The FAR overhaul, side by side
FAR Part 50: Extraordinary Contractual Actions and the Safety Act
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 34 sections, 7,041 words (Part 50 as in force, eCFR as of Oct 29, 2026). Overhaul text: 34 sections, 6,407 words, titled "Extraordinary Contractual Actions and the SAFETY Act" (on acquisition.gov ↗, issued Jul 31, 2025). By number: 14 the same, 20 changed, 0 not in the overhaul, 0 new.
50.102-3: Changed (87% alike)
Today: Limitations on exercise of authority.
(a) Pub. L. 85-804 is not authority for—
(1) Using a cost-plus-a-percentage-of-cost system of contracting;
(2) Making any contract that violates existing law limiting profit or fees;
(3) Providing for other than full and open competition for award of contracts for supplies or services; or
(4) Waiving any bid bond, payment bond, performance bond, or other bond required by law.
(b) No contract, amendment, or modification shall be made under Pub. L. 85-804's authority—
(1) Unless the approving authority finds that the action will facilitate the national defense;
(2) Unless other legal authority within the agency concerned is deemed to be lacking or inadequate;
(3) Except within the limits of the amounts appropriated and the statutory contract authorization (however, indemnification agreements authorized by an agency head (50.104-3) are not limited to amounts appropriated or to contract authorization); and
(4) That will obligate the Government for any amount over $150 million, unless the Senate and House Committees on Armed Services are notified in writing of the proposed obligation and 60 days of continuous session of Congress have passed since the transmittal of such notification. However, this paragraph (b)(4) does not apply to indemnification agreements authorized under 50.104-3.
(c) No contract shall be amended or modified unless the contractor submits a request before all obligations (including final payment) under the contract have been discharged. No amendment or modification shall increase the contract price to an amount higher than the lowest rejected bid of any responsible bidder, if the contract was negotiated under 14.404-1(f).
(d) No informal commitment shall be formalized unless—
(1) The contractor submits a written request for payment within 6 months after furnishing, or arranging to furnish, supplies or services in reliance upon the commitment; and
(2) The approving authority finds that, at the time the commitment was made, it was impracticable to use normal contracting procedures.
(e) The exercise of authority by officials below the secretarial level is subject to the following additional limitations:
(1) The action shall not—
(i) Release a contractor from performance of an obligation over $90,000;
(ii) Result in an increase in cost to the Government over $90,000;
(iii) Deal with, or directly affect, any matter that has been submitted to the Government Accountability Office; or
(iv) Involve disposal of Government surplus property.
(2) Mistakes shall not be corrected by an action obligating the Government for over $1,000, unless the contracting officer receives notice of the mistake before final payment.
(3) The correction of a contract because of a mistake in its making shall not increase the original contract price to an amount higher than the next lowest responsive offer of a responsible offeror.
(f) No executive department or agency shall exercise the indemnification authority granted under paragraph 1A of E.O. 10789 with respect to any supply or service that has been, or could be, designated by the Secretary of Homeland Security as a qualified anti-terrorism technology unless—
(1) For the Department of Defense, the Secretary of Defense has determined that the exercise of authority under E.O. 10789 is necessary for the timely and effective conduct of the United States military or intelligence activities, after consideration of the authority provided under the SAFETY Act (Subtitle G of title VIII of the Homeland Security Act of 2002, 6 U.S.C. 441-444); or
(2) For other departments and agencies that have authority under E.O. 10789—
(i) The Secretary of Homeland Security has advised whether the use of the authority under the SAFETY Act would be appropriate; and
(ii) The Director of the Office of Management and Budget has approved the exercise of authority under the Executive order.
Overhaul text: Limitations on exercise of authority.
(a) Pub. L. 85-804 is not authority for—
(1) Using a cost-plus-a-percentage-of-cost system of contracting;
(2) Making any contract that violates existing law limiting profit or fees;
(3) Providing for other than full and open competition for award of contracts for supplies or services; or
(4) Waiving any bid bond, payment bond, performance bond, or other bond required by law.
(b) No contract, amendment, or modification shall be made under Pub. L. 85-804’s authority-
(1) Unless the approving authority finds that the action will facilitate the national defense;
(2) Unless other legal authority within the agency concerned is deemed to be lacking or inadequate;
(3) Except within the limits of the amounts appropriated and the statutory contract authorization (however, indemnification agreements authorized by an agency head (50.104-3) are not limited to amounts appropriated or to contract authorization); and
(4) That will obligate the Government for any amount over $150 million unless the Senate and House Committees on Armed Services are notified in writing of the proposed obligation and 60 days of continuous session of Congress have passed since the transmittal of such notification. However, this paragraph (b)(4) does not apply to indemnification agreements authorized under 50.104-3.
(c) No contract shall be amended or modified unless the contractor submits a request before all obligations (including final payment) under the contract have been discharged. No amendment or modification shall increase the contract price to an amount higher than the lowest rejected bid of any responsible bidder, if the contract was negotiated under 14.404-1(f).
(d) No informal commitment will be formalized unless—
(1) The contractor submits a written request for payment within 6 months after furnishing, or arranging to furnish, supplies or services in reliance upon the commitment; and
(2) The approving authority finds that, at the time the commitment was made, it was impracticable to use normal contracting procedures.
(e) No executive department or agency will exercise the indemnification authority granted under paragraph 1 A of E.O. 10789 with respect to any supply or service that has been, or could be, designated by the Secretary of Homeland Security as a qualified anti-terrorism technology unless—
(1) For the Department of Defense, the Secretary of Defense has determined that the exercise of authority under E.O. 10789 is necessary for the timely and effective conduct of the United States military or intelligence activities, after consideration of the authority provided under the SAFETY Act (Subtitle G of title VIII of the Homeland Security Act of 2002, 6 U.S.C. 441-444); or
(2) For other departments and agencies that have authority under E.O. 10789—
(i) The Secretary of Homeland Security has advised whether the use of the authority under the SAFETY Act would be appropriate; and
(ii) The Director of the Office of Management and Budget has approved the exercise of authority under the Executive order.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 50.000 | Scope of part. | Scope of part. | Changed · 96% alike | 127 → 132 |
| 50.100 | Definitions. | Definitions. | Same | 48 → 48 |
| 50.101 | General. | General. | Same | 0 → 0 |
| 50.101-1 | Authority. | Authority. | Same | 144 → 144 |
| 50.101-2 | Policy. | Policy. | Changed · 57% alike | 151 → 114 |
| 50.101-3 | Records. | Records. | Changed · 95% alike | 64 → 64 |
| 50.102 | Delegation of and limitations on exercise of authority. | Delegation of and limitations on exercise of authority. | Same | 0 → 0 |
| 50.102-1 | Delegation of authority. | Delegation of authority. | Changed · 99% alike | 160 → 160 |
| 50.102-2 | Contract adjustment boards. | Contract adjustment boards. | Changed · 97% alike | 75 → 75 |
| 50.102-3 | Limitations on exercise of authority. | Limitations on exercise of authority. | Changed · 87% alike | 618 → 484 |
| 50.103 | Contract adjustments. | Contract adjustments. | Same | 21 → 21 |
| 50.103-1 | General. | General. | Same | 117 → 117 |
| 50.103-2 | Types of contract adjustment. | Types of contract adjustment. | Changed · 98% alike | 395 → 407 |
| 50.103-3 | Contract adjustment. | Contract adjustment. | Changed · 92% alike | 218 → 212 |
| 50.103-4 | Facts and evidence. | Facts and evidence. | Changed · 98% alike | 1306 → 1313 |
| 50.103-5 | Processing cases. | Processing cases. | Changed · 45% alike | 250 → 72 |
| 50.103-6 | Disposition. | Disposition. | Changed · 64% alike | 183 → 103 |
| 50.103-7 | Contract requirements. | Contract requirements. | Same | 134 → 134 |
| 50.104 | Residual powers. | Residual powers. | Same | 46 → 46 |
| 50.104-1 | Standards for use. | Standards for use. | Changed · 98% alike | 131 → 131 |
| 50.104-2 | General. | General. | Changed · 85% alike | 53 → 43 |
| 50.104-3 | Special procedures for unusually hazardous or nuclear risks. | Special procedures for unusually hazardous or nuclear risks. | Changed · 99% alike | 753 → 755 |
| 50.104-4 | Contract clause. | Contract clause. | Changed · 98% alike | 57 → 57 |
| 50.200 | Scope of subpart. | Scope of subpart. | Same | 27 → 27 |
| 50.201 | Definitions. | Definitions. | Same | 447 → 447 |
| 50.202 | Authorities. | Authorities. | Changed · 96% alike | 74 → 76 |
| 50.203 | General. | General. | Changed · 99% alike | 119 → 120 |
| 50.204 | Policy. | Policy. | Same | 182 → 182 |
| 50.205 | Procedures. | Procedures. | Same | 0 → 0 |
| 50.205-1 | SAFETY Act Considerations. | SAFETY Act Considerations. | Changed · 98% alike | 244 → 248 |
| 50.205-2 | Pre-qualification designation notice. | Pre-qualification designation notice. | Changed · 32% alike | 297 → 75 |
| 50.205-3 | Authorization of offers contingent upon SAFETY Act designation or certification before contract award. | Authorization of offers contingent upon SAFETY Act designation or certification before contract award. | Same | 144 → 144 |
| 50.205-4 | Authorization of awards made presuming SAFETY Act designation or certification after contract award. | Authorization of awards made presuming SAFETY Act designation or certification after contract award. | Same | 134 → 134 |
| 50.206 | Solicitation provisions and contract clause. | Solicitation provisions and contract clause. | Changed · 100% alike | 322 → 322 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress