DFARS 252.217-7006 Title.

In plain English: This clause sets out who owns materials and equipment on a vessel during a job order. Materials and equipment the contractor incorporates into a vessel become Government property once delivered to the work location, while leftover contractor-furnished items not placed on a vessel go to the contractor upon completion or with Contracting Officer approval, unless the Government already paid for them. It also clarifies that the vessel and its equipment, stores, cargo, and ship's materials are not treated as Government-furnished property. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 217.7104(a), which says when contracting officers use it.

Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.217-7006 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.217-7006 · Ask the AI chat about it

In more detail

Applies to: contractors performing ship repair or vessel job orders under DFARS 217.7104

What it requires

  • Deliver materials and equipment to be incorporated in a vessel to the location specified for the work, where title then vests in the Government
  • Obtain Contracting Officer approval during performance if contractor-furnished materials not placed on a vessel are to be retained before job order completion
  • Recognize that unused contractor-furnished materials become the contractor's property on completion, unless the Government reimbursed their cost

Key terms: title · job order · vest · contractor-furnished materials and equipment · Government-furnished property

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 217.7104(a), use the following clause:

Title (DEC 1991)

(a) Unless otherwise provided, title to all materials and equipment to be incorporated in a vessel in the performance of a job order shall vest in the Government upon delivery at the location specified for the performance of the work.

(b) Upon completion of the job order, or with the approval of the Contracting Officer during performance of the job order, all Contractor-furnished materials and equipment not incorporated in, or placed on, any vessel, shall become the property of the Contractor, unless the Government has reimbursed the Contractor for the cost of the materials and equipment.

(c) The vessel, its equipment, movable stores, cargo, or other ship's materials shall not be considered Government-furnished property.

(End of clause)

Sections it refers to

Sections that refer to it

Related DFARS 252.217 sections

← 252.217-7005 Inspection and manner of doing work. · 252.217-7007 Payments. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.