The FAR overhaul, side by side
FAR Part 50: Extraordinary Contractual Actions and the Safety Act
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 34 sections, 7,041 words (Part 50 as in force, eCFR as of Oct 29, 2026). Overhaul text: 34 sections, 6,407 words, titled "Extraordinary Contractual Actions and the SAFETY Act" (on acquisition.gov ↗, issued Jul 31, 2025). By number: 14 the same, 20 changed, 0 not in the overhaul, 0 new.
50.104-3: Changed (99% alike)
Today: Special procedures for unusually hazardous or nuclear risks.
(a) Indemnification requests. (1) Contractor requests for the indemnification clause to cover unusually hazardous or nuclear risks should be submitted to the contracting officer and shall include the following information:
(i) Identification of the contract for which the indemnification clause is requested.
(ii) Identification and definition of the unusually hazardous or nuclear risks for which indemnification is requested, with a statement indicating how the contractor would be exposed to them.
(iii) A statement, executed by a corporate official with binding contractual authority, of all insurance coverage applicable to the risks to be defined in the contract as unusually hazardous or nuclear, including—
(A) Names of insurance companies, policy numbers, and expiration dates;
(B) A description of the types of insurance provided (including the extent to which the contractor is self-insured or intends to self-insure), with emphasis on identifying the risks insured against and the coverage extended to persons or property, or both;
(C) Dollar limits per occurrence and annually, and any other limitation, for relevant segments of the total insurance coverage;
(D) Deductibles, if any, applicable to losses under the policies;
(E) Any exclusions from coverage under such policies for unusually hazardous or nuclear risks; and
(F) Applicable workers' compensation insurance coverage.
(iv) The controlling or limiting factors for determining the amount of financial protection the contractor is to provide and maintain, with information regarding the availability, cost, and terms of additional insurance or other forms of financial protection.
(v) Whether the contractor's insurance program has been approved or accepted by any Government agency; and whether the contractor has an indemnification agreement covering similar risks under any other Government program, and, if so, a brief description of any limitations.
(vi) If the contractor is a division or subsidiary of a parent corporation—
(A) A statement of any insurance coverage of the parent corporation that bears on the risks for which the contractor seeks indemnification; and
(B) A description of the precise legal relationship between parent and subsidiary or division.
(2) If the dollar value of the contractor's insurance coverage varies by 10 percent or more from that stated in an indemnification request submitted in accordance with paragraph (a)(1) of this subsection, or if other significant changes in insurance coverage occur after submission and before approval, the contractor shall immediately submit to the contracting officer a brief description of the changes.
(b) Action on indemnification requests. (1) The contracting officer, with assistance from legal counsel and cognizant program office personnel, shall review the indemnification request and ascertain whether it contains all required information. If the contracting officer, after considering the facts and evidence, denies the request, the contracting officer shall notify the contractor promptly of the denial and of the reasons for it. If recommending approval, the contracting officer shall forward the request (as modified, if necessary, by negotiation) through channels to the appropriate official specified in 50.102-1(d). The contracting officer's submission shall include all information submitted by the contractor and—
(i) All pertinent information regarding the proposed contract or program, including the period of performance, locations, and facilities involved;
(ii) A definition of the unusually hazardous or nuclear risks involved in the proposed contract or program, with a statement that the parties have agreed to it;
(iii) A statement by responsible authority that the indemnification action would facilitate the national defense;
(iv) A statement that the contract will involve unusually hazardous or nuclear risks that could impose liability upon the contractor in excess of financial protection reasonably available;
(v) A statement that the contractor is complying with applicable Government safety requirements;
(vi) A statement of whether the indemnification should be extended to subcontractors; and
(vii) A description of any significant changes in the contractor's insurance coverage (see 50.104-3(a)(2)) occurring since submission of the indemnification request.
(2) Approval of a request to include the indemnification clause in a contract shall be by a Memorandum of Decision executed by the appropriate official specified in 50.102-1(d).
(3) When use of the indemnification clause is approved under paragraph (b)(2) of this subsection, the definition of unusually hazardous or nuclear risks (see paragraph (b)(1)(ii) of this subsection) shall be incorporated into the contract, along with the clause.
(4) When approval is—
(i) Authorized in the Memorandum of Decision; and
(ii) Justified by the circumstances, the contracting officer may approve the contractor's written request to provide for indemnification of subcontractors, using the same procedures as those required for contractors.
Overhaul text: Special procedures for unusually hazardous or nuclear risks.
(a) Indemnification requests .
(1) Contractor requests for the indemnification clause to cover unusually hazardous or nuclear risks should be submitted to the contracting officer and must include the following information:
(i) Identification of the contract for which the indemnification clause is requested.
(ii) Identification and definition of the unusually hazardous or nuclear risks for which indemnification is requested, with a statement indicating how the contractor would be exposed to them.
(iii) A statement, executed by a corporate official with binding contractual authority, of all insurance coverage applicable to the risks to be defined in the contract as unusually hazardous or nuclear, including-
(A) Names of insurance companies, policy numbers, and expiration dates;
(B) A description of the types of insurance provided (including the extent to which the contractor is self-insured or intends to self-insure), with emphasis on identifying the risks insured against and the coverage extended to persons or property, or both;
(C) Dollar limits per occurrence and annually, and any other limitation, for relevant segments of the total insurance coverage;
(D) Deductibles, if any, applicable to losses under the policies;
(E) Any exclusions from coverage under such policies for unusually hazardous or nuclear risks; and
(F) Applicable workers’ compensation insurance coverage.
(iv) The controlling or limiting factors for determining the amount of financial protection the contractor is to provide and maintain, with information regarding the availability, cost, and terms of additional insurance or other forms of financial protection.
(v) Whether the contractor’s insurance program has been approved or accepted by any Government agency; and whether the contractor has an indemnification agreement covering similar risks under any other Government program, and, if so, a brief description of any limitations.
(vi) If the contractor is a division or subsidiary of a parent corporation-
(A) A statement of any insurance coverage of the parent corporation that bears on the risks for which the contractor seeks indemnification; and
(B) A description of the precise legal relationship between parent and subsidiary or division.
(2) If the dollar value of the contractor’s insurance coverage varies by 10 percent or more from that stated in an indemnification request submitted in accordance with paragraph (a)(1) of this subsection, or if other significant changes in insurance coverage occur after submission and before approval, the contractor shall immediately submit to the contracting officer a brief description of the changes.
(b) Action on indemnification requests .
(1) The contracting officer, with assistance from legal counsel and cognizant program office personnel, shall review the indemnification request and ascertain whether it contains all required information. If the contracting officer, after considering the facts and evidence, denies the request, the contracting officer shall notify the contractor promptly of the denial and of the reasons for it. If recommending approval, the contracting officer shall forward the request (as modified, if necessary, by negotiation) through channels to the appropriate official specified in 50.102-1(d). The contracting officer’s submission shall include all information submitted by the contractor and-
(i) All pertinent information regarding the proposed contract or program, including the period of performance, locations, and facilities involved;
(ii) A definition of the unusually hazardous or nuclear risks involved in the proposed contract or program, with a statement that the parties have agreed to it;
(iii) A statement by responsible authority that the indemnification action would facilitate the national defense;
(iv) A statement that the contract will involve unusually hazardous or nuclear risks that could impose liability upon the contractor in excess of financial protection reasonably available;
(v) A statement that the contractor is complying with applicable Government safety requirements;
(vi) A statement of whether the indemnification should be extended to subcontractors; and
(vii) A description of any significant changes in the contractor's insurance coverage (see 50.104-3(a)(2)) occurring since submission of the indemnification request.
(2) Approval of a request to include the indemnification clause in a contract shall be by a Memorandum of Decision executed by the appropriate official specified in 50.102-1(d).
(3) When use of the indemnification clause is approved under paragraph (b)(2) of this subsection, the definition of unusually hazardous or nuclear risks (see paragraph (b)(1)(ii) of this subsection) shall be incorporated into the contract, along with the clause.
(4) When approval is-
(i) Authorized in the Memorandum of Decision; and
(ii) Justified by the circumstances, the contracting officer may approve the contractor’s written request to provide for indemnification of subcontractors, using the same procedures as those required for contractors.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 50.000 | Scope of part. | Scope of part. | Changed · 96% alike | 127 → 132 |
| 50.100 | Definitions. | Definitions. | Same | 48 → 48 |
| 50.101 | General. | General. | Same | 0 → 0 |
| 50.101-1 | Authority. | Authority. | Same | 144 → 144 |
| 50.101-2 | Policy. | Policy. | Changed · 57% alike | 151 → 114 |
| 50.101-3 | Records. | Records. | Changed · 95% alike | 64 → 64 |
| 50.102 | Delegation of and limitations on exercise of authority. | Delegation of and limitations on exercise of authority. | Same | 0 → 0 |
| 50.102-1 | Delegation of authority. | Delegation of authority. | Changed · 99% alike | 160 → 160 |
| 50.102-2 | Contract adjustment boards. | Contract adjustment boards. | Changed · 97% alike | 75 → 75 |
| 50.102-3 | Limitations on exercise of authority. | Limitations on exercise of authority. | Changed · 87% alike | 618 → 484 |
| 50.103 | Contract adjustments. | Contract adjustments. | Same | 21 → 21 |
| 50.103-1 | General. | General. | Same | 117 → 117 |
| 50.103-2 | Types of contract adjustment. | Types of contract adjustment. | Changed · 98% alike | 395 → 407 |
| 50.103-3 | Contract adjustment. | Contract adjustment. | Changed · 92% alike | 218 → 212 |
| 50.103-4 | Facts and evidence. | Facts and evidence. | Changed · 98% alike | 1306 → 1313 |
| 50.103-5 | Processing cases. | Processing cases. | Changed · 45% alike | 250 → 72 |
| 50.103-6 | Disposition. | Disposition. | Changed · 64% alike | 183 → 103 |
| 50.103-7 | Contract requirements. | Contract requirements. | Same | 134 → 134 |
| 50.104 | Residual powers. | Residual powers. | Same | 46 → 46 |
| 50.104-1 | Standards for use. | Standards for use. | Changed · 98% alike | 131 → 131 |
| 50.104-2 | General. | General. | Changed · 85% alike | 53 → 43 |
| 50.104-3 | Special procedures for unusually hazardous or nuclear risks. | Special procedures for unusually hazardous or nuclear risks. | Changed · 99% alike | 753 → 755 |
| 50.104-4 | Contract clause. | Contract clause. | Changed · 98% alike | 57 → 57 |
| 50.200 | Scope of subpart. | Scope of subpart. | Same | 27 → 27 |
| 50.201 | Definitions. | Definitions. | Same | 447 → 447 |
| 50.202 | Authorities. | Authorities. | Changed · 96% alike | 74 → 76 |
| 50.203 | General. | General. | Changed · 99% alike | 119 → 120 |
| 50.204 | Policy. | Policy. | Same | 182 → 182 |
| 50.205 | Procedures. | Procedures. | Same | 0 → 0 |
| 50.205-1 | SAFETY Act Considerations. | SAFETY Act Considerations. | Changed · 98% alike | 244 → 248 |
| 50.205-2 | Pre-qualification designation notice. | Pre-qualification designation notice. | Changed · 32% alike | 297 → 75 |
| 50.205-3 | Authorization of offers contingent upon SAFETY Act designation or certification before contract award. | Authorization of offers contingent upon SAFETY Act designation or certification before contract award. | Same | 144 → 144 |
| 50.205-4 | Authorization of awards made presuming SAFETY Act designation or certification after contract award. | Authorization of awards made presuming SAFETY Act designation or certification after contract award. | Same | 134 → 134 |
| 50.206 | Solicitation provisions and contract clause. | Solicitation provisions and contract clause. | Changed · 100% alike | 322 → 322 |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress