The FAR overhaul, side by side
FAR Part 15: Contracting by Negotiation
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 81 sections, 32,499 words (Part 15 as in force, eCFR as of Oct 29, 2026). Overhaul text: 91 sections, 28,441 words (on acquisition.gov ↗, issued Sep 30, 2025). By number: 1 the same, 44 changed, 36 not in the overhaul (10 with the same heading under another number), 46 new.
15.105-5: New number
Today
No section with this number.
Overhaul text: Make-or-buy decision.
(a) General. The Government may choose to review and agree on the offeror's make-or-buy program when necessary to ensure negotiation of reasonable contract prices, satisfactory performance, or implementation of socioeconomic policies.
(b) Acquisitions requiring make-or-buy programs.
(1) Contracting officers may require offerors to submit make-or-buy program plans for acquisitions requiring certified cost or pricing data whose estimated value is $20 million or more, except when the proposed contract is for research or development and, if prototypes or hardware are involved, no significant follow-on production is anticipated.
(2) Contracting officers may only require offerors to submit make-or-buy programs for acquisitions whose estimated value is under $20 million if the contracting officer—
(i) Determines that the information is necessary; and
(ii) Documents the reasons in the contract file.
(c) RFP requirements. When offerors must submit proposed make-or-buy programs, the RFP must include—
(1) A statement that the program and required supporting information must accompany the offer; and
(2) A description of factors to be used in evaluating the proposed program.
(d) Required information from offerors.
(1) The information required from an offeror about a make-or-buy program must—
(i) Be confined to those major items or work efforts that normally would require company management review of the make-or-buy decision because they are complex, costly, needed in large quantities, or require additional equipment or real property to produce;
(ii) Not include raw materials, products, commercial services, and off-the-shelf items, unless their potential impact on contract cost or schedule is critical; and,
(iii) Not include items or work efforts estimated to cost less than 1 percent of the total estimated contract price or any minimum dollar amount set by the agency.
(2) To support a make-or-buy program, the following information must be provided by an offeror in its proposal:
(i) A description of each major item or work effort.
(ii) Categorization of each major item or work effort as “must make,” “must buy, or “can either make or buy.”
(iii) For each item or work effort categorized as “can either make or buy,” a proposal either to “make” or to “buy.”
(iv) Reasons for categorizing items and work efforts as “must make” or “must buy,” and proposing to “make” or to “buy” those categorized as “can either make or buy.” The reasons must include the consideration given to the evaluation factors described in the RFP and must be in sufficient detail to permit the contracting officer to evaluate the categorization or proposal.
(v) Designation of the plant or division proposed to make each item or perform each work effort, and a statement as to whether the existing or proposed new facility is in or near a labor surplus area.
(vi) Identification of proposed subcontractors, if known, and their location and size status.
(vii) Any recommendations to defer make-or-buy decisions when categorization of some items or work efforts is impracticable at the time of submission.
(viii) Any other information the contracting officer requires in order to evaluate the program.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 15.000 | Scope of part. | Scope. | Changed · 35% alike | 28 → 46 |
| 15.001 | Definitions. | Definitions. | Changed · 75% alike | 136 → 149 |
| 15.002 | Types of negotiated acquisition. | Types of negotiated acquisition. | Changed · 47% alike | 94 → 121 |
| 15.100 | Scope of subpart. | Scope. | Changed · 17% alike | 27 → 32 |
| 15.101 | Best value continuum. | Early exchanges with industry. | Changed · 5% alike | 95 → 452 |
| 15.101-1 | Tradeoff process. | none | Not in the overhaul | 153 → – |
| 15.101-2 | Lowest price technically acceptable source selection process. | none | Not in the overhaul | 555 → – |
| 15.101-3 | Tiered evaluation of small business offers. | none | Not in the overhaul | 28 → – |
| 15.102 | Oral presentations. | Structuring a request for proposals. | Changed · 8% alike | 550 → 330 |
| 15.103 | none | Developing a competitive source selection approach. | New number | – → 82 |
| 15.103-1 | none | Tradeoff approach. | New number | – → 64 |
| 15.103-2 | none | Lowest price technically acceptable approach. | New number | – → 385 |
| 15.103-3 | none | Highest technically rated with a fair and reasonable price approach | New number | – → 238 |
| 15.103-4 | none | Phased acquisition. | New number | – → 101 |
| 15.104 | none | Establishing competitive evaluation factors and significant subfactors. | New number | – → 709 |
| 15.105 | none | Other considerations. | New number | – → 0 |
| 15.105-1 | none | Oral presentations. | New number | – → 76 |
| 15.105-2 | none | Negotiations disclosure. | New number | – → 50 |
| 15.105-3 | none | Limitation on tiered evaluations for multiple award contracts. | New number | – → 35 |
| 15.105-4 | none | Request for cost or pricing data. | New number | – → 261 |
| 15.105-5 | none | Make-or-buy decision. | New number | – → 515 |
| 15.105-6 | none | Should-cost review. | New number Same heading as today's 15.407-4 | – → 28 |
| 15.105-7 | none | Unit prices. | New number | – → 55 |
| 15.106 | none | Amending a request for proposal. | New number | – → 328 |
| 15.107 | none | Submission, modification, revision, and withdrawal of proposals. | New number Same heading as today's 15.208 | – → 593 |
| 15.108 | none | Receiving proposals. | New number | – → 143 |
| 15.109 | none | Uniform contract format. | New number | – → 74 |
| 15.109-1 | none | Part I - The Schedule. | New number | – → 317 |
| 15.109-2 | none | Part II - Contract Clauses. | New number Same heading as today's 15.204-3 | – → 55 |
| 15.109-3 | none | Part III - List of Documents, Exhibits, and Other Attachments. | New number Same heading as today's 15.204-4 | – → 37 |
| 15.109-4 | none | Part IV - Representations and Instructions. | New number Same heading as today's 15.204-5 | – → 155 |
| 15.110 | none | Solicitation provisions and contract clauses. | New number Same heading as today's 15.209 | – → 1609 |
| 15.200 | Scope of subpart. | Scope. | Changed · 35% alike | 36 → 15 |
| 15.201 | Exchanges with industry before receipt of proposals. | Source selection responsibilities. | Changed · 7% alike | 527 → 352 |
| 15.202 | Advisory multi-step process. | Evaluating competitive proposals. | Changed · 9% alike | 250 → 735 |
| 15.203 | Requests for proposals. | Competitive award without negotiation. | Changed · 6% alike | 566 → 64 |
| 15.204 | Contract format. | Competitive award with negotiation. | Changed · 0% alike | 93 → 0 |
| 15.204-1 | Uniform contract format. | Establishing a competitive range. | Changed · 12% alike | 108 → 139 |
| 15.204-2 | Part I—The Schedule. | Competitive negotiations. | Changed · 6% alike | 359 → 409 |
| 15.204-3 | Part II—Contract Clauses. | none | Not in the overhaul Same heading at 15.109-2 | 61 → – |
| 15.204-4 | Part III—List of Documents, Exhibits, and Other Attachments. | none | Not in the overhaul Same heading at 15.109-3 | 37 → – |
| 15.204-5 | Part IV—Representations and Instructions. | none | Not in the overhaul Same heading at 15.109-4 | 189 → – |
| 15.205 | Issuing solicitations. | Source selection decision. | Changed · 7% alike | 40 → 72 |
| 15.206 | Amending the solicitation. | Preaward notices and debriefings. | Changed · 5% alike | 305 → 69 |
| 15.206-1 | none | Preaward notices. | New number | – → 189 |
| 15.206-2 | none | Preaward debriefing. | New number | – → 411 |
| 15.207 | Handling proposals and information. | Award. | Changed · 0% alike | 195 → 0 |
| 15.207-1 | none | Award to successful offeror. | New number | – → 185 |
| 15.207-2 | none | Award notice. | New number | – → 249 |
| 15.208 | Submission, modification, revision, and withdrawal of proposals. | none | Not in the overhaul Same heading at 15.107 | 611 → – |
| 15.209 | Solicitation provisions and contract clauses. | none | Not in the overhaul Same heading at 15.110 | 509 → – |
| 15.210 | Forms. | none | Not in the overhaul | 90 → – |
| 15.300 | Scope of subpart. | Scope. | Changed · 17% alike | 17 → 64 |
| 15.301 | [Reserved] | Postaward debriefing of offerors. | Changed · 0% alike | 0 → 15 |
| 15.301-1 | none | Debriefing process. | New number | – → 597 |
| 15.301-2 | none | Opportunity for follow-up questions. | New number | – → 22 |
| 15.302 | Source selection objective. | Protests against award. | Changed · 9% alike | 15 → 169 |
| 15.303 | Responsibilities. | Discovery of mistakes. | Changed · 6% alike | 211 → 27 |
| 15.304 | Evaluation factors and significant subfactors. | Defective certified cost or pricing data after award. | Changed · 5% alike | 712 → 1622 |
| 15.305 | Proposal evaluation. | Estimating systems. | Changed · 6% alike | 703 → 109 |
| 15.306 | Exchanges with offerors after receipt of proposals. | none | Not in the overhaul | 1314 → – |
| 15.307 | Proposal revisions. | none | Not in the overhaul | 116 → – |
| 15.308 | Source selection decision. | none | Not in the overhaul | 101 → – |
| 15.400 | Scope of subpart. | Scope of subpart. | Changed · 95% alike | 29 → 28 |
| 15.401 | Definitions. | Definitions. | Changed · 98% alike | 57 → 57 |
| 15.402 | Pricing policy. | General. | Changed · 51% alike | 440 → 232 |
| 15.403 | Obtaining certified cost or pricing data. | Obtaining cost or pricing data. | Same | 0 → 0 |
| 15.403-1 | Prohibition on obtaining certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35). | Data other than certified cost or pricing data. | Changed · 12% alike | 1320 → 708 |
| 15.403-2 | Other circumstances where certified cost or pricing data are not required. | Prohibitions on obtaining certified cost or pricing data. | Changed · 4% alike | 47 → 1218 |
| 15.403-3 | Requiring data other than certified cost or pricing data. | Certified cost or pricing data. | Changed · 7% alike | 847 → 752 |
| 15.403-4 | Requiring certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35). | Certificate of current cost or pricing data. | Changed · 12% alike | 809 → 500 |
| 15.403-5 | Instructions for submission of certified cost or pricing data and data other than certified cost or pricing data. | none | Not in the overhaul | 258 → – |
| 15.404 | Proposal analysis. | Cost and/or price analysis. | Changed · 0% alike | 0 → 287 |
| 15.404-1 | Proposal analysis techniques. | Price analysis. | Changed · 28% alike | 2546 → 481 |
| 15.404-2 | Data to support proposal analysis. | Cost analysis. | Changed · 7% alike | 909 → 411 |
| 15.404-3 | Subcontract pricing considerations. | Cost realism analysis. | Changed · 9% alike | 456 → 276 |
| 15.404-4 | Profit. | Technical cost or price analysis. | Changed · 4% alike | 1730 → 201 |
| 15.404-5 | none | Unit prices. | New number | – → 164 |
| 15.404-6 | none | Unbalanced pricing. | New number | – → 213 |
| 15.404-7 | none | Review and justification of pass-through contracts. | New number | – → 180 |
| 15.404-8 | none | Subcontract pricing considerations. | New number | – → 467 |
| 15.404-9 | none | Profit. | New number | – → 1489 |
| 15.405 | Price negotiation. | Special cost or pricing areas. | Changed · 0% alike | 369 → 0 |
| 15.405-1 | none | Inaccurate, incomplete, or noncurrent cost or pricing data. | New number | – → 99 |
| 15.405-2 | none | Make-or-buy programs. | New number Same heading as today's 15.407-2 | – → 359 |
| 15.405-3 | none | Forward pricing rate agreements. | New number Same heading as today's 15.407-3 | – → 200 |
| 15.405-4 | none | Should-cost review. | New number Same heading as today's 15.407-4 | – → 804 |
| 15.406 | Documentation. | Data to support proposal analysis. | Changed · 0% alike | 0 → 777 |
| 15.406-1 | Prenegotiation objectives. | none | Not in the overhaul Same heading at 15.408-1 | 132 → – |
| 15.406-2 | Certificate of current cost or pricing data. | none | Not in the overhaul | 540 → – |
| 15.406-3 | Documenting the negotiation. | none | Not in the overhaul Same heading at 15.408-2 | 444 → – |
| 15.407 | Special cost or pricing areas. | Price negotiation. | Changed · 0% alike | 0 → 301 |
| 15.407-1 | Defective certified cost or pricing data. | none | Not in the overhaul | 1720 → – |
| 15.407-2 | Make-or-buy programs. | none | Not in the overhaul Same heading at 15.405-2 | 1060 → – |
| 15.407-3 | Forward pricing rate agreements. | none | Not in the overhaul Same heading at 15.405-3 | 249 → – |
| 15.407-4 | Should-cost review. | none | Not in the overhaul Same heading at 15.105-6 | 852 → – |
| 15.407-5 | Estimating systems. | none | Not in the overhaul | 140 → – |
| 15.408 | Solicitation provisions and contract clauses. | Documentation. | Changed · 0% alike | 4305 → 0 |
| 15.408-1 | none | Prenegotiation objectives. | New number Same heading as today's 15.406-1 | – → 89 |
| 15.408-2 | none | Documenting the negotiation. | New number Same heading as today's 15.406-3 | – → 3301 |
| 15.500 | none | Scope of subpart. | New number | – → 18 |
| 15.501 | Definition. | Definitions. | Changed · 8% alike | 13 → 145 |
| 15.502 | Applicability. | General. | Changed · 2% alike | 52 → 374 |
| 15.503 | Notifications to unsuccessful offerors. | Preparing unsolicited proposals. | Changed · 0% alike | 538 → 0 |
| 15.503-1 | none | Scope of proposals. | New number | – → 167 |
| 15.503-2 | none | Content of proposals. | New number | – → 296 |
| 15.503-3 | none | Restricting use and disclosure of data. | New number | – → 232 |
| 15.504 | Award to successful offeror. | Receipt and initial review of unsolicited proposals. | Changed · 10% alike | 225 → 79 |
| 15.504-1 | none | Initial Review. | New number | – → 151 |
| 15.504-2 | none | Handling use and disclosure of data restrictions. | New number | – → 516 |
| 15.505 | Preaward debriefing of offerors. | Evaluation of unsolicited proposals. | Changed · 7% alike | 414 → 258 |
| 15.506 | Postaward debriefing of offerors. | Criteria for acceptance and negotiation of an unsolicited proposal. | Changed · 4% alike | 458 → 57 |
| 15.507 | Protests against award. | none | Not in the overhaul | 170 → – |
| 15.508 | Discovery of mistakes. | none | Not in the overhaul | 27 → – |
| 15.509 | Forms. | none | Not in the overhaul | 76 → – |
| 15.600 | Scope of subpart. | none | Not in the overhaul | 19 → – |
| 15.601 | Definitions. | none | Not in the overhaul | 145 → – |
| 15.602 | Policy. | none | Not in the overhaul | 72 → – |
| 15.603 | General. | none | Not in the overhaul | 228 → – |
| 15.604 | Agency points of contact. | none | Not in the overhaul | 198 → – |
| 15.605 | Content of unsolicited proposals. | none | Not in the overhaul | 298 → – |
| 15.606 | Agency procedures. | none | Not in the overhaul | 69 → – |
| 15.606-1 | Receipt and initial review. | none | Not in the overhaul | 159 → – |
| 15.606-2 | Evaluation. | none | Not in the overhaul | 161 → – |
| 15.607 | Criteria for acceptance and negotiation of an unsolicited proposal. | none | Not in the overhaul | 169 → – |
| 15.608 | Prohibitions. | none | Not in the overhaul | 120 → – |
| 15.609 | Limited use of data. | none | Not in the overhaul | 798 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress