FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2
DFARS 252.236-7000 Modification proposals—price breakdown.
In plain English: When a contractor submits a proposal to modify its contract, this clause requires a price breakdown itemized as the Contracting Officer specifies and within the time they set. The breakdown must show enough detail to analyze profit and all costs for material, labor, equipment, subcontracts, and overhead, and must cover all work added, deleted, or changed. Contractors must also support subcontract amounts with similar breakdowns and justify any requested time extension. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 236.570(a), which says when contracting officers use it.
Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.236-7000 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.236-7000 · Ask the AI chat about it
In more detail
Applies to: contractors submitting proposals for contract modifications
What it requires
- Furnish a price breakdown, itemized as required and within the time the Contracting Officer specifies, with any modification proposal
- Include enough detail to permit analysis of profit and all costs for material, labor, equipment, subcontracts, and overhead
- Cover all work involved in the modification, whether deleted, added, or changed
- Provide similar price breakdowns to support amounts claimed for subcontracts and include a justification for any proposed time extension
Key terms: Modification proposal · Price breakdown · Contracting Officer · Subcontracts · Overhead
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 236.570(a), use the following clause:
Modification Proposals—Price Breakdown (DEC 1991)
(a) The Contractor shall furnish a price breakdown, itemized as required and within the time specified by the Contracting Officer, with any proposal for a contract modification.
(b) The price breakdown—
(1) Must include sufficient detail to permit an analysis of profit, and of all costs for—
(i) Material;
(ii) Labor;
(iii) Equipment;
(iv) Subcontracts; and
(v) Overhead; and
(2) Must cover all work involved in the modification, whether the work was deleted, added, or changed.
(c) The Contractor shall provide similar price breakdowns to support any amounts claimed for subcontracts.
(d) The Contractor's proposal shall include a justification for any time extension proposed.
(End of clause)
Sections it refers to
- 236.570 Additional provisions and clauses.
Sections that refer to it
- 236.570 Additional provisions and clauses.
Related DFARS 252.236 sections
- 252.236-7001 Contract drawings and specifications.
- 252.236-7002 Obstruction of navigable waterways.
- 252.236-7003 Payment for mobilization and preparatory work.
- 252.236-7004 Payment for mobilization and demobilization.
- 252.236-7005 Airfield safety precautions.
- 252.236-7006 Cost limitation.
- 252.236-7007 Additive or deductive items.
- 252.236-7008 Contract prices—bidding schedules.
- 252.236-7009 [Reserved]
- 252.236-7010 Overseas military construction—Preference for United States firms.
- 252.236-7011 Overseas architect-engineer services—Restriction to United States firms.
- 252.236-7012 Military construction on Kwajalein Atoll—evaluation preference.
← 252.235-7011 Final scientific or technical report. · 252.236-7001 Contract drawings and specifications. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.