DFARS 252.236-7001 Contract drawings and specifications.
In plain English: This clause says the Government gives the contractor one free set of contract drawings and specifications, and the contractor must check them on receipt, verify figures before starting work, and report discrepancies promptly. It also sets rules for resolving conflicts (large-scale drawings govern small-scale ones; written figures govern over scale measurements) and makes the contractor responsible for omitted or misdescribed details that are necessary or customary, so gaps in the drawings do not excuse incomplete work. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 236.570(a), which says when contracting officers use it.
Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.236-7001 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.236-7001 · Ask the AI chat about it
In more detail
Applies to: contractors performing construction or other work under DoD contracts that include drawings and specifications
What it requires
- Check all drawings furnished immediately upon receipt
- Compare all drawings and verify the figures before laying out the work
- Promptly notify the Contracting Officer of any discrepancies
- Perform omitted or misdescribed details that are manifestly necessary or customarily performed, as if correctly described
Key terms: contract drawings and specifications · Contracting Officer · large-scale drawings govern small-scale drawings · figures marked on drawings take precedence over scale measurements · discrepancies
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 236.570(a), use the following clause:
Contract Drawings and Specifications (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall—
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general—
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title File Drawing No.
(End of clause)
Sections it refers to
- 236.570 Additional provisions and clauses.
Sections that refer to it
- 236.570 Additional provisions and clauses.
Related DFARS 252.236 sections
- 252.236-7000 Modification proposals—price breakdown.
- 252.236-7002 Obstruction of navigable waterways.
- 252.236-7003 Payment for mobilization and preparatory work.
- 252.236-7004 Payment for mobilization and demobilization.
- 252.236-7005 Airfield safety precautions.
- 252.236-7006 Cost limitation.
- 252.236-7007 Additive or deductive items.
- 252.236-7008 Contract prices—bidding schedules.
- 252.236-7009 [Reserved]
- 252.236-7010 Overseas military construction—Preference for United States firms.
- 252.236-7011 Overseas architect-engineer services—Restriction to United States firms.
- 252.236-7012 Military construction on Kwajalein Atoll—evaluation preference.
← 252.236-7000 Modification proposals—price breakdown. · 252.236-7002 Obstruction of navigable waterways. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.