The FAR overhaul, side by side

FAR Part 50: Extraordinary Contractual Actions and the Safety Act

Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.

Today: 34 sections, 7,041 words (Part 50 as in force, eCFR as of Oct 29, 2026). Overhaul text: 34 sections, 6,407 words, titled "Extraordinary Contractual Actions and the SAFETY Act" (on acquisition.gov ↗, issued Jul 31, 2025). By number: 14 the same, 20 changed, 0 not in the overhaul, 0 new.

50.104-1: Changed (98% alike)

Today: Standards for use.

This section in plain English

Subject to the limitations in 50.102-3, residual powers may be used in accordance with the policies in 50.101-2 when necessary and appropriate, all circumstances considered. In authorizing the inclusion of the clause at 52.250-1, Indemnification Under Public Law 85-804, in a contract or subcontract, an agency head may require the indemnified contractor to provide and maintain financial protection of the type and amount determined appropriate. In deciding whether to approve use of the indemnification clause, and in determining the type and amount of financial protection the indemnified contractor is to provide and maintain, an agency head shall consider such factors as self-insurance, other proof of financial responsibility, workers' compensation insurance, and the availability, cost, and terms of private insurance. The approval and determination shall be final.

Overhaul text: Standards for use.

On acquisition.gov ↗

Subject to the limitations in 50.102-3, residual powers may be used in accordance with the policies in 50.101-2 when necessary and appropriate, all circumstances considered. In authorizing the inclusion of the clause at 52.250-1, Indemnification Under Public Law 85-804, in a contract or subcontract, an agency head may require the indemnified contractor to provide and maintain financial protection of the type and amount determined appropriate. In deciding whether to approve use of the indemnification clause, and in determining the type and amount of financial protection the indemnified contractor is to provide and maintain, an agency head must consider such factors as self-insurance, other proof of financial responsibility, workers' compensation insurance, and the availability, cost, and terms of private insurance. The approval and determination must be final.

Section by section

SectionTodayOverhaul textStatusWords
50.000Scope of part.Scope of part.Changed · 96% alike127 → 132
50.100Definitions.Definitions.Same48 → 48
50.101General.General.Same0 → 0
50.101-1Authority.Authority.Same144 → 144
50.101-2Policy.Policy.Changed · 57% alike151 → 114
50.101-3Records.Records.Changed · 95% alike64 → 64
50.102Delegation of and limitations on exercise of authority.Delegation of and limitations on exercise of authority.Same0 → 0
50.102-1Delegation of authority.Delegation of authority.Changed · 99% alike160 → 160
50.102-2Contract adjustment boards.Contract adjustment boards.Changed · 97% alike75 → 75
50.102-3Limitations on exercise of authority.Limitations on exercise of authority.Changed · 87% alike618 → 484
50.103Contract adjustments.Contract adjustments.Same21 → 21
50.103-1General.General.Same117 → 117
50.103-2Types of contract adjustment.Types of contract adjustment.Changed · 98% alike395 → 407
50.103-3Contract adjustment.Contract adjustment.Changed · 92% alike218 → 212
50.103-4Facts and evidence.Facts and evidence.Changed · 98% alike1306 → 1313
50.103-5Processing cases.Processing cases.Changed · 45% alike250 → 72
50.103-6Disposition.Disposition.Changed · 64% alike183 → 103
50.103-7Contract requirements.Contract requirements.Same134 → 134
50.104Residual powers.Residual powers.Same46 → 46
50.104-1Standards for use.Standards for use.Changed · 98% alike131 → 131
50.104-2General.General.Changed · 85% alike53 → 43
50.104-3Special procedures for unusually hazardous or nuclear risks.Special procedures for unusually hazardous or nuclear risks.Changed · 99% alike753 → 755
50.104-4Contract clause.Contract clause.Changed · 98% alike57 → 57
50.200Scope of subpart.Scope of subpart.Same27 → 27
50.201Definitions.Definitions.Same447 → 447
50.202Authorities.Authorities.Changed · 96% alike74 → 76
50.203General.General.Changed · 99% alike119 → 120
50.204Policy.Policy.Same182 → 182
50.205Procedures.Procedures.Same0 → 0
50.205-1SAFETY Act Considerations.SAFETY Act Considerations.Changed · 98% alike244 → 248
50.205-2Pre-qualification designation notice.Pre-qualification designation notice.Changed · 32% alike297 → 75
50.205-3Authorization of offers contingent upon SAFETY Act designation or certification before contract award.Authorization of offers contingent upon SAFETY Act designation or certification before contract award.Same144 → 144
50.205-4Authorization of awards made presuming SAFETY Act designation or certification after contract award.Authorization of awards made presuming SAFETY Act designation or certification after contract award.Same134 → 134
50.206Solicitation provisions and contract clause.Solicitation provisions and contract clause.Changed · 100% alike322 → 322