36.508 | Other contracts. | none | Not in the overhaul | 92 → – |
| 36.509 | Protection of existing vegetation, structures, equipment, utilities, and improvements. | none | Not in the overhaul | 99 → – |
| 36.510 | Operations and storage areas. | none | Not in the overhaul | 94 → – |
| 36.511 | Use and possession prior to completion. | none | Not in the overhaul | 65 → – |
| 36.512 | Cleaning up. | none | Not in the overhaul | 92 → – |
| 36.513 | Accident prevention. | none | Not in the overhaul | 201 → – |
| 36.514 | Availability and use of utility services. | none | Not in the overhaul | 98 → – |
| 36.515 | Schedules for construction contracts. | none | Not in the overhaul | 104 → – |
| 36.516 | Quantity surveys. | none | Not in the overhaul | 82 → – |
| 36.517 | Layout of work. | none | Not in the overhaul | 47 → – |
| 36.518 | Work oversight in cost-reimbursement construction contracts. | none | Not in the overhaul | 29 → – |
| 36.519 | Organization and direction of the work. | none | Not in the overhaul | 28 → – |
| 36.520 | Contracting by negotiation. | none | Not in the overhaul | 22 → – |
| 36.521 | Specifications and drawings for construction. | none | Not in the overhaul | 135 → – |
| 36.522 | Preconstruction conference. | none | Not in the overhaul | 48 → – |
| 36.523 | Site visit. | none | Not in the overhaul | 54 → – |
| 36.600 | Scope of subpart. | none | Not in the overhaul | 29 → – |
| 36.601 | Policy. | none | Not in the overhaul | 0 → – |
| 36.601-1 | Public announcement. | none | Not in the overhaul Same heading at 36.102-1 | 42 → – |
| 36.601-2 | Competition. | none | Not in the overhaul | 23 → – |
| 36.601-3 | Applicable contracting procedures. | none | Not in the overhaul | 265 → – |
| 36.601-4 | Implementation. | none | Not in the overhaul | 273 → – |
| 36.602 | Selection of firms for architect-engineer contracts. | none | Not in the overhaul | 0 → – |
| 36.602-1 | Selection criteria. | none | Not in the overhaul | 212 → – |
| 36.602-2 | Evaluation boards. | none | Not in the overhaul | 128 → – |
| 36.602-3 | Evaluation board functions. | none | Not in the overhaul | 147 → – |
| 36.602-4 | Selection authority. | none | Not in the overhaul Same heading at 36.202-2 | 193 → – |
| 36.602-5 | Short selection process for contracts not to exceed the simplified acquisition threshold. | none | Not in the overhaul Same heading at 36.202-4 | 213 → – |
| 36.603 | Collecting data on and appraising firms' qualifications. | none | Not in the overhaul | 334 → – |
| 36.604 | Performance evaluation. | none | Not in the overhaul | 15 → – |
| 36.605 | Government cost estimate for architect-engineer work. | none | Not in the overhaul | 149 → – |
| 36.606 | Negotiations. | none | Not in the overhaul | 309 → – |
| 36.607 | Release of information on firm selection. | none | Not in the overhaul | 149 → – |
| 36.608 | Liability for Government costs resulting from design errors or deficiencies. | none | Not in the overhaul | 155 → – |
| 36.609 | Contract clauses. | none | Not in the overhaul | 0 → – |
| 36.609-1 | Design within funding limitations. | none | Not in the overhaul | 359 → – |
| 36.609-2 | Redesign responsibility for design errors or deficiencies. | none | Not in the overhaul | 93 → – |
| 36.609-3 | Work oversight in architect-engineer contracts. | none | Not in the overhaul | 21 → – |
| 36.609-4 | Requirements for registration of designers. | none | Not in the overhaul | 59 → – |
| 36.700 | Scope of subpart. | none | Not in the overhaul | 42 → – |
| 36.701 | Standard and optional forms for use in contracting for construction or dismantling, demolition, or removal of improvements. | none | Not in the overhaul | 202 → – |
| 36.702 | Forms for use in contracting for architect-engineer services. | none | Not in the overhaul | 144 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress