FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2

DFARS 252.217-7006 Title.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This clause governs who owns materials and equipment used on a vessel under a job order. Title to materials and equipment that will be built into the vessel passes to the Government when they are delivered to the work location. It also explains what happens to leftover Contractor-furnished items and clarifies that the vessel itself and its contents are not Government-furnished property.

Applies to: Contractors performing a job order on a vessel under a DFARS contract

What it requires

  • Deliver materials and equipment to the specified work location so title vests in the Government
  • Return or transfer Contractor-furnished materials and equipment not incorporated into the vessel to the Contractor upon completion or with Contracting Officer approval, unless the Government reimbursed their cost

Key terms: title · job order · Government-furnished property · Contractor-furnished materials and equipment · Contracting Officer

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 217.7104(a), use the following clause:

Title (DEC 1991)

(a) Unless otherwise provided, title to all materials and equipment to be incorporated in a vessel in the performance of a job order shall vest in the Government upon delivery at the location specified for the performance of the work.

(b) Upon completion of the job order, or with the approval of the Contracting Officer during performance of the job order, all Contractor-furnished materials and equipment not incorporated in, or placed on, any vessel, shall become the property of the Contractor, unless the Government has reimbursed the Contractor for the cost of the materials and equipment.

(c) The vessel, its equipment, movable stores, cargo, or other ship's materials shall not be considered Government-furnished property.

(End of clause)

Sections it refers to

Sections that refer to it

← 252.217-7005 Inspection and manner of doing work. · 252.217-7007 Payments. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

DFARS 252.217-7006 Title · SpendQuery