DFARS 252.217-7007 Payments.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This clause explains how the Government will make progress payments to a contractor for work performed under a job order before the work is finished. It also describes when the contractor can submit invoices, the minimum amount for progress payments, and how the Government will retain a portion of payments until final completion and acceptance.
Applies to: Contractors performing job orders under a Master Agreement, as prescribed in DFARS 217.7104(a).
What it requires
- Submit invoices in the form and number of copies directed by the Contracting Officer.
- Upon request, furnish the Contracting Officer any reports concerning expenditures on the work to date that the Contracting Officer may require.
- Upon completion of the work and final inspection and acceptance, submit invoices in such form and with such copies as the Contracting Officer may prescribe to be paid the price of the job order, less any performance reserves and previous payments.
Key terms: Progress payments · Job order · Contracting Officer · Master Agreement · Changes clause
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 217.7104(a), use the following clause:
Payments (DEC 1991)
(a) Progress payments, as used in this clause, means payments made before completion of work in progress under a job order.
(b) Upon submission by the Contractor of invoices in the form and number of copies directed by the Contracting Officer, and as approved by the Contracting Officer, the Government will make progress payments as work progresses under the job order.
(1) Generally, the Contractor may submit invoices on a semi-monthly basis, unless expenditures justify a more frequent submission.
(2) The Government need not make progress payments for invoices aggregating less than $5,000.
(3) The Contracting Officer shall approve progress payments based on the value, computed on the price of the job order, of labor and materials incorporated in the work, materials suitably stored at the site of the work, and preparatory work completed, less the aggregate of any previous payments.
(4) Upon request, the Contractor will furnish the Contracting Officer any reports concerning expenditures on the work to date that the Contracting Officer may require.
(c) The Government will retain until final completion and acceptance of all work covered by the job order, an amount estimated or approved by the Contracting Officer under paragraph (b) of this clause. The amount retained will be in accordance with the rate authorized by Congress for Naval vessel repair contracts at the time of job order award.
(d) The Contracting Officer may direct that progress payments be based on the price of the job order as adjusted as a result of change orders under the Changes clause of the Master Agreement. If the Contracting Officer does not so direct—
(1) Payments of any increases shall be made from time to time after the amount of the increase is determined under the Changes clause of the Master Agreement; and
(2) Reductions resulting from decreases shall be made for the purposes of subsequent progress payments as soon as the amounts are determined under the Changes clause of the Master Agreement.
(e) Upon completion of the work under a job order and final inspection and acceptance, and upon submission of invoices in such form and with such copies as the Contracting Officer may prescribe, the Contractor shall be paid for the price of the job order, as adjusted pursuant to the Changes clause of the Master Agreement, less any performance reserves deemed necessary by the Contracting Officer, and less the amount of any previous payments.
(f) All materials, equipment, or any other property or work in process covered by the progress payments made by the Government, upon the making of those progress payments, shall become the sole property of the Government, and are subject to the provisions of the Title clause of the Master Agreement.
(End of clause)
← 252.217-7006 Title. · 252.217-7008 Bonds. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.