The FAR overhaul, side by side
FAR Part 42: Contract Administration and Audit Services
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 84 sections, 18,724 words (Part 42 as in force, eCFR as of Oct 29, 2026). Overhaul text: 67 sections, 17,612 words (on acquisition.gov ↗, issued Sep 30, 2025, updated Nov 17, 2026). By number: 2 the same, 40 changed, 42 not in the overhaul (19 with the same heading under another number), 25 new.
42.705-3: Not in the overhaul
Today: Educational institutions.
(a) General. (1) Postdetermined final indirect cost rates shall be used in the settlement of indirect costs for all cost-reimbursement contracts with educational institutions, unless predetermined final indirect cost rates are authorized and used (see paragraph (b) below).
(2) The OMB Uniform Guidance at 2 CFR part 200, appendix III assigns each educational institution (defined as an institution of higher education in the OMB Uniform Guidance at 2 CFR part 200, subpart A, and 20 U.S.C. 1001) to a single Government agency for the negotiation of indirect cost rates and provides that those rates shall be accepted by all Federal agencies. Cognizant Government agencies and educational institutions are listed in the Directory of Federal Contract Audit Offices (see 42.103).
(3) The cognizant agency for indirect costs shall establish the billing rates and final indirect cost rates at the educational institution (defined as an institution of higher education in 2 CFR 200, subpart A, and 20 U.S.C. 1001) consistent with the requirements of this subpart, Subpart 31.3, and the OMB Uniform Guidance at 2 CFR part 200, subpart E and appendix III. The agency shall follow the procedures outlined in 42.705-1(b).
(4) If the cognizant agency is unable to reach agreement with an institution, the appeals system of the cognizant agency shall be followed for resolution of the dispute.
(b) Predetermined final indirect cost rates. (1) Under cost-reimbursement research and development contracts with universities, colleges, or other educational institutions (41 U.S.C. 4708), payment for reimbursable indirect costs may be made on the basis of predetermined final indirect cost rates. The cognizant agency is not required to establish predetermined rates, but if they are established, their use must be extended to all the institution's Government contracts.
(2) In deciding whether the use of predetermined rates would be appropriate for the educational institution concerned, the agency should consider both the stability of the institution's indirect costs and bases over a period of years and any anticipated changes in the amount of the direct and indirect costs.
(3) Unless their use is approved at a level in the agency (see subparagraph (a)(2) above) higher than the contracting officer, predetermined rates shall not be used when—
(i) There has been no recent audit of the indirect costs;
(ii) There have been frequent or wide fluctuations in the indirect cost rates and the bases over a period of years; or
(iii) The estimated reimbursable costs for any individual contract are expected to exceed $1 million annually.
(4)(i) If predetermined rates are to be used and no rates have been previously established for the institution's current fiscal year, the agency shall obtain from the institution a proposal for predetermined rates.
(ii) If the proposal is found to be generally acceptable, the agency shall negotiate the predetermined rates with the institution. The rates should be based on an audit of the institution's costs for the year immediately preceding the year in which the rates are being negotiated. If this is not possible, an earlier audit may be used, but appropriate steps should be taken to identify and evaluate significant variations in costs incurred or in bases used that may have a bearing on the reasonableness of the proposed rates. However, in the case of smaller contracts (i.e., contracts that do not exceed the simplified acquisition threshold), an audit made at an earlier date is acceptable if (A) there have been no significant changes in the contractor's organization and (B) it is reasonably apparent that another audit would have little effect on the rates finally agreed upon and the potential for overpayment of indirect cost is relatively insignificant.
(5) If predetermined rates are used—
(i) The contracting officer shall include the negotiated rates and bases in the contract Schedule; and
(ii) See 16.307(g), which prescribes the clause at 52.216-15, Predetermined Indirect Cost Rates.
(6) Predetermined indirect cost rates shall be applicable for a period of not more than four years. The agency shall obtain the contractor's proposal for new predetermined rates sufficiently in advance so that the new rates, based on current data, may be promptly negotiated near the beginning of the new fiscal year or other period agreed to by the parties (see paragraphs (b) and (d) of the clause at 52.216-15, Predetermined Indirect Cost Rates).
(7) Contracting officers shall use billing rates established by the agency to reimburse the contractor for work performed during a period not covered by predetermined rates.
(8) The OMB Uniform Guidance at 2 CFR part 200, subpart E and appendix III, provides additional guidance on how long predetermined rates may be used.
Overhaul text
No section with this number.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 42.000 | Scope of part. | Scope of part. | Same | 16 → 16 |
| 42.001 | [Reserved] | Interagency agreements. | Changed · 0% alike | 0 → 57 |
| 42.002 | Interagency agreements. | Cognizant Federal agency. | Changed · 11% alike | 85 → 117 |
| 42.003 | Cognizant Federal agency. | none | Not in the overhaul | 174 → – |
| 42.101 | Contract audit responsibilities. | Contract audit responsibilities. | Changed · 89% alike | 203 → 178 |
| 42.102 | Assignment of contract audit services. | Assignment of contract audit services. | Changed · 76% alike | 81 → 63 |
| 42.103 | Contract audit services directory. | Contract audit services directory. | Changed · 69% alike | 80 → 68 |
| 42.201 | Contract administration responsibilities. | Contract administration responsibilities. | Changed · 78% alike | 94 → 68 |
| 42.202 | Assignment of contract administration. | Assignment of contract administration. | Changed · 89% alike | 581 → 542 |
| 42.203 | Contract administration services directory. | Contract administration services directory. | Changed · 70% alike | 76 → 52 |
| 42.301 | General. | General. | Changed · 94% alike | 48 → 48 |
| 42.302 | Contract administration functions. | Contract administration functions. | Changed · 91% alike | 2160 → 2091 |
| 42.401 | Contract correspondence. | General. | Changed · 12% alike | 79 → 68 |
| 42.402 | Visits to contractors' facilities. | Assignment and location. | Changed · 4% alike | 287 → 156 |
| 42.403 | Evaluation of contract administration offices. | Responsibilities. | Changed · 8% alike | 35 → 123 |
| 42.500 | Scope of subpart. | Scope of subpart. | Changed · 40% alike | 28 → 17 |
| 42.501 | General. | Definition. | Changed · 4% alike | 185 → 34 |
| 42.502 | Selecting contracts for postaward orientation. | Purpose. | Changed · 4% alike | 176 → 71 |
| 42.503 | Postaward conferences. | General. | Same | 0 → 0 |
| 42.503-1 | Postaward conference arrangements. | Policy. | Changed · 9% alike | 91 → 203 |
| 42.503-2 | Postaward conference procedure. | Certificate of indirect costs. | Changed · 8% alike | 132 → 396 |
| 42.503-3 | Postaward conference report. | none | Not in the overhaul | 66 → – |
| 42.504 | Postaward letters. | Billing rates. | Changed · 8% alike | 58 → 349 |
| 42.505 | Postaward subcontractor conferences. | Final indirect cost rates. | Changed · 10% alike | 127 → 197 |
| 42.505-1 | none | Contracting officer determination procedure. | New number Same heading as today's 42.705-1 | – → 888 |
| 42.505-2 | none | Auditor determination procedure. | New number Same heading as today's 42.705-2 | – → 327 |
| 42.505-3 | none | Educational institutions. | New number Same heading as today's 42.705-3 | – → 643 |
| 42.505-4 | none | State and local governments. | New number Same heading as today's 42.705-4 | – → 74 |
| 42.505-5 | none | Nonprofit organizations other than educational institutions and state and local governments. | New number | – → 49 |
| 42.506 | none | Cost-sharing rates and limitations on indirect cost rates. | New number Same heading as today's 42.707 | – → 184 |
| 42.507 | none | Quick-closeout procedure. | New number Same heading as today's 42.708 | – → 313 |
| 42.508 | none | Penalties for Unallowable Costs. | New number Same heading as today's 42.709 | – → 0 |
| 42.508-1 | none | Scope. | New number | – → 84 |
| 42.508-2 | none | General. | New number | – → 147 |
| 42.508-3 | none | Responsibilities. | New number | – → 107 |
| 42.508-4 | none | Assessing the penalty. | New number Same heading as today's 42.709-4 | – → 234 |
| 42.508-5 | none | Computing Interest. | New number Same heading as today's 42.709-5 | – → 108 |
| 42.508-6 | none | Waiver of the penalty. | New number Same heading as today's 42.709-6 | – → 150 |
| 42.508-7 | none | Contract clause. | New number Same heading as today's 42.709-7 | – → 72 |
| 42.600 | none | Scope of subpart. | New number | – → 26 |
| 42.601 | General. | Notice of intent to disallow costs. | Changed · 5% alike | 74 → 407 |
| 42.602 | Assignment and location. | Contract clause. | Changed · 4% alike | 295 → 39 |
| 42.603 | Responsibilities. | Disallowing costs after incurrence. | Changed · 5% alike | 123 → 220 |
| 42.700 | Scope of subpart. | Scope of subpart. | Changed · 27% alike | 17 → 49 |
| 42.701 | Definition. | General. | Changed · 7% alike | 34 → 24 |
| 42.702 | Purpose. | Procedures. | Changed · 4% alike | 71 → 117 |
| 42.703 | General. | Solicitation provision and contract clause. | Changed · 0% alike | 0 → 21 |
| 42.703-1 | Policy. | none | Not in the overhaul | 234 → – |
| 42.703-2 | Certificate of indirect costs. | none | Not in the overhaul | 406 → – |
| 42.704 | Billing rates. | none | Not in the overhaul | 369 → – |
| 42.705 | Final indirect cost rates. | none | Not in the overhaul | 200 → – |
| 42.705-1 | Contracting officer determination procedure. | none | Not in the overhaul Same heading at 42.505-1 | 846 → – |
| 42.705-2 | Auditor determination procedure. | none | Not in the overhaul Same heading at 42.505-2 | 299 → – |
| 42.705-3 | Educational institutions. | none | Not in the overhaul Same heading at 42.505-3 | 779 → – |
| 42.705-4 | State and local governments. | none | Not in the overhaul Same heading at 42.505-4 | 85 → – |
| 42.705-5 | Nonprofit organizations other than educational and state and local governments. | none | Not in the overhaul | 27 → – |
| 42.706 | Distribution of documents. | none | Not in the overhaul | 81 → – |
| 42.707 | Cost-sharing rates and limitations on indirect cost rates. | none | Not in the overhaul Same heading at 42.506 | 257 → – |
| 42.708 | Quick-closeout procedure. | none | Not in the overhaul Same heading at 42.507 | 330 → – |
| 42.709 | Penalties for Unallowable Costs. | none | Not in the overhaul Same heading at 42.508 | 0 → – |
| 42.709-1 | Scope. | none | Not in the overhaul | 84 → – |
| 42.709-2 | General. | none | Not in the overhaul | 152 → – |
| 42.709-3 | Responsibilities. | none | Not in the overhaul | 146 → – |
| 42.709-4 | Assessing the penalty. | none | Not in the overhaul Same heading at 42.508-4 | 226 → – |
| 42.709-5 | Computing interest. | none | Not in the overhaul Same heading at 42.508-5 | 113 → – |
| 42.709-6 | Waiver of the penalty. | none | Not in the overhaul Same heading at 42.508-6 | 247 → – |
| 42.709-7 | Contract clause. | none | Not in the overhaul Same heading at 42.508-7 | 72 → – |
| 42.800 | Scope of subpart. | none | Not in the overhaul | 26 → – |
| 42.801 | Notice of intent to disallow costs. | General. | Changed · 5% alike | 386 → 47 |
| 42.802 | Contract clause. | Applicability. | Changed · 7% alike | 39 → 15 |
| 42.803 | Disallowing costs after incurrence. | Surveillance requirements. | Changed · 7% alike | 291 → 170 |
| 42.804 | none | Assignment of criticality designator. | New number Same heading as today's 42.1105 | – → 103 |
| 42.805 | none | Contract clause. | New number Same heading as today's 42.709-7 | – → 48 |
| 42.900 | Scope of subpart. | Scope of subpart. | Changed · 24% alike | 54 → 48 |
| 42.901 | General. | Responsibility for executing agreements. | Changed · 5% alike | 29 → 167 |
| 42.902 | Procedures. | Processing agreements. | Changed · 10% alike | 117 → 508 |
| 42.903 | Solicitation provision and contract clause. | Applicability of novation agreements. | Changed · 1% alike | 21 → 1986 |
| 42.904 | none | Agreement to recognize contractor’s change of name. | New number Same heading as today's 42.1205 | – → 555 |
| 42.1001 | none | General. | New number | – → 22 |
| 42.1002 | none | Suspension of work. | New number Same heading as today's 42.1302 | – → 45 |
| 42.1003 | none | Stop-work orders. | New number Same heading as today's 42.1303 | – → 291 |
| 42.1004 | none | Government delay of work. | New number Same heading as today's 42.1304 | – → 176 |
| 42.1005 | none | Contract clauses. | New number Same heading as today's 42.1305 | – → 151 |
| 42.1100 | none | Scope of subpart. | New number | – → 14 |
| 42.1101 | General. | General. | Changed · 5% alike | 48 → 224 |
| 42.1102 | Applicability. | Policy. | Changed · 2% alike | 31 → 703 |
| 42.1103 | Policy. | Procedures. | Changed · 1% alike | 43 → 2674 |
| 42.1104 | Surveillance requirements. | Contract clause. | Changed · 3% alike | 170 → 26 |
| 42.1105 | Assignment of criticality designator. | none | Not in the overhaul Same heading at 42.804 | 21 → – |
| 42.1106 | Reporting requirements. | none | Not in the overhaul | 167 → – |
| 42.1107 | Contract clause. | none | Not in the overhaul Same heading at 42.508-7 | 60 → – |
| 42.1200 | Scope of subpart. | none | Not in the overhaul | 48 → – |
| 42.1201 | [Reserved] | General. | Changed · 0% alike | 0 → 93 |
| 42.1202 | Responsibility for executing agreements. | none | Not in the overhaul | 165 → – |
| 42.1203 | Processing agreements. | none | Not in the overhaul | 504 → – |
| 42.1204 | Applicability of novation agreements. | none | Not in the overhaul | 1987 → – |
| 42.1205 | Agreement to recognize contractor's change of name. | none | Not in the overhaul Same heading at 42.904 | 550 → – |
| 42.1301 | General. | Procedures. | Changed · 5% alike | 48 → 349 |
| 42.1302 | Suspension of work. | none | Not in the overhaul Same heading at 42.1002 | 45 → – |
| 42.1303 | Stop-work orders. | none | Not in the overhaul Same heading at 42.1003 | 291 → – |
| 42.1304 | Government delay of work. | none | Not in the overhaul Same heading at 42.1004 | 176 → – |
| 42.1305 | Contract clauses. | none | Not in the overhaul Same heading at 42.1005 | 137 → – |
| 42.1500 | Scope of subpart. | none | Not in the overhaul | 66 → – |
| 42.1501 | General. | none | Not in the overhaul | 222 → – |
| 42.1502 | Policy. | none | Not in the overhaul | 699 → – |
| 42.1503 | Procedures. | none | Not in the overhaul | 1371 → – |
| 42.1504 | Contract clause. | none | Not in the overhaul Same heading at 42.508-7 | 26 → – |
| 42.1601 | General. | none | Not in the overhaul | 95 → – |
| 42.1701 | Procedures. | none | Not in the overhaul | 362 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress