The FAR overhaul, side by side
FAR Part 6: Competition Requirements
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 34 sections, 6,960 words (Part 6 as in force, eCFR as of Oct 29, 2026). Overhaul text: 21 sections, 3,330 words (on acquisition.gov ↗, issued Jun 27, 2025). By number: 0 the same, 7 changed, 27 not in the overhaul (10 with the same heading under another number), 14 new.
6.101: Changed (11% alike)
Today: Policy.
(a) 10 U.S.C. 3201 and 41 U.S.C. 3301 require, with certain limited exceptions (see subparts 6.2 and 6.3), that contracting officers shall promote and provide for full and open competition in soliciting offers and awarding Government contracts.
(b) Contracting officers shall provide for full and open competition through use of the competitive procedure(s) contained in this subpart that are best suited to the circumstances of the contract action and consistent with the need to fulfill the Government's requirements efficiently (10 U.S.C. 3201 and 41 U.S.C. 3301).
Overhaul text: Full and open competition.
(a) Except as authorized by 6.102 and 6.103, contracting officers must obtain full and open competition by using competitive procedures to solicit offers and award Government contracts (see 10 U.S.C. 3201 and 41 U.S.C. 3301).
(b) Contracting officers must use the competitive procedure, or combination of procedures, best suited to efficiently fulfill the Government’s requirements. Competitive procedures include sealed bids, competitive proposals, and other procedures explicitly authorized by statute.
(1) Sealed bids . For sealed bidding procedures, see part 14. Use sealed bids only when the contracting officer has found that all of the following apply:
(i) Time permits staff to solicit, submit, and evaluate sealed bids;
(ii) The award will be made on the basis of price and other price-related factors;
(iii) Discussion with bidders is unnecessary; and
(iv) Contracting officers reasonably expect to receive more than one sealed bid.
(2) Competitive proposals . For competitive proposal procedures, see part 15.
(3) Other competitive procedures . The following procedures are also considered competitive procedures (see 41 U.S.C. 152):
(i) Selection of sources for architect-engineer contracts according to the provisions of 40 U.S.C. 1102 et seq .
(ii) Competitive selection of basic and applied research, as well as that part of development not related to developing a specific system or hardware procurement, if award results from—
(A) Proposals in response to a general solicitation or broad agency announcement; and
(B) A peer review or scientific review of such proposals.
(iii) Use of procedures established by the Administrator of General Services for the multiple award schedule program of the General Services Administration.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 6.000 | Scope of part. | Scope of part. | Changed · 29% alike | 66 → 11 |
| 6.001 | Applicability. | Applicability. | Changed · 86% alike | 178 → 155 |
| 6.002 | Limitations. | Limitations. | Changed · 77% alike | 21 → 18 |
| 6.003 | [Reserved] | Advocates for competition. | Changed · 0% alike | 0 → 68 |
| 6.100 | Scope of subpart. | none | Not in the overhaul | 21 → – |
| 6.101 | Policy. | Full and open competition. | Changed · 11% alike | 89 → 265 |
| 6.102 | Use of competitive procedures. | Full and open competition after excluding sources. | Changed · 11% alike | 239 → 65 |
| 6.102-1 | none | Establishing or maintaining alternative sources. | New number Same heading as today's 6.202 | – → 270 |
| 6.102-2 | none | Set-asides for small business concerns. | New number Same heading as today's 6.203 | – → 47 |
| 6.102-3 | none | Set-asides for local firms during a major disaster or emergency. | New number Same heading as today's 6.208 | – → 29 |
| 6.103 | none | Other than full and open competition. | New number | – → 134 |
| 6.103-1 | none | Only one responsible source and no other supplies or services will satisfy agency requirements. | New number Same heading as today's 6.302-1 | – → 295 |
| 6.103-2 | none | Unusual and compelling urgency. | New number Same heading as today's 6.302-2 | – → 271 |
| 6.103-3 | none | Industrial mobilization; engineering, developmental, or research capability; or expert services. | New number Same heading as today's 6.302-3 | – → 121 |
| 6.103-4 | none | International agreement. | New number Same heading as today's 6.302-4 | – → 103 |
| 6.103-5 | none | Authorized or required by statute. | New number Same heading as today's 6.302-5 | – → 381 |
| 6.103-6 | none | National security. | New number Same heading as today's 6.302-6 | – → 54 |
| 6.103-7 | none | Public interest. | New number Same heading as today's 6.302-7 | – → 104 |
| 6.104 | none | Justification and approval. | New number | – → 88 |
| 6.104-1 | none | Justification content. | New number | – → 386 |
| 6.104-2 | none | Approval of justification. | New number | – → 241 |
| 6.200 | Scope of subpart. | none | Not in the overhaul | 19 → – |
| 6.201 | Policy. | none | Not in the overhaul | 14 → – |
| 6.202 | Establishing or maintaining alternative sources. | none | Not in the overhaul Same heading at 6.102-1 | 267 → – |
| 6.203 | Set-asides for small business concerns. | none | Not in the overhaul Same heading at 6.102-2 | 82 → – |
| 6.204 | Section 8(a) competition. | none | Not in the overhaul | 73 → – |
| 6.205 | Set-asides for HUBZone small business concerns. | none | Not in the overhaul | 59 → – |
| 6.206 | Set-asides for service-disabled veteran-owned small business (SDVOSB) concerns eligible under the SDVOSB Program. | none | Not in the overhaul | 75 → – |
| 6.207 | Set-asides for economically disadvantaged women-owned small business (EDWOSB) concerns or women-owned small business (WOSB) concerns eligible under the WOSB Program. | none | Not in the overhaul | 63 → – |
| 6.208 | Set-asides for local firms during a major disaster or emergency. | none | Not in the overhaul Same heading at 6.102-3 | 101 → – |
| 6.300 | Scope of subpart. | none | Not in the overhaul | 20 → – |
| 6.301 | Policy. | Availability of the justification. | Changed · 11% alike | 227 → 224 |
| 6.302 | Circumstances permitting other than full and open competition. | none | Not in the overhaul | 30 → – |
| 6.302-1 | Only one responsible source and no other supplies or services will satisfy agency requirements. | none | Not in the overhaul Same heading at 6.103-1 | 907 → – |
| 6.302-2 | Unusual and compelling urgency. | none | Not in the overhaul Same heading at 6.103-2 | 428 → – |
| 6.302-3 | Industrial mobilization; engineering, developmental, or research capability; or expert services. | none | Not in the overhaul Same heading at 6.103-3 | 629 → – |
| 6.302-4 | International agreement. | none | Not in the overhaul Same heading at 6.103-4 | 191 → – |
| 6.302-5 | Authorized or required by statute. | none | Not in the overhaul Same heading at 6.103-5 | 542 → – |
| 6.302-6 | National security. | none | Not in the overhaul Same heading at 6.103-6 | 165 → – |
| 6.302-7 | Public interest. | none | Not in the overhaul Same heading at 6.103-7 | 195 → – |
| 6.303 | Justifications. | none | Not in the overhaul | 0 → – |
| 6.303-1 | Requirements. | none | Not in the overhaul | 297 → – |
| 6.303-2 | Content. | none | Not in the overhaul | 575 → – |
| 6.304 | Approval of the justification. | none | Not in the overhaul | 336 → – |
| 6.305 | Availability of the justification. | none | Not in the overhaul | 349 → – |
| 6.401 | Sealed bidding and competitive proposals. | none | Not in the overhaul | 187 → – |
| 6.501 | Requirement. | none | Not in the overhaul | 99 → – |
| 6.502 | Duties and responsibilities. | none | Not in the overhaul | 416 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress