DFARS 252.236-7004 Payment for mobilization and demobilization.
In plain English: This clause says the Government pays the full cost of moving the contractor's plant and equipment to and from the work site under a single lump-sum item, with the payment split between a portion paid after mobilization and the remainder paid after demobilization. If the Contracting Officer finds the split does not reasonably reflect actual costs, the contractor may be required to justify its bid price with cost data, and failure to do so lets the Contracting Officer pay actual costs instead, with that determination not appealable. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 236.570(b)(2), which says when contracting officers use it.
Last amended 2022-05-26 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.236-7004 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.236-7004 · Ask the AI chat about it
In more detail
Applies to: Contractors under fixed-price construction contracts with a lump-sum mobilization and demobilization item
What it requires
- Furnish cost data to justify the mobilization/demobilization price if the Contracting Officer requests it
- Accept the Contracting Officer's determination of actual costs if the price is not justified to the Contracting Officer's satisfaction
Key terms: mobilization · demobilization · plant and equipment · lump sum price · Contracting Officer
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 236.570(b)(2), use the following clause:
Payment for Mobilization and Demobilization (DEC 1991)
(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.
(1) ________ percent of the lump sum price upon completion of the contractor's mobilization at the work site.
(2) The remaining ________ percent upon completion of demobilization.
(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a) (1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.
(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of—
(i) Actual mobilization costs at completion of mobilization;
(ii) Actual demobilization costs at completion of demobilization; and
(iii) The remainder of this item in the final payment under this contract.
(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.
(End of clause)
Sections it refers to
- 236.570 Additional provisions and clauses.
Sections that refer to it
- 236.570 Additional provisions and clauses.
Related DFARS 252.236 sections
- 252.236-7000 Modification proposals—price breakdown.
- 252.236-7001 Contract drawings and specifications.
- 252.236-7002 Obstruction of navigable waterways.
- 252.236-7003 Payment for mobilization and preparatory work.
- 252.236-7005 Airfield safety precautions.
- 252.236-7006 Cost limitation.
- 252.236-7007 Additive or deductive items.
- 252.236-7008 Contract prices—bidding schedules.
- 252.236-7009 [Reserved]
- 252.236-7010 Overseas military construction—Preference for United States firms.
- 252.236-7011 Overseas architect-engineer services—Restriction to United States firms.
- 252.236-7012 Military construction on Kwajalein Atoll—evaluation preference.
← 252.236-7003 Payment for mobilization and preparatory work. · 252.236-7005 Airfield safety precautions. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.