The FAR overhaul, side by side
FAR Part 6: Competition Requirements
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 34 sections, 6,960 words (Part 6 as in force, eCFR as of Oct 29, 2026). Overhaul text: 21 sections, 3,330 words (on acquisition.gov ↗, issued Jun 27, 2025). By number: 0 the same, 7 changed, 27 not in the overhaul (10 with the same heading under another number), 14 new.
6.303-1: Not in the overhaul
Today: Requirements.
(a) A contracting officer shall not commence negotiations for a sole source contract, commence negotiations for a contract resulting from an unsolicited proposal, or award any other contract without providing for full and open competition unless the contracting officer—
(1) Justifies, if required in 6.302, the use of such actions in writing;
(2) Certifies the accuracy and completeness of the justification; and
(3) Obtains the approval required by 6.304.
(b) The contracting officer shall not award a sole-source contract under the 8(a) authority (15 U.S.C. 637(a)) for an amount exceeding $30 million unless—
(1) The contracting officer justifies the use of a sole-source contract in writing in accordance with 6.303-2;
(2) The justification is approved by the appropriate official designated at 6.304; and
(3) The justification and related information are made public after award in accordance with 6.305.
(c) Technical and requirements personnel are responsible for providing and certifying as accurate and complete necessary data to support their recommendation for other than full and open competition.
(d) Justifications required by paragraph (a) of this section may be made on an individual or class basis. Any justification for contracts awarded under the authority of 6.302-7 shall only be made on an individual basis. Whenever a justification is made and approved on a class basis, the contracting officer must ensure that each contract action taken pursuant to the authority of the class justification and approval is within the scope of the class justification and approval and shall document the contract file for each contract action accordingly.
(e) The justifications for contracts awarded under the authority cited in 6.302-2 may be prepared and approved within a reasonable time after contract award when preparation and approval prior to award would unreasonably delay the acquisitions.
Overhaul text
No section with this number.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 6.000 | Scope of part. | Scope of part. | Changed · 29% alike | 66 → 11 |
| 6.001 | Applicability. | Applicability. | Changed · 86% alike | 178 → 155 |
| 6.002 | Limitations. | Limitations. | Changed · 77% alike | 21 → 18 |
| 6.003 | [Reserved] | Advocates for competition. | Changed · 0% alike | 0 → 68 |
| 6.100 | Scope of subpart. | none | Not in the overhaul | 21 → – |
| 6.101 | Policy. | Full and open competition. | Changed · 11% alike | 89 → 265 |
| 6.102 | Use of competitive procedures. | Full and open competition after excluding sources. | Changed · 11% alike | 239 → 65 |
| 6.102-1 | none | Establishing or maintaining alternative sources. | New number Same heading as today's 6.202 | – → 270 |
| 6.102-2 | none | Set-asides for small business concerns. | New number Same heading as today's 6.203 | – → 47 |
| 6.102-3 | none | Set-asides for local firms during a major disaster or emergency. | New number Same heading as today's 6.208 | – → 29 |
| 6.103 | none | Other than full and open competition. | New number | – → 134 |
| 6.103-1 | none | Only one responsible source and no other supplies or services will satisfy agency requirements. | New number Same heading as today's 6.302-1 | – → 295 |
| 6.103-2 | none | Unusual and compelling urgency. | New number Same heading as today's 6.302-2 | – → 271 |
| 6.103-3 | none | Industrial mobilization; engineering, developmental, or research capability; or expert services. | New number Same heading as today's 6.302-3 | – → 121 |
| 6.103-4 | none | International agreement. | New number Same heading as today's 6.302-4 | – → 103 |
| 6.103-5 | none | Authorized or required by statute. | New number Same heading as today's 6.302-5 | – → 381 |
| 6.103-6 | none | National security. | New number Same heading as today's 6.302-6 | – → 54 |
| 6.103-7 | none | Public interest. | New number Same heading as today's 6.302-7 | – → 104 |
| 6.104 | none | Justification and approval. | New number | – → 88 |
| 6.104-1 | none | Justification content. | New number | – → 386 |
| 6.104-2 | none | Approval of justification. | New number | – → 241 |
| 6.200 | Scope of subpart. | none | Not in the overhaul | 19 → – |
| 6.201 | Policy. | none | Not in the overhaul | 14 → – |
| 6.202 | Establishing or maintaining alternative sources. | none | Not in the overhaul Same heading at 6.102-1 | 267 → – |
| 6.203 | Set-asides for small business concerns. | none | Not in the overhaul Same heading at 6.102-2 | 82 → – |
| 6.204 | Section 8(a) competition. | none | Not in the overhaul | 73 → – |
| 6.205 | Set-asides for HUBZone small business concerns. | none | Not in the overhaul | 59 → – |
| 6.206 | Set-asides for service-disabled veteran-owned small business (SDVOSB) concerns eligible under the SDVOSB Program. | none | Not in the overhaul | 75 → – |
| 6.207 | Set-asides for economically disadvantaged women-owned small business (EDWOSB) concerns or women-owned small business (WOSB) concerns eligible under the WOSB Program. | none | Not in the overhaul | 63 → – |
| 6.208 | Set-asides for local firms during a major disaster or emergency. | none | Not in the overhaul Same heading at 6.102-3 | 101 → – |
| 6.300 | Scope of subpart. | none | Not in the overhaul | 20 → – |
| 6.301 | Policy. | Availability of the justification. | Changed · 11% alike | 227 → 224 |
| 6.302 | Circumstances permitting other than full and open competition. | none | Not in the overhaul | 30 → – |
| 6.302-1 | Only one responsible source and no other supplies or services will satisfy agency requirements. | none | Not in the overhaul Same heading at 6.103-1 | 907 → – |
| 6.302-2 | Unusual and compelling urgency. | none | Not in the overhaul Same heading at 6.103-2 | 428 → – |
| 6.302-3 | Industrial mobilization; engineering, developmental, or research capability; or expert services. | none | Not in the overhaul Same heading at 6.103-3 | 629 → – |
| 6.302-4 | International agreement. | none | Not in the overhaul Same heading at 6.103-4 | 191 → – |
| 6.302-5 | Authorized or required by statute. | none | Not in the overhaul Same heading at 6.103-5 | 542 → – |
| 6.302-6 | National security. | none | Not in the overhaul Same heading at 6.103-6 | 165 → – |
| 6.302-7 | Public interest. | none | Not in the overhaul Same heading at 6.103-7 | 195 → – |
| 6.303 | Justifications. | none | Not in the overhaul | 0 → – |
| 6.303-1 | Requirements. | none | Not in the overhaul | 297 → – |
| 6.303-2 | Content. | none | Not in the overhaul | 575 → – |
| 6.304 | Approval of the justification. | none | Not in the overhaul | 336 → – |
| 6.305 | Availability of the justification. | none | Not in the overhaul | 349 → – |
| 6.401 | Sealed bidding and competitive proposals. | none | Not in the overhaul | 187 → – |
| 6.501 | Requirement. | none | Not in the overhaul | 99 → – |
| 6.502 | Duties and responsibilities. | none | Not in the overhaul | 416 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress