The FAR overhaul, side by side
FAR Part 15: Contracting by Negotiation
Not in force. The overhaul text is the FAR Council's rewrite, which agencies adopt by class deviation while the rules are being made. It is not the regulation in force and can still change: today's FAR is what applies unless your contract or the agency's deviation says otherwise.
Today: 81 sections, 32,499 words (Part 15 as in force, eCFR as of Oct 29, 2026). Overhaul text: 91 sections, 28,441 words (on acquisition.gov ↗, issued Sep 30, 2025). By number: 1 the same, 44 changed, 36 not in the overhaul (10 with the same heading under another number), 46 new.
15.208: Not in the overhaul
Today: Submission, modification, revision, and withdrawal of proposals.
(a) Offerors are responsible for submitting proposals, and any revisions, and modifications, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. Offerors may use any transmission method authorized by the solicitation (i.e., regular mail, electronic commerce, or facsimile). If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposals are due.
(b)(1) Any proposal, modification, or revision, that is received at the designated Government office after the exact time specified for receipt of proposals is “late” and will not be considered unless it is received before award is made, the contracting officer determines that accepting the late proposal would not unduly delay the acquisition; and—
(i) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of proposals and was under the Government's control prior to the time set for receipt of proposals; or
(iii) It was the only proposal received.
(2) However, a late modification of an otherwise successful proposal, that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the Government office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation closing date, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Proposals may be withdrawn by written notice at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. The contracting officer must document the contract file when oral withdrawals are made. One copy of withdrawn proposals should be retained in the contract file (see 4.803(a)(10)). Extra copies of the withdrawn proposals may be destroyed or returned to the offeror at the offerors request. Where practicable, electronically transmitted proposals that are withdrawn must be purged from primary and backup data storage systems after a copy is made for the file. Extremely bulky proposals must only be returned at the offeror's request and expense.
(f) The contracting officer must promptly notify any offeror if its proposal, modification, or revision was received late, and must inform the offeror whether its proposal will be considered, unless contract award is imminent and the notice prescribed in 15.503(b) would suffice.
(g) Late proposals and modifications that are not considered must be held unopened, unless opened for identification, until after award and then retained with other unsuccessful proposals.
(h) If available, the following must be included in the contracting office files for each late proposal, modification, revision, or withdrawal:
(1) The date and hour of receipt.
(2) A statement regarding whether the proposal was considered for award, with supporting rationale.
(3) The envelope, wrapper, or other evidence of date of receipt.
Overhaul text
No section with this number.
Section by section
| Section | Today | Overhaul text | Status | Words |
|---|---|---|---|---|
| 15.000 | Scope of part. | Scope. | Changed · 35% alike | 28 → 46 |
| 15.001 | Definitions. | Definitions. | Changed · 75% alike | 136 → 149 |
| 15.002 | Types of negotiated acquisition. | Types of negotiated acquisition. | Changed · 47% alike | 94 → 121 |
| 15.100 | Scope of subpart. | Scope. | Changed · 17% alike | 27 → 32 |
| 15.101 | Best value continuum. | Early exchanges with industry. | Changed · 5% alike | 95 → 452 |
| 15.101-1 | Tradeoff process. | none | Not in the overhaul | 153 → – |
| 15.101-2 | Lowest price technically acceptable source selection process. | none | Not in the overhaul | 555 → – |
| 15.101-3 | Tiered evaluation of small business offers. | none | Not in the overhaul | 28 → – |
| 15.102 | Oral presentations. | Structuring a request for proposals. | Changed · 8% alike | 550 → 330 |
| 15.103 | none | Developing a competitive source selection approach. | New number | – → 82 |
| 15.103-1 | none | Tradeoff approach. | New number | – → 64 |
| 15.103-2 | none | Lowest price technically acceptable approach. | New number | – → 385 |
| 15.103-3 | none | Highest technically rated with a fair and reasonable price approach | New number | – → 238 |
| 15.103-4 | none | Phased acquisition. | New number | – → 101 |
| 15.104 | none | Establishing competitive evaluation factors and significant subfactors. | New number | – → 709 |
| 15.105 | none | Other considerations. | New number | – → 0 |
| 15.105-1 | none | Oral presentations. | New number | – → 76 |
| 15.105-2 | none | Negotiations disclosure. | New number | – → 50 |
| 15.105-3 | none | Limitation on tiered evaluations for multiple award contracts. | New number | – → 35 |
| 15.105-4 | none | Request for cost or pricing data. | New number | – → 261 |
| 15.105-5 | none | Make-or-buy decision. | New number | – → 515 |
| 15.105-6 | none | Should-cost review. | New number Same heading as today's 15.407-4 | – → 28 |
| 15.105-7 | none | Unit prices. | New number | – → 55 |
| 15.106 | none | Amending a request for proposal. | New number | – → 328 |
| 15.107 | none | Submission, modification, revision, and withdrawal of proposals. | New number Same heading as today's 15.208 | – → 593 |
| 15.108 | none | Receiving proposals. | New number | – → 143 |
| 15.109 | none | Uniform contract format. | New number | – → 74 |
| 15.109-1 | none | Part I - The Schedule. | New number | – → 317 |
| 15.109-2 | none | Part II - Contract Clauses. | New number Same heading as today's 15.204-3 | – → 55 |
| 15.109-3 | none | Part III - List of Documents, Exhibits, and Other Attachments. | New number Same heading as today's 15.204-4 | – → 37 |
| 15.109-4 | none | Part IV - Representations and Instructions. | New number Same heading as today's 15.204-5 | – → 155 |
| 15.110 | none | Solicitation provisions and contract clauses. | New number Same heading as today's 15.209 | – → 1609 |
| 15.200 | Scope of subpart. | Scope. | Changed · 35% alike | 36 → 15 |
| 15.201 | Exchanges with industry before receipt of proposals. | Source selection responsibilities. | Changed · 7% alike | 527 → 352 |
| 15.202 | Advisory multi-step process. | Evaluating competitive proposals. | Changed · 9% alike | 250 → 735 |
| 15.203 | Requests for proposals. | Competitive award without negotiation. | Changed · 6% alike | 566 → 64 |
| 15.204 | Contract format. | Competitive award with negotiation. | Changed · 0% alike | 93 → 0 |
| 15.204-1 | Uniform contract format. | Establishing a competitive range. | Changed · 12% alike | 108 → 139 |
| 15.204-2 | Part I—The Schedule. | Competitive negotiations. | Changed · 6% alike | 359 → 409 |
| 15.204-3 | Part II—Contract Clauses. | none | Not in the overhaul Same heading at 15.109-2 | 61 → – |
| 15.204-4 | Part III—List of Documents, Exhibits, and Other Attachments. | none | Not in the overhaul Same heading at 15.109-3 | 37 → – |
| 15.204-5 | Part IV—Representations and Instructions. | none | Not in the overhaul Same heading at 15.109-4 | 189 → – |
| 15.205 | Issuing solicitations. | Source selection decision. | Changed · 7% alike | 40 → 72 |
| 15.206 | Amending the solicitation. | Preaward notices and debriefings. | Changed · 5% alike | 305 → 69 |
| 15.206-1 | none | Preaward notices. | New number | – → 189 |
| 15.206-2 | none | Preaward debriefing. | New number | – → 411 |
| 15.207 | Handling proposals and information. | Award. | Changed · 0% alike | 195 → 0 |
| 15.207-1 | none | Award to successful offeror. | New number | – → 185 |
| 15.207-2 | none | Award notice. | New number | – → 249 |
| 15.208 | Submission, modification, revision, and withdrawal of proposals. | none | Not in the overhaul Same heading at 15.107 | 611 → – |
| 15.209 | Solicitation provisions and contract clauses. | none | Not in the overhaul Same heading at 15.110 | 509 → – |
| 15.210 | Forms. | none | Not in the overhaul | 90 → – |
| 15.300 | Scope of subpart. | Scope. | Changed · 17% alike | 17 → 64 |
| 15.301 | [Reserved] | Postaward debriefing of offerors. | Changed · 0% alike | 0 → 15 |
| 15.301-1 | none | Debriefing process. | New number | – → 597 |
| 15.301-2 | none | Opportunity for follow-up questions. | New number | – → 22 |
| 15.302 | Source selection objective. | Protests against award. | Changed · 9% alike | 15 → 169 |
| 15.303 | Responsibilities. | Discovery of mistakes. | Changed · 6% alike | 211 → 27 |
| 15.304 | Evaluation factors and significant subfactors. | Defective certified cost or pricing data after award. | Changed · 5% alike | 712 → 1622 |
| 15.305 | Proposal evaluation. | Estimating systems. | Changed · 6% alike | 703 → 109 |
| 15.306 | Exchanges with offerors after receipt of proposals. | none | Not in the overhaul | 1314 → – |
| 15.307 | Proposal revisions. | none | Not in the overhaul | 116 → – |
| 15.308 | Source selection decision. | none | Not in the overhaul | 101 → – |
| 15.400 | Scope of subpart. | Scope of subpart. | Changed · 95% alike | 29 → 28 |
| 15.401 | Definitions. | Definitions. | Changed · 98% alike | 57 → 57 |
| 15.402 | Pricing policy. | General. | Changed · 51% alike | 440 → 232 |
| 15.403 | Obtaining certified cost or pricing data. | Obtaining cost or pricing data. | Same | 0 → 0 |
| 15.403-1 | Prohibition on obtaining certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35). | Data other than certified cost or pricing data. | Changed · 12% alike | 1320 → 708 |
| 15.403-2 | Other circumstances where certified cost or pricing data are not required. | Prohibitions on obtaining certified cost or pricing data. | Changed · 4% alike | 47 → 1218 |
| 15.403-3 | Requiring data other than certified cost or pricing data. | Certified cost or pricing data. | Changed · 7% alike | 847 → 752 |
| 15.403-4 | Requiring certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35). | Certificate of current cost or pricing data. | Changed · 12% alike | 809 → 500 |
| 15.403-5 | Instructions for submission of certified cost or pricing data and data other than certified cost or pricing data. | none | Not in the overhaul | 258 → – |
| 15.404 | Proposal analysis. | Cost and/or price analysis. | Changed · 0% alike | 0 → 287 |
| 15.404-1 | Proposal analysis techniques. | Price analysis. | Changed · 28% alike | 2546 → 481 |
| 15.404-2 | Data to support proposal analysis. | Cost analysis. | Changed · 7% alike | 909 → 411 |
| 15.404-3 | Subcontract pricing considerations. | Cost realism analysis. | Changed · 9% alike | 456 → 276 |
| 15.404-4 | Profit. | Technical cost or price analysis. | Changed · 4% alike | 1730 → 201 |
| 15.404-5 | none | Unit prices. | New number | – → 164 |
| 15.404-6 | none | Unbalanced pricing. | New number | – → 213 |
| 15.404-7 | none | Review and justification of pass-through contracts. | New number | – → 180 |
| 15.404-8 | none | Subcontract pricing considerations. | New number | – → 467 |
| 15.404-9 | none | Profit. | New number | – → 1489 |
| 15.405 | Price negotiation. | Special cost or pricing areas. | Changed · 0% alike | 369 → 0 |
| 15.405-1 | none | Inaccurate, incomplete, or noncurrent cost or pricing data. | New number | – → 99 |
| 15.405-2 | none | Make-or-buy programs. | New number Same heading as today's 15.407-2 | – → 359 |
| 15.405-3 | none | Forward pricing rate agreements. | New number Same heading as today's 15.407-3 | – → 200 |
| 15.405-4 | none | Should-cost review. | New number Same heading as today's 15.407-4 | – → 804 |
| 15.406 | Documentation. | Data to support proposal analysis. | Changed · 0% alike | 0 → 777 |
| 15.406-1 | Prenegotiation objectives. | none | Not in the overhaul Same heading at 15.408-1 | 132 → – |
| 15.406-2 | Certificate of current cost or pricing data. | none | Not in the overhaul | 540 → – |
| 15.406-3 | Documenting the negotiation. | none | Not in the overhaul Same heading at 15.408-2 | 444 → – |
| 15.407 | Special cost or pricing areas. | Price negotiation. | Changed · 0% alike | 0 → 301 |
| 15.407-1 | Defective certified cost or pricing data. | none | Not in the overhaul | 1720 → – |
| 15.407-2 | Make-or-buy programs. | none | Not in the overhaul Same heading at 15.405-2 | 1060 → – |
| 15.407-3 | Forward pricing rate agreements. | none | Not in the overhaul Same heading at 15.405-3 | 249 → – |
| 15.407-4 | Should-cost review. | none | Not in the overhaul Same heading at 15.105-6 | 852 → – |
| 15.407-5 | Estimating systems. | none | Not in the overhaul | 140 → – |
| 15.408 | Solicitation provisions and contract clauses. | Documentation. | Changed · 0% alike | 4305 → 0 |
| 15.408-1 | none | Prenegotiation objectives. | New number Same heading as today's 15.406-1 | – → 89 |
| 15.408-2 | none | Documenting the negotiation. | New number Same heading as today's 15.406-3 | – → 3301 |
| 15.500 | none | Scope of subpart. | New number | – → 18 |
| 15.501 | Definition. | Definitions. | Changed · 8% alike | 13 → 145 |
| 15.502 | Applicability. | General. | Changed · 2% alike | 52 → 374 |
| 15.503 | Notifications to unsuccessful offerors. | Preparing unsolicited proposals. | Changed · 0% alike | 538 → 0 |
| 15.503-1 | none | Scope of proposals. | New number | – → 167 |
| 15.503-2 | none | Content of proposals. | New number | – → 296 |
| 15.503-3 | none | Restricting use and disclosure of data. | New number | – → 232 |
| 15.504 | Award to successful offeror. | Receipt and initial review of unsolicited proposals. | Changed · 10% alike | 225 → 79 |
| 15.504-1 | none | Initial Review. | New number | – → 151 |
| 15.504-2 | none | Handling use and disclosure of data restrictions. | New number | – → 516 |
| 15.505 | Preaward debriefing of offerors. | Evaluation of unsolicited proposals. | Changed · 7% alike | 414 → 258 |
| 15.506 | Postaward debriefing of offerors. | Criteria for acceptance and negotiation of an unsolicited proposal. | Changed · 4% alike | 458 → 57 |
| 15.507 | Protests against award. | none | Not in the overhaul | 170 → – |
| 15.508 | Discovery of mistakes. | none | Not in the overhaul | 27 → – |
| 15.509 | Forms. | none | Not in the overhaul | 76 → – |
| 15.600 | Scope of subpart. | none | Not in the overhaul | 19 → – |
| 15.601 | Definitions. | none | Not in the overhaul | 145 → – |
| 15.602 | Policy. | none | Not in the overhaul | 72 → – |
| 15.603 | General. | none | Not in the overhaul | 228 → – |
| 15.604 | Agency points of contact. | none | Not in the overhaul | 198 → – |
| 15.605 | Content of unsolicited proposals. | none | Not in the overhaul | 298 → – |
| 15.606 | Agency procedures. | none | Not in the overhaul | 69 → – |
| 15.606-1 | Receipt and initial review. | none | Not in the overhaul | 159 → – |
| 15.606-2 | Evaluation. | none | Not in the overhaul | 161 → – |
| 15.607 | Criteria for acceptance and negotiation of an unsolicited proposal. | none | Not in the overhaul | 169 → – |
| 15.608 | Prohibitions. | none | Not in the overhaul | 120 → – |
| 15.609 | Limited use of data. | none | Not in the overhaul | 798 → – |
- Sections are matched by number. The overhaul renumbers and merges a great deal, so "not in the overhaul" means the number is gone, not always that the rule is: its content may sit in another section, in a part's practitioner guide, or be dropped.
- "How alike" compares the two texts word for word (1.00 = the same words). It says how much was rewritten, not what the change means for a contract.
- Agencies adopt the overhaul by their own class deviations, some with changes: check the agency's deviation and the clauses in your contract.
- Not legal advice. FAR rule changes in progress